RIDGE -v- BGC CONSTRUCTION PTY LTD [2007] WADC 117
| DISTRICT COURT OF WESTERN AUSTRALIA | Citation No: | [2007] WADC 117 | |
| Case No: | CIV:2179/2005 | 21, 22 & 25 JUNE 2007 | |
| Coram: | GOETZE DCJ | 6/07/07 | |
| PERTH | |||
| 21 | Judgment Part: | 1 of 1 | |
| Result: | Judgment for plaintiff in the sum of $183,885.21 | ||
| PDF Version |
| Parties: | PETER CARLTON RICHARD RIDGE BGC CONSTRUCTION PTY LTD (ACN 008 783 248) |
Catchwords: | Damages Contract to build domestic home Repudiation of contract by builder Consumer requiring to seek alternative builder against background of increasing building prices Approach to assessment of damages |
Legislation: | Nil |
Case References: | Alcoa Minerals of Jamaica Inc v Herbert Broderick, [2000] BLR 282 Bellgrove v Eldridge (1954) 90 CLR 613 Bevan Investments Ltd v Blackhall & Struthers (No 2) [1978] 2 NZLR 97 Burns v M A N Automotive (Aust) Pty Ltd (1986) 161 CLR 653 Dodd Properties (Kent) Ltd v Canterbury City Council [1980] 1 All ER 928 Glenmont Investments v O'Loughlin (No 2) (2000) 79 SASR 185 Hadley v Baxendale (1854) 9 Exch 341 McKay & Anor v Hudson & Ors [2001] WASCA 387 Radford v De Froberville [1978] 1 All ER 33 Woodward Pty Ltd v Kelleher, unreported; NSWCA; BC8902118; 30 May 1989 |
JURISDICTION : DISTRICT COURT OF WESTERN AUSTRALIA
- IN CIVIL
- Plaintiff
AND
BGC CONSTRUCTION PTY LTD (ACN 008 783 248)
Defendant
Catchwords:
Damages - Contract to build domestic home - Repudiation of contract by builder - Consumer requiring to seek alternative builder against background of increasing building prices - Approach to assessment of damages
Legislation:
Nil
Result:
Judgment for plaintiff in the sum of $183,885.21
(Page 2)
Representation:
Counsel:
Plaintiff : Mr I A Morison
Defendant : Mr J R B Ley
Solicitors:
Plaintiff : Solomon Bros
Defendant : Hotchin Hanly
Case(s) referred to in judgment(s):
Alcoa Minerals of Jamaica Inc v Herbert Broderick, [2000] BLR 282
Bellgrove v Eldridge (1954) 90 CLR 613
Bevan Investments Ltd v Blackhall & Struthers (No 2) [1978] 2 NZLR 97
Burns v M A N Automotive (Aust) Pty Ltd (1986) 161 CLR 653
Dodd Properties (Kent) Ltd v Canterbury City Council [1980] 1 All ER 928
Glenmont Investments v O'Loughlin (No 2) (2000) 79 SASR 185
Hadley v Baxendale (1854) 9 Exch 341
McKay & Anor v Hudson & Ors [2001] WASCA 387
Radford v De Froberville [1978] 1 All ER 33
Woodward Pty Ltd v Kelleher, unreported; NSWCA; BC8902118; 30 May 1989
(Page 3)
- GOETZE DCJ:
Introduction
1 Between February 2004 and June 2005, the plaintiff negotiated with the defendant to construct a house on the plaintiff's vacant lot adjacent to a canal at Halls Head, Mandurah.
2 The plaintiff intended that following the completion of construction by the defendant and…
Continue reading Ridge v BGC Construction Pty Ltd
Sign in free to access the full text
- AGLC
- Ridge v BGC Construction Pty Ltd [2007] WADC 117
- Case
- [2007] WADC 117
- Decision Date
CaseChat Overview and Summary
The court had to determine the appropriate measure of damages for the plaintiff's loss. Specifically, the legal issue was whether the damages should be assessed based on the difference in cost between the original and replacement builders, or if there were other factors that should be considered in determining the quantum of damages. The court also needed to consider whether the increasing building prices due to market conditions should impact the assessment of damages.
The court held that the appropriate measure of damages was the difference in cost between the original and replacement builders. The court noted that the plaintiff had taken reasonable steps to mitigate their loss by engaging another builder to complete the project. The court rejected the argument that increasing building prices should be a factor in assessing damages, as this would effectively allow the builder to benefit from market fluctuations. The court concluded that the plaintiff was entitled to damages in the amount of $183,885.21, which represented the difference in cost between the two builders. This amount was deemed a reasonable and just compensation for the loss suffered by the plaintiff as a result of the builder's repudiation of the contract.
Orders
Orders of the court
Judgment for plaintiff in the sum of $183,885.21
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.