| IN THE COURT OF APPEAL | [1997] QCA 447 |
| SUPREME COURT OF QUEENSLAND |
Appeal No. 1863 of 1997
Brisbane
[State of Qld v. Multiplex Constructions P/L]
BETWEEN:
STATE OF QUEENSLAND
Appellant
AND:
MULTIPLEX CONSTRUCTIONS PTY. LTD. ACN 008 687 063
Respondent
Davies J.A. Pincus J.A. Lee J.
Judgment delivered 19 December 1997
Joint reasons for judgment of Davies J.A. and Lee J.; separate reasons of Pincus J.A. dissenting in part.
DECLARATION AND ORDER MADE BELOW SET ASIDE. IT IS DECLARED THAT, ON THE PROPER CONSTRUCTION OF CLAUSE 35.5 OF THE GENERAL CONDITIONS OF CONTRACT, THE WRITTEN CLAIM REFERRED TO IN THE THIRD PARAGRAPH SHOULD BE GIVEN BY THE CONTRACTOR NO LATER THAN 28 DAYS AFTER DELAY HAS FIRST OCCURRED.
NO ORDER AS TO COSTS OF HEARING BELOW. RESPONDENT TO PAY
APPELLANT'S COSTS OF THIS APPEAL.
| CATCHWORDS: | CIVIL - construction of a building contract - whether the phrase "after the delay occurs" means after the period of delay is completed or after the point of time at which the contractor could properly say that delay has occurred, notwithstanding that it is still occurring. Lewis v. Green [1905] 2 Ch. 341 |
| Counsel: | Mr. D. Gore Q.C., with him Mr. M. Williams for the appellant Mr. R. A. Holt S.C. for the respondent |
| Solicitors: | Mr. B. T. Dunphy, Crown Solicitor for the appellant Clayton Utz for the respondent |
| Hearing Date: | 21 October 1997 |
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
Appeal No. 1863 of 1997
Brisbane
| Before | Davies J.A. Pincus J.A. Lee J. |
[State of Qld v. Multiplex Constructions P/L]
BETWEEN:
STATE OF QUEENSLAND
Appellant
AND:
MULTIPLEX CONSTRUCTIONS PTY. LTD. ACN 008 687 063
Respondent
JOINT REASONS FOR JUDGMENT - DAVIES J.A. AND LEE J.
Judgment delivered 19 December 1997
The question below and in this Court concerns the construction of cl.35.5 of a building contract
dated 12 October 1995 between the appellant, the State of Queensland, as principal and the
respondent as contractor for the construction of the Queensland Conservatorium of Music. The
question of construction was decided by the learned primary Judge pursuant to an application made by
the respondent under O.64 r.1A of the Rules of the Supreme Court. Although no question arises in this
Court as to whether his Honour should have decided that question, because it had been urged below
that he should not do so it is desirable to say something about that lest it may be thought, in future cases,
that there should be any doubt about the correctness of his Honour deciding it.
It is true that deciding the question of construction here would not "settle the litigation between
the parties", to adopt a phrase from the decision of Warrington J. in Lewis v. Green [1905] 2 Ch. 340
at 344 relied on below by the present appellant. But, whatever the position may have been in England
in 1905, that is certainly not the correct approach now either under O.64 r.1A or under…
Continue reading Re Multiplex Constructions Pty Ltd
Sign in free to access the full text
- AGLC
- Re Multiplex Constructions Pty Ltd [1997] QCA 447
- Case
- [1997] QCA 447
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were pivotal for the resolution of the dispute. The court needed to ascertain the precise meaning of the phrase "after the delay occurs" and how it should be applied in the context of the contract. This involved an examination of the contract terms, industry practice, and relevant legal precedents. The interpretation of this phrase had significant implications for the timing of certain contractual obligations and the potential penalties for delays.
In delivering the judgment, the court delved into the language of the contract and considered the broader context in which it was used. The court examined the ordinary and natural meaning of the phrase in question and sought to interpret it in a way that gave effect to the intentions of the parties. The court also looked to relevant legal principles and precedents to aid in its interpretation. Ultimately, the court determined that the phrase "after the delay occurs" meant after the period of delay was completed, rather than at the point when the delay could first be identified. This interpretation was based on a consideration of the contractual language and the practical implications of each possible meaning. The court's decision provided clarity on the obligations of the parties and resolved the ambiguity in the contract.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.