Redpath Contract Services Pty Ltd v Anglo Coal (Grosvenor Management) Pty Ltd

Link copied
Case Copied 32 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Redpath Contract Services Pty Ltd v Anglo Coal (Grosvenor Management) Pty Ltd [2016] QSC 313

PARTIES:

In BS 11338/16:

REDPATH CONTRACT SERVICES PTY LTD (ABN 96 133 126 904)
(applicant)
v
ANGLO COAL (GROSVENOR MANAGEMENT) PTY LTD (ABN 16 153 794 122)

(respondent)

In BS 11418/16:

ANGLO COAL (GROSVENOR MANAGEMENT) PTY LTD (ACN 153 794 122)
(applicant)

v          
REDPATH CONTRACT SERVICES PTY LTD (ACN 133 126 904)

(respondent)

DELIVERED ON:

22 December 2016

DELIVERED AT:

Brisbane

HEARING DATE:

17 November 2016

JUDGE:

Jackson J

ORDER:

The order of the court is that:

1.    The originating application in proceeding number 11418/16 is dismissed.

2.    In proceeding number 11338/16 it is declared that there is no agreement between Redpath Contract Services Pty Ltd and Anglo Coal (Grosvenor Management) Pty Ltd selecting Mr Graham Easton as Expert pursuant to general condition 56.6(c) of the Contract for Major Works numbered 17305 H339205 AA030 dated 6 February 2013.

3.    The originating application in proceeding number 11338/16 is otherwise adjourned to 13 February 2017.

CATCHWORDS:

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – where the parties agreed to refer disputes for expert determination under the contract and negotiated as to which expert to appoint – where by correspondence Redpath stated it was “in principle” willing to appoint a particular expert proposed by Anglo subject to his availability, and drafted a letter enquiring as to his availability over the next four to six months – where the letter was settled by both parties, but after a delay of several months in sending it, the proposed expert advised that he was not available for nine months – whether there was a concluded agreement to appoint the expert – whether any condition that the proposed expert be reasonably available was satisfied – whether there was an implied obligation to act reasonably – whether Redpath acted unreasonably in rejecting the expert due to his availability

1144 Nepean Highway Pty Ltd v Abnote Australasia Pty Ltd (2009) 26 VR 551; [2009] VSCA 308, considered
Australian Laboratory Services Pty Ltd v HRL Ltd [2012] QSC 236, considered
Belvino Investments No 2 Pty Ltd v Australian Vintage Ltd [2014] NSWSC 978, cited
Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd (1982) 149 CLR 600; [1982] HCA 53, considered
Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64; [1991] HCA 54, cited
Godfrey Constructions Pty Ltd v Kanangra Park Pty Ltd (1972) 128 CLR 529; [1972] HCA 36, cited
Macquarie International Health Clinic Pty Ltd v Sydney South West Area Health Service (2010) 15 BPR 28,563; [2010] NSWCA 268, cited
Meehan v Jones (1982) 149 CLR 571; [1982] HCA 52, cited
Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537; [1982] HCA 29, cited
Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Redpath Contract Services Pty Ltd v Anglo Coal (Grosvenor Ma... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2016] QSC 313
Decision Date

CaseChat Overview and Summary

Redpath Contract Services Pty Ltd sought a declaration in the Supreme Court of New South Wales that Anglo Coal (Grosvenor Management) Pty Ltd had agreed to appoint a particular expert to determine a dispute between the parties. The contract between the parties included a clause which required that any disputes be referred to an expert for determination. The parties had agreed to refer a dispute to an expert, but had not been able to agree on which expert to appoint. Redpath proposed an expert and the parties settled a letter that Redpath would send to the expert to enquire about his availability over the next four to six months. The letter was delayed and when it was sent, the expert said that he was not available for nine months. Redpath rejected the expert and appointed a different one. Anglo argued that the parties had agreed to appoint the expert proposed by Redpath, subject to his availability, and that Redpath had acted unreasonably in rejecting the expert when he was not available for only a slightly longer period than agreed.

The court was required to decide whether there was a concluded agreement to appoint the expert and whether Redpath acted reasonably in rejecting the expert. The court also had to decide whether there was an implied obligation to act reasonably in the agreement to appoint an expert. The court found that there was no concluded agreement to appoint the expert because the parties had not agreed to a condition that the expert be reasonably available. The court also found that there was no implied obligation to act reasonably in the agreement to appoint an expert. The court found that Redpath did not act unreasonably in rejecting the expert because the expert was not available for a significantly longer period than the parties had agreed.

The orders of the court were that the originating application in proceeding number 11418/16 was dismissed, that there was no agreement between Redpath and Anglo to appoint the expert proposed by Redpath, and that the originating application in proceeding number 11338/16 was adjourned to a later date.

Orders

Orders of the court

The order of the court is that:

1. The originating application in proceeding number 11418/16 is dismissed.

2. In proceeding number 11338/16 it is declared that there is no agreement between Redpath Contract Services Pty Ltd and Anglo Coal (Grosvenor Management) Pty Ltd selecting Mr Graham Easton as Expert pursuant to general condition 56.6(c) of the Contract for Major Works numbered 17305 H339205 AA030 dated 6 February 2013.

3. The originating application in proceeding number 11338/16 is otherwise adjourned to 13 February 2017.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established