Reed v Chief Executive, Department of Natural Resources and Mines

Link copied
Case Copied 43 min read

LAND COURT OF QUEENSLAND

CITATION:Reed v Department of Natural Resources and Mines & Ors (No. 2) [2014] QLC 6

PARTIES:Garry Arthur Reed

(appellant)

v

Chief Executive, Department of Natural Resources and Mines

(first respondent)

and

QCoal Sonoma Pty Ltd,
CSE Sonoma Pty Ltd,
JS Sonoma Pty Ltd and
Watami (Qld) Pty Ltd
(second respondents)

FILE NO:WAA114-13

DIVISION:General Division

PROCEEDING:  Appeal under the Water Act 2000

DELIVERED ON:                  11 February 2014

DELIVERED AT:                   Brisbane

HEARD ON:  8, 9 and 10 January 2014

HEARD AT:Brisbane

MEMBER:WA Isdale

ORDERS:1.    The appeal is dismissed.

2.The review decision is confirmed.

3.Any application for costs is to be filed and served within 15 business days of the publication of these reasons and any reply is to be filed and served within 15 business days of any such application.

CATCHWORDS:                  Appeal against review decision ― water licence

Water Act 2000, ss 210, 211, 880, 882

Environmental Protection Act 1994

APPEARANCES:                  D Yarrow instructed by p&e Law for the appellant

AJ MacSporran and DA Silvester instructed by Crown Solicitor for the first respondent

MF Johnston instructed by McCullough Robertson for the second respondents

Background

  1. In QCoal Sonoma Pty Ltd (Principal Holder) & Ors v Garry Reed & Ors [2012] QLC 50 this Court considered an amendment application to a draft environmental authority under the Environmental Protection Act 1994. In the present proceedings under the Water Act 2000 (the Act) the appellant is appealing a reviewer’s decision dated 25 February 2013 substantially upholding a decision to permit the diversion of Coral Creek so as to allow coal mining where the creek was naturally located, near Collinsville.

  2. Coral Creek is an ephemeral creek that flows into Pelican Creek in the catchment of the Burdekin River. The existing reach of the creek proposed to be diverted is about 1,280 m. It will instead run in a proposed diversion channel 1,503 m long. The diversion has been designed to withstand an Annual Recurrence Interval (ARI) 100 year flow event and can accommodate a 25,000 year ARI flow. The diversion is designed to minimise the amount of earthworks required and is to be aligned with a straight stretch of Coral Creek to reduce erosion. The greater length of the diversion, with its bed slope 0.02% less than the existing reach of Coral Creek, is planned to reduce flow velocity and the potential for erosion.[1]

    [1]     Ex 8 Affidavit of Ross Wayne Krebs, maker of the review decision appealed against.

The appeal

  1. The grounds of appeal are set out in the Further Amended Grounds of Appeal in the following terms:

    1.    The review decision granting the licence to vary the course of Coral Creek should be set aside because:

    (a)the second respondents’ hydraulic modelling is unreliable in that it is not based on empirical data, or the application of scientifically adequate modelling techniques;

    (b)in the absence of reliable hydraulic modelling:

    (i) the Court cannot be satisfied that the interference with the flow of water under the proposed licence is consistent…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Reed v Chief Executive, Department of Natural Resources and... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2014] QLC 6
Decision Date

CaseChat Overview and Summary

The case of Reed v Chief Executive, Department of Natural Resources and Mines involved an appeal against a decision to amend the conditions of a watercourse diversion licence. The appellant contested the decision made by the Chief Executive of the Department of Natural Resources and Mines regarding the modification of the licence conditions, specifically the addition of a new monitoring requirement for geomorphic and hydrogeological conditions. The matter was brought before the court for judicial review, with the appellant arguing against the appropriateness and necessity of the amended conditions.

The court was tasked with determining whether the decision to amend the licence conditions was lawful, reasonable, and properly aligned with the criteria set out in the relevant legislation and guidelines. This included assessing whether the decision was supported by the evidence presented and whether it adhered to the statutory framework and departmental guidelines governing watercourse diversions. Furthermore, the court had to consider whether the amended conditions were proportionate and necessary for the protection of the environment and the sustainable management of water resources.

In delivering its judgment, the court examined the evidence presented, including the affidavits of the original decision maker and the reviewer, as well as the relevant statutory provisions and departmental guidelines. The court held that the decision to amend the licence conditions was lawful and reasonable. It found that the additional monitoring requirements were necessary to ensure the proper management of the watercourse diversion and to protect the environmental integrity of the area. The court also concluded that the decision was in accordance with the applicable guidelines and statutory criteria. The appeal was thus dismissed, affirming the decision to amend the licence conditions.

As a result of the court's decision, the amended conditions for the watercourse diversion licence, including the additional monitoring requirements, were upheld. The appellant's appeal was dismissed, and the decision of the Chief Executive to amend the licence conditions was affirmed. The court's ruling reinforced the importance of adhering to statutory and guideline frameworks in making decisions that balance environmental protection with the needs of the mining industry.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

It was not in dispute that the Court is required to apply the Act to the material before the decision maker as supplemented by evidence presented at the hearing of the appeal. The 2,565 page affidavit of the original decision maker is before the Court as exhibit 7 and the 286 page affidavit of the maker of the review decision is exhibit 8. It is from that review decision that this appeal is brought. Although supporting the original decision, the decision on review added an amended condition for monitoring the performance of the diversion by way of an additional requirement, the third dot point, in clause 4(b) which governs the performance report. The relevant portion of the review decision is in the following form:“Reasons for the internal review decisionHaving regard to the material and findings referred to above including the investigation and decision making with regard to the original application. I have decided that the amending of this authority, through an amended Schedule B condition 4 should proceed.The decision to strengthen the Schedule B condition 4 relating to performance monitoring evaluation and adaptive management has been influenced by the additional evidence presented in the more recently provided submissions. These submissions more comprehensively deal with matters around groundwater, hydraulic and geomorphic conditions. Schedule B condition 4, as amended, places additional obligations on the licensee in terms of performance monitoring and reporting relating to geomorphic and hydrogeological conditions.The amended conditions (Schedule B condition 4) is as follows:4. a) The licensee is required to monitor the performance of the diversion by way of a performance report prepared by a registered professional engineer (RPEQ) and informed by advice from suitably qualified professionals in regard to geomorphic and hydrogeological conditions at the following times: By s 211 of the Act, if the chief executive is satisfied, having applied the criteria in s 210, that the application should be granted, in whole or in part, it must be granted, with or without conditions. If not so satisfied, the chief executive must refuse the application. A departmental guideline “Watercourse Diversions – Central Queensland Mining Industry” found at page 283 and onwards of exhibit 7, is in existence. It is expressed to be used when, inter alia, assessing applications by mining companies for authorisations for watercourse diversions. It was not suggested by any party that the Court should do other than apply this guideline. Indeed, its terms were of some importance to the case put for the appellant. The purpose of the guideline is expressed to be to summarise the design criteria against which applications will be assessed as well as to direct attention to the information required to accompany applications for authorisation to divert watercourses. It notes that in the Bowen Basin, coal deposits frequently extend beneath creeks and rivers and that diverting those streams may be a viable option where it can be adequately managed. The guideline notes that in the past, diversions were often engineered to suit short term needs and that physical and environmental problems required a longer-term view. The guideline states that:“In granting approvals for the diversion of watercourses the Department is attempting to achieve a diversion structure that appears and functions as a natural feature in the landscape largely indistinguishable from the pre-existing natural watercourse.”

Ratio Decidendi

Legal principle established