SUPREME COURT OF QUEENSLAND
CITATION:
RHG Construction Fitout and Maintenance Pty Ltd v Kangaroo Point Developments MP Property Pty Ltd & Ors [2021] QCA 117
PARTIES:
RHG CONSTRUCTION FITOUT AND MAINTENANCE PTY LTD
ABN 67 159 703 349
(appellant)
v
KANGAROO POINT DEVELOPMENTS MP PROPERTY PTY LTD ATF KANGAROO POINT DEVELOPMENTS
MP PROPERTY UNIT TRUST
ABN 80 283 808 292
(first respondent)
CHERIDEN FARTHING (ADJUDICATION REGISTRAR)
(second respondent)
NOEL EVAN JENSEN (ADJUDICATOR J1057076)
(third respondent)FILE NO/S:
Appeal No 2738 of 2021
SC No 13394 of 2020DIVISION:
Court of Appeal
PROCEEDING:
General Civil Appeal
ORIGINATING COURT:
Supreme Court at Brisbane – [2021] QSC 30 (Dalton J)DELIVERED ON:
28 May 2021
DELIVERED AT:
Brisbane
HEARING DATE:
12 April 2021
JUDGES:
Sofronoff P and McMurdo and Mullins JJA
ORDER:
Appeal allowed.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – RECOVERY ON QUANTUM MERUIT – CERTIFICATES – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – ADJUDICATION OF PAYMENT CLAIMS – where the appellant was a contractor builder who served a payment claim for a progress payment upon the first respondent principal under a standard form “AS 4902-2000” Contract – where the appellant also submitted a payment claim to the Superintendent under the Contract – where the Superintendent issued a payment schedule and certificate evidencing their assessment of the moneys due to the appellant and first respondent – where the first respondent’s solicitors disputed the Superintendent’s issued payment schedule as a valid “payment schedule” under the Building Industry Fairness (Security of Payment) Act 2017 (the Act) – where the first respondent’s solicitors issued a second payment schedule outlining that they did not owe any moneys to the appellant – where the appellant elected to begin an adjudication under the Act – where the adjudicator accepted that the appellant rightly identified the Superintendent’s payment schedule as a valid payment schedule under s 69 of the Act and concluded that the first respondent owed moneys to the appellant with interest – where the first respondent originated proceedings in the Supreme Court which declared the adjudication decision void on the basis that it lacked jurisdiction as the appellant did not identify the relevant payment schedule as required by s 79(2)(c) of the Act – whether the appellant properly identified the Superintendent’s payment schedule instead of the first respondent’s solicitors’ payment schedule as the relevant “payment schedule” for adjudication under the Act – whether the second payment schedule issued by the first respondent’s solicitors was served within the statutory delivery period under s 76 of the Act
Building and Construction Industry Payments Act 2004 (Qld) (repealed)
Building Industry Fairness (Security of Payment) Act 2017 (Qld), s 69, s 75, s 76, s 78, s 79, s 200COUNSEL:
D Clothier QC, with F J Chen, for the appellant
M H Hindman QC, with M J Steele, for the respondentSOLICITORS:
CDI Lawyers as town agent for Jackson McDonald for the appellant
McInnes Wilson Lawyers for the first respondent
SOFRONOFF P:
Keep reading for free
Create a free CaseChat account to read RHG Construction Fitout and Maintenance Pty Ltd v Kangaroo P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] QCA 117
- Decision Date
CaseChat Overview and Summary
The court examined the statutory framework provided by the Building Industry Fairness (Security of Payment) Act 2017, particularly focusing on the requirements for the identification of a payment schedule and the timelines for issuing payment schedules. The court determined that RHG Construction correctly identified the Superintendent’s payment schedule as the relevant document for adjudication, rather than the second payment schedule issued by the first respondent's solicitors. The court also found that the second payment schedule was not served within the statutory period, thereby invalidating it as a basis for disputing the adjudication decision. Consequently, the court concluded that the adjudicator had jurisdiction and correctly found that the first respondent owed moneys to RHG Construction with interest.
The appeal was allowed, and the decision of the Supreme Court was overturned. The adjudicator's decision was reinstated, affirming that the first respondent owed moneys to RHG Construction with interest as determined in the adjudication. This outcome underscores the importance of adhering to statutory timelines and correctly identifying the relevant payment schedule in disputes under the Building Industry Fairness (Security of Payment) Act 2017. The final orders of the court were to allow the appeal and reinstate the adjudicator's decision, compelling the first respondent to pay the amount owed to the appellant along with interest.
Orders
Orders of the court
Appeal allowed.
Background
Background to the litigation
The first respondent's solicitors disputed the validity of the Superintendent's payment schedule as a "payment schedule" under the Building Industry Fairness (Security of Payment) Act 2017 (the Act). In response, the first respondent's solicitors issued a second payment schedule, stating that no moneys were owed to the appellant. Upon this dispute, the appellant elected to initiate adjudication proceedings under the Act. The adjudicator found that the Superintendent's payment schedule was a valid payment schedule under s 69 of the Act and determined that the first respondent owed the appellant moneys, including interest.
The first respondent initiated proceedings in the Supreme Court, challenging the validity of the adjudication decision. The Supreme Court declared the adjudication decision void, holding that the appellant had failed to identify the relevant payment schedule as required by s 79(2)(c) of the Act. The first respondent argued that the appellant should have identified their solicitors' second payment schedule as the relevant payment schedule for adjudication purposes.
The case initially arose when RHG Construction Fitout and Maintenance Pty Ltd submitted a payment claim to Kangaroo Point Developments MP Property Pty Ltd, the principal under a construction contract. Following the issuance of a payment schedule by the Superintendent, the first respondent's solicitors disputed the validity of this payment schedule. This dispute led to the appellant initiating adjudication proceedings under the Building Industry Fairness (Security of Payment) Act 2017. The adjudicator ruled in favour of the appellant, determining that the first respondent owed the appellant moneys.
The first respondent challenged the validity of the adjudication decision in the Supreme Court, arguing that the appellant had not correctly identified the relevant payment schedule as required by s 79(2)(c) of the Act. The Supreme Court agreed with the first respondent and declared the adjudication decision void. Dissatisfied with this outcome, the appellant appealed to a higher court, seeking to overturn the Supreme Court's decision.
Decision
Reasons for decision
1. Whether the appellant properly identified the Superintendent's payment schedule instead of the first respondent's solicitors' payment schedule as the relevant "payment schedule" for adjudication under the Act.
2. Whether the second payment schedule issued by the first respondent's solicitors was served within the statutory delivery period under s 76 of the Act.
Held
1. The court held that the appellant properly identified the Superintendent's payment schedule instead of the first respondent's solicitors' payment schedule as the relevant "payment schedule" for adjudication under the Act.
2. The court held that the second payment schedule issued by the first respondent's solicitors was not served within the statutory delivery period under s 76 of the Act.
Ratio Decidendi
Legal Principle Established
The court considered whether the appellant had properly identified the Superintendent's payment schedule instead of the first respondent's solicitors' payment schedule as the relevant "payment schedule" for adjudication under the Act. The court held that the appellant was entitled to rely on the Superintendent's payment schedule as the relevant payment schedule for the purposes of the adjudication, given the Superintendent was the person with the contractual responsibility for issuing payment schedules under the Contract. The court reasoned that the first respondent's solicitors' payment schedule, which was issued in dispute of the Superintendent's payment schedule, did not constitute a valid payment schedule under s 69 of the Act. Consequently, the appellant's identification of the Superintendent's payment schedule was proper, and the adjudication decision was not void for lack of jurisdiction.
The court also examined whether the second payment schedule issued by the first respondent's solicitors was served within the statutory delivery period under s 76 of the Act. The court determined that the second payment schedule was not served within the statutory period, as it was issued after the statutory period had expired. The court emphasised the importance of strict compliance with the statutory delivery period for payment schedules under the Act. As the second payment schedule was not served within the statutory period, it did not constitute a valid payment schedule for the purposes of the adjudication, and the adjudicator's decision to rely on the Superintendent's payment schedule was correct. The court's decision to allow the appeal and set aside the Supreme Court's declaration that the adjudication decision was void was based on these findings. The ratio decidendi of this case is that a contractor builder may rely on a payment schedule issued by the Superintendent as the relevant payment schedule for adjudication purposes under the Act, provided it is properly identified and served within the statutory delivery period.