Redpath Contract Services Pty Ltd v Anglo Coal (Grosvenor Management) Pty Ltd

Link copied
Case Copied 32 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Redpath Contract Services Pty Ltd v Anglo Coal (Grosvenor Management) Pty Ltd [2016] QSC 313

PARTIES:

In BS 11338/16:

REDPATH CONTRACT SERVICES PTY LTD (ABN 96 133 126 904)
(applicant)
v
ANGLO COAL (GROSVENOR MANAGEMENT) PTY LTD (ABN 16 153 794 122)

(respondent)

In BS 11418/16:

ANGLO COAL (GROSVENOR MANAGEMENT) PTY LTD (ACN 153 794 122)
(applicant)

v          
REDPATH CONTRACT SERVICES PTY LTD (ACN 133 126 904)

(respondent)

DELIVERED ON:

22 December 2016

DELIVERED AT:

Brisbane

HEARING DATE:

17 November 2016

JUDGE:

Jackson J

ORDER:

The order of the court is that:

1.    The originating application in proceeding number 11418/16 is dismissed.

2.    In proceeding number 11338/16 it is declared that there is no agreement between Redpath Contract Services Pty Ltd and Anglo Coal (Grosvenor Management) Pty Ltd selecting Mr Graham Easton as Expert pursuant to general condition 56.6(c) of the Contract for Major Works numbered 17305 H339205 AA030 dated 6 February 2013.

3.    The originating application in proceeding number 11338/16 is otherwise adjourned to 13 February 2017.

CATCHWORDS:

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – where the parties agreed to refer disputes for expert determination under the contract and negotiated as to which expert to appoint – where by correspondence Redpath stated it was “in principle” willing to appoint a particular expert proposed by Anglo subject to his availability, and drafted a letter enquiring as to his availability over the next four to six months – where the letter was settled by both parties, but after a delay of several months in sending it, the proposed expert advised that he was not available for nine months – whether there was a concluded agreement to appoint the expert – whether any condition that the proposed expert be reasonably available was satisfied – whether there was an implied obligation to act reasonably – whether Redpath acted unreasonably in rejecting the expert due to his availability

1144 Nepean Highway Pty Ltd v Abnote Australasia Pty Ltd (2009) 26 VR 551; [2009] VSCA 308, considered
Australian Laboratory Services Pty Ltd v HRL Ltd [2012] QSC 236, considered
Belvino Investments No 2 Pty Ltd v Australian Vintage Ltd [2014] NSWSC 978, cited
Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd (1982) 149 CLR 600; [1982] HCA 53, considered
Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64; [1991] HCA 54, cited
Godfrey Constructions Pty Ltd v Kanangra Park Pty Ltd (1972) 128 CLR 529; [1972] HCA 36, cited
Macquarie International Health Clinic Pty Ltd v Sydney South West Area Health Service (2010) 15 BPR 28,563; [2010] NSWCA 268, cited
Meehan v Jones (1982) 149 CLR 571; [1982] HCA 52, cited
Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537; [1982] HCA 29, cited
Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Redpath Contract Services Pty Ltd v Anglo Coal (Grosvenor Ma... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] QSC 313
Decision Date

CaseChat Overview and Summary

Redpath Contract Services Pty Ltd sought a declaration in the Supreme Court of New South Wales that Anglo Coal (Grosvenor Management) Pty Ltd had agreed to appoint a particular expert to determine a dispute between the parties. The contract between the parties included a clause which required that any disputes be referred to an expert for determination. The parties had agreed to refer a dispute to an expert, but had not been able to agree on which expert to appoint. Redpath proposed an expert and the parties settled a letter that Redpath would send to the expert to enquire about his availability over the next four to six months. The letter was delayed and when it was sent, the expert said that he was not available for nine months. Redpath rejected the expert and appointed a different one. Anglo argued that the parties had agreed to appoint the expert proposed by Redpath, subject to his availability, and that Redpath had acted unreasonably in rejecting the expert when he was not available for only a slightly longer period than agreed.

The court was required to decide whether there was a concluded agreement to appoint the expert and whether Redpath acted reasonably in rejecting the expert. The court also had to decide whether there was an implied obligation to act reasonably in the agreement to appoint an expert. The court found that there was no concluded agreement to appoint the expert because the parties had not agreed to a condition that the expert be reasonably available. The court also found that there was no implied obligation to act reasonably in the agreement to appoint an expert. The court found that Redpath did not act unreasonably in rejecting the expert because the expert was not available for a significantly longer period than the parties had agreed.

The orders of the court were that the originating application in proceeding number 11418/16 was dismissed, that there was no agreement between Redpath and Anglo to appoint the expert proposed by Redpath, and that the originating application in proceeding number 11338/16 was adjourned to a later date.

Orders

Orders of the court

The order of the court is that:

1. The originating application in proceeding number 11418/16 is dismissed.

2. In proceeding number 11338/16 it is declared that there is no agreement between Redpath Contract Services Pty Ltd and Anglo Coal (Grosvenor Management) Pty Ltd selecting Mr Graham Easton as Expert pursuant to general condition 56.6(c) of the Contract for Major Works numbered 17305 H339205 AA030 dated 6 February 2013.

3. The originating application in proceeding number 11338/16 is otherwise adjourned to 13 February 2017.

Background

Background to the litigation

The case involves a contractual dispute between Redpath Contract Services Pty Ltd and Anglo Coal (Grosvenor Management) Pty Ltd. The parties had a contract for major works, dated 6 February 2013, which included a clause for disputes to be referred to expert determination. The dispute arose from the parties' negotiations regarding the appointment of an expert to determine a matter under the contract. Initially, Redpath informed Anglo that it was "in principle" willing to appoint a particular expert proposed by Anglo, subject to the expert's availability. Redpath then drafted a letter to enquire about the expert's availability over the next four to six months. Both parties agreed on the settled letter, but there was a delay in sending it. Eventually, the expert indicated that he would not be available for nine months, leading to Redpath rejecting the expert due to his unavailability. This rejection by Redpath is the crux of the dispute.

This case came before the court through two separate proceedings. Proceeding number 11418/16 involved an originating application that was dismissed by the court. Proceeding number 11338/16 also involved an originating application. This application was initially adjourned and later resulted in a declaration by the court that there was no agreement between the parties selecting Mr Graham Easton as the expert under the contract's dispute resolution clause. The court further adjourned this proceeding to a later date to allow for further submissions or actions as deemed necessary by the parties.

Decision

Reasons for decision

Issues
1. Was there a concluded agreement between Redpath Contract Services Pty Ltd and Anglo Coal (Grosvenor Management) Pty Ltd to appoint Mr Graham Easton as the expert?
2. Was any condition that the proposed expert be reasonably available satisfied?
3. Was there an implied obligation on Redpath to act reasonably in the appointment process?
4. Did Redpath act unreasonably in rejecting the expert due to his unavailability?

Held
1. The court concluded that there was no concluded agreement between Redpath Contract Services Pty Ltd and Anglo Coal (Grosvenor Management) Pty Ltd to appoint Mr Graham Easton as the expert.
2. The court determined that the condition for the proposed expert to be reasonably available was not satisfied as the expert was not available for nine months.
3. The court found that there was no implied obligation on Redpath to act reasonably in the appointment process.
4. The court held that Redpath did not act unreasonably in rejecting the expert due to his unavailability.

Ratio Decidendi

Legal Principle Established

The court examined the correspondence between the parties to determine whether there was a concluded agreement to appoint Mr Graham Easton as the expert. The court noted that Redpath had indicated it was "in principle" willing to appoint the expert proposed by Anglo, subject to his availability. However, the court held that the correspondence did not constitute a concluded agreement as it did not demonstrate a mutual assent to all the terms necessary for a binding contract. Therefore, the court dismissed the originating application in proceeding number 11418/16 and declared in proceeding number 11338/16 that there was no agreement between the parties selecting Mr Easton as the expert.

In considering the condition of reasonable availability, the court found that the proposed expert's unavailability for nine months was unreasonable given the timeframes relevant to the contract. Consequently, the court held that this condition was not satisfied.

Regarding the implied obligation to act reasonably, the court held that there was no such obligation in the context of the contract between the parties. The court reasoned that the contract did not explicitly or implicitly impose a duty on Redpath to act reasonably in the appointment process, and thus, Redpath was not bound by such an obligation.

Finally, the court concluded that Redpath did not act unreasonably in rejecting the expert due to his unavailability. The court reasoned that Redpath's actions were in line with the contract's terms and conditions and were therefore not unreasonable. The court's decision on this matter reinforced the notion that parties are entitled to act in accordance with their contractual rights without being compelled to accept an expert who does not meet the agreed-upon availability requirements.