QCoal Sonoma Pty Ltd (Principal Holder) v Reed (No. 3)

Link copied
Case Copied 20 min read

LAND COURT OF QUEENSLAND

CITATION:QCoal Sonoma Pty Ltd (Principal Holder) & Ors v Garry Reed & Ors (No. 3) [2012] QLC 0050

PARTIES:QCoal Sonoma Pty Ltd, Cliffs Australia Coal Pty Ltd, CSC Sonoma Pty Ltd, JS Sonoma Pty Ltd and Watami (Qld) Pty Ltd

(applicants)

v.

Garry Reed, Greg James, Brett Murphy, Michael Lucas, Cynthia Jean Winston, Carol Cosentino, Carole Denise Wyper, Bill Wyper, Patricia Julien and Whitsunday Regional Council

(respondents)

and

Chief Executive, Department of Environment and Heritage Protection
(statutory party)

FILE NO:EPA1002-11

DIVISION:General Division

PROCEEDING:  Amendment Application for environmental authority

DELIVERED ON:                  19 September 2012

DELIVERED AT:                   Brisbane

HEARD ON:  23 August 2012

HEARD AT:Brisbane

MEMBER:Mr WA Isdale

ORDERS:1.  I recommend to the Honourable the Minister for Environment and Heritage Protection that Environmental Authority (Mining Activities) Draft Permit Number MIN100385405-Sonoma Coal Mine be issued with the following variations to the conditions in the draft:

That condition F28 be amended from:

F28Progressive rehabilitation must commence within 2 years when areas become available within the operational land.

to

F28Progressive rehabilitation must commence within two years when areas become available within the operational land except in the case of areas affected by stream diversion where it must commence as soon as practicable and not later than within two years of when areas become available for rehabilitation.

That condition F30 be amended from:

F30Complete an investigation into the rehabilitation of disturbed areas and submit a report to the administering authority proposing acceptance criteria to meet the outcomes in Table 19: Final land use and rehabilitation approval schedule and Table 20: Landform Design - unconsolidated material by 30 June 2015.

to

F30Complete an investigation into the rehabilitation of disturbed areas and submit a report to the administering authority proposing acceptance criteria and rehabilitation methods to meet the outcomes in Table 19: Final land use and rehabilitation approval schedule and Table 20: Landform Design - unconsolidated material by 30 June 2015.”

2.  I direct that the Registrar of the Land Court send a copy of these reasons to the Honourable Andrew Powell MP, Minister for Environment and Heritage Protection.

CATCHWORDS:                  OBJECTIONS DECISION ― DRAFT ENVIRONMENTAL AUTHORITY ― VARIATIONS TO CONDITIONS

Environmental Protection Act 1994, ss 216, 219, 222, 223, 251(4)
Water Act 2000

Xstrata Coal Queensland Pty Ltd & Ors v Friends of the Earth-Brisbane Co-Op Ltd & Ors [2012] QLC 013

APPEARANCES:                  Mr D Kelly SC and Mr M Johnson instructed by McCullough Robertson solicitors for the applicants

Ms P J Hay and Mr D Stevenson instructed by Environmental Defender’s Office of North Queensland Inc for the respondent, Garry Reed
Mr P Brown, instructed by Ms LJ Hoult, for the Department of Environment and Heritage Protection, the statutory party

Background

  1. By a Notice dated 19 December 2011 and filed on 20 December 2011 the statutory party, the Department of Environment and Heritage Protection referred an environmental authority (mining lease) amendment application to this Court. The statutory party took this step in accordance with s.219…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read QCoal Sonoma Pty Ltd (Principal Holder) v Reed (No. 3) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2012] QLC 50
Decision Date

CaseChat Overview and Summary

In the matter of the Environmental Protection Act 1994, QCoal Sonoma Pty Ltd applied for an amendment to an existing environmental authority that governs its mining activities in Coral Creek. The Department of Environment and Heritage Protection referred the matter to the court for an objections decision under s.219 of the Act. The statutory party, pursuant to s.223 of the Act, required the Court to consider the application documents, relevant regulatory requirements, standard criteria, the status of any application under the Mineral Resources Act for each relevant mining tenement, and each current objection. The primary objection was raised by the level 2 objector, Mr Reed. The Court was required to decide whether the application should be granted, granted with conditions, or refused.

The Court considered the objections raised by Mr Reed and the submissions provided by the parties. It was noted that the draft amended EA did not authorise the diversion of Coral Creek or any other watercourse, as that would be a separate matter for an application under the Water Act 2000. The Court held that the objections raised by Mr Reed did not establish that the application should be refused, and that the draft amended EA would regulate the environmental impacts of mining activities in the area where the creek is proposed to be diverted, if that diversion is authorised under the Water Act 2000. The Court concluded that the application should be granted on the basis of the draft amended EA.

The Court recommended to the EPA Minister that the application be granted on the basis of the draft amended EA. The Court's recommendation was based on the consideration of the application documents, relevant regulatory requirements, standard criteria, and the objections raised by Mr Reed. The Court held that the objections did not establish that the application should be refused, and that the draft amended EA would regulate the environmental impacts of mining activities in the area where the creek is proposed to be diverted, if that diversion is authorised under the Water Act 2000. The Court's recommendation was made in accordance with s.222 of the Act.

The Court's final orders were that the application be granted on the basis of the draft amended EA, and that the recommendation be made to the EPA Minister. The Court's recommendation was based on its consideration of the application documents, relevant regulatory requirements, standard criteria, and the objections raised by Mr Reed. The Court held that the objections did not establish that the application should be refused, and that the draft amended EA would regulate the environmental impacts of mining activities in the area where the creek is proposed to be diverted, if that diversion is authorised under the Water Act 2000. The Court's final orders were made in accordance with s.222 of the Act.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

By a Notice dated 19 December 2011 and filed on 20 December 2011 the statutory party, the Department of Environment and Heritage Protection referred an environmental authority (mining lease) amendment application to this Court. The statutory party took this step in accordance with s.219 of the Environmental Protection Act 1994 (the Act). The Court is required by the Act to make an objections decision under Subdivision 1 of Division 7 of Part 6 of Chapter 5 of the Act. The decision is made after an objections decision hearing. The Act requires that the objections decision for the application must be a recommendation to the “EPA Minister”, the Minister for the time being administering the Act, the Minister for Environment and Heritage Protection, the Honourable Andrew Powell MP (the Minister). Section 222 of the Act provides that the objections decision for the application must be that:“(a) the application be granted on the basis of the draft environmental authority for the application; or(b) the application be granted, but on stated conditions that are different to the conditions in the draft; or(c) the application be refused.”Section 223 is in the following form:“223 Matters to be considered for objections decisionIn making the objections decision for the application, the Land Court must consider the following—(a) the application documents for the application;(b) any relevant regulatory requirement;(c) the standard criteria;(d) to the extent the application relates to mining activities in a wild river area—the wild river declaration for the area;(e) each current objection;(f) any suitability report obtained for the application;(g) the status of any application under the Mineral Resources Act for each relevant mining tenement.” The Sonoma coal mine, about 6 km south of Collinsville operates with an existing Environmental Authority (EA), MIN 100385405. QCoal Sonoma Pty Ltd has applied, as the principal applicant, to amend the EA which prevents mining activities within 30 m of the top of the high bank of Coral Creek. The applicants propose to divert 1280 m of the creek in order to extract coal from beneath where the creek presently runs, hence the application to amend the EA. After public notice of the proposal, the statutory party received the present objections and referred them to the Court. The parties have provided written submissions to assist the Court and the applicants and level 2 objector provided oral submissions in addition. The applicants no longer rely on the material that was filed in response to Mr Reed’s material, so the Court can have no regard to that. The draft amended EA does not authorise the diversion of Coral Creek or any other watercourse. That will be a separate matter for an application under the Water Act 2000 and is not relevant for present purposes.[1] The draft amended EA would regulate the environmental impacts of mining activities in the area where the creek is proposed to be diverted, if that diversion is authorised under the Water Act 2000.[1] Xstrata Coal Queensland Pty Ltd & Ors v Friends of the Earth-Brisbane Co-Op Ltd & Ors [2012] QLC 013, [79].

Ratio Decidendi

Legal principle established