Re Concrete Constructions Group Pty Ltd

Link copied
Case Copied 16 min read

IN THE COURT OF APPEAL

SUPREME COURT OF QUEENSLAND

Appeal No. 144 of 1995

Brisbane

[Blue Chip Pty. Ltd. v. Concrete Constructions Group Pty. Ltd.]

BETWEEN

BLUE CHIP PTY. LTD.

(Respondent) Appellant

AND

CONCRETE CONSTRUCTIONS GROUP PTY. LTD.

(Applicant) Respondent

Fitzgerald P.
McPherson J.A.

Helman J.

Judgment delivered 02/04/96

Separate reasons by Fitzgerald P., concurring in the order proposed in the joint reasons for judgment by McPherson J.A. and Helman J.

APPEAL DISMISSED WITH COSTS.

CATCHWORDS

BUILDING CONTRACT - Implied terms - Express right to payments certified by the superintendent should not be qualified by discovering hidden meanings extricated from half-expressed reservations in the other parts of the document.

Counsel:  D. Gore Q.C., for the appellant
R. Hold S.C. for the respondent
Solicitors:  Stubbs Barbeler Grant for the appellants
Corrs Chambers Westgarth for the respondent

Hearing Date: 8 March 1996

IN THE COURT OF APPEAL [1996] QCA 086
SUPREME COURT OF QUEENSLAND Appeal No. 144 of 1995
Brisbane
Before Fitzgerald P.
McPherson J.A.
Helman J.

[Blue Chip P/L v. Concrete Constructions Group P/L]

BETWEEN:

BLUE CHIP PTY LTD

(ACN 010 748 302) (Respondent) Appellant

AND:

CONCRETE CONSTRUCTIONS GROUP PTY LTD

(ACN 008 390 074) (Applicant) Respondent

REASONS FOR JUDGMENT - FITZGERALD P.

Judgment delivered 02/04/1996

The circumstances giving rise to this appeal are set out in the reasons for judgment of the other members

of the Court.

In accordance with the principal’s instructions that it did not wish at that time to deduct liquidated

damages for the contractor’s delay in practical completion, on 15 December 1994 the superintendent

issued the contractor with a payment certificate for $887,304.00, accompanied by a letter stating that

the principal retained its right to all liquidated damages due. Assuming that the contractor then had no

entitlement to an extension of time, the liquidated damages would have totalled $630,000.00; 126 days
at $5,000.00 per day.

By 28 December 1994, when progress certificate no. 16 fell due for payment, the liquidated damages

claimed by the principal had increased to $770,000.00; 154 days at $5,000.00. The principal

deducted that sum and paid the contractor only $117,304.00 in respect of certificate no. 16. Its sole

claim to make this reduced payment was that such a course was authorised by the fourth paragraph of

cl. 42.1 of the General Conditions of Contract. It should be noted at this point that when certificate no.

16 had been issued on 15 December, the contractor had been warned that the principal reserved its

right to deduct the liquidated damages from the certificate “in the event that the principal determines such

a deduction is appropriate”. Obviously, that was the conclusion which the principal had reached by 28

December when it deducted the liquidated damages from the certificate amount.

The argument for the principal was based on the introductory words to the fourth paragraph of General

Condition 42.1 and, read by reference only to that clause, they provide a foundation for the principal’s

submission. At its simplest, the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Re Concrete Constructions Group Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[1996] QCA 86
Decision Date

CaseChat Overview and Summary

The parties to this case were Concrete Constructions Group Pty Ltd and another party whose identity was redacted for confidentiality reasons. The dispute arose out of a building contract, with the primary issue being the interpretation of the contract's terms regarding payment certifications. The matter was heard in the Supreme Court of Victoria.

The legal issue before the court was whether an express right to payments certified by the superintendent could be limited by terms that were only partially expressed and required interpretation from other parts of the contract. The court needed to determine whether the contract's terms should be interpreted in a way that would impose hidden qualifications on the express right to payments.

The court found that the express right to payments certified by the superintendent should not be limited by hidden meanings derived from half-expressed reservations in other parts of the document. The court held that the contract's terms should be interpreted in a way that gave effect to the plain meaning of the express terms, and that the parties could not rely on ambiguous or obscure terms to limit the express rights granted. The court emphasised the importance of avoiding interpretations that would introduce hidden qualifications into express contractual rights.

As a result of the court's decision, the party seeking to limit the express right to payments was not successful. The court held that the contract should be interpreted in a way that gave effect to the express terms, without imposing hidden meanings or qualifications derived from other parts of the contract. The court's decision provides guidance for parties to building contracts, emphasising the importance of clear and unambiguous contractual language.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established