Kingston Building (Australia) Pty Ltd v Dial D Pty Ltd as trustee for the Smith Street Unit Trust

Link copied
Case Copied 12 min read

Supreme Court


New South Wales

Medium Neutral Citation: Kingston Building (Australia) Pty Ltd v Dial D Pty Ltd as trustee for the Smith Street Unit Trust [2013] NSWSC 173
Hearing dates:4 March 2013
Decision date: 05 March 2013
Jurisdiction:Equity Division - Technology and Construction List
Before: Stevenson J
Decision:

Plaintiff entitled to judgment

Catchwords: BUILDING AND CONSTRUCTION - entitlement to progress claim - subsequent inconsistent progress certificate
Cases Cited: Algons Engineering Pty Limited v Abigroup Contractors Pty Limited [1997] NSWSC 478
Re Concrete Constructions Group Pty Ltd [1996] QCA 86
Macquarie International Health Clinic Pty ltd v Sydney South West Area Health Service [2010] NSWCA 268
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457
Category:Principal judgment
Parties: Kingston Building (Australia) Pty Ltd (plaintiff)
Dial D Pty Limited as trustee for the Smith Street Unit Trust (defendant)
Representation: Counsel:
F P Hicks with A D Gerard (plaintiff)
F G Kalyk (defendant)
Solicitors:
Moray & Agnew Lawyers (plaintiff)
Keystone Lawyers (defendant)
File Number(s):SC 2013/27998
Publication restriction:Nil

EX TEMPORE Judgment (REVISED 6 MARCH 2013)

Introduction

  1. This is a dispute between a builder and a proprietor as to the builder's entitlement to be paid a progress claim. The builder made that progress claim on 21 December 2012.

Background

  1. On 31 March 2010 the plaintiff, Kingston Building (Australia) Pty Ltd ("the Builder") and the defendant, Dial D Pty Ltd as trustee for the Smith Street Unit Trust ("the Proprietor"), entered an agreement ("the Contract") pursuant to which the Builder agreed to construct for the Proprietor a medical centre in Charlestown. The contract sum was $9,345,189, subject to variations and other adjustments.

  1. Work achieved practical completion on 5 July 2012. Thereafter, the Builder undertook further variations and remedial works in the period from July to December 2012.

  1. The Builder has done no work on the site since 21 December 2012.

  1. On 21 December 2012 the Builder sent the Superintendent under the Contract a Progress Claim of $1,170,695.09 ("the Progress Claim").

  1. The matter for consideration is whether, in the events that happened, the Builder is entitled to be paid the amount of that Progress Claim.

Decision

  1. In my opinion, the Builder is entitled to be paid the amount of that Progress Claim. I propose to give judgment in the Builder's favour for that amount.

Terms of the Contract

  1. Clauses 37.1 and 37.2 of the Contract are in the following terms (to facilitate reference to sub-clauses within these clauses, I have added sub-clause numbering, thus "[x]"): -

"37.1 Progress claims
[1] The Contractor shall claim payment progressively in accordance with Item 28.
[2] An early progress claim shall be deemed to have been made on the date for making that claim.
[3] Each progress claim shall be given in writing to the Superintendent and shall include details of the value of WUC done and may include details of other moneys then due to the Contractor pursuant to provisions of the Contract.
37.2 Certificates
[1] The Superintendent shall, within 14 days…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Kingston Building (Australia) Pty Ltd v Dial D Pty Ltd as tr... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2013] NSWSC 173
Decision Date

CaseChat Overview and Summary

The case involved Kingston Building (Australia) Pty Ltd, the builder, and Dial D Pty Ltd, the trustee for the Smith Street Unit Trust. The dispute related to a progress claim by Kingston for additional payment in relation to construction work performed on a property at Smith Street. The matter was heard in the Supreme Court of New South Wales. The builder argued that it was entitled to the additional payment claimed, while the trustee for the Unit Trust contended that the claim was invalid due to a subsequent inconsistent progress certificate.

The primary legal issue was whether the builder was entitled to a progress claim when it had issued a subsequent progress certificate that was inconsistent with the original claim. The court had to determine whether the subsequent certificate, which omitted certain items included in the original claim, operated as a waiver of the original claim. A secondary issue was whether the builder could still be entitled to the additional payment despite the inconsistent certificate.

The court found that the subsequent certificate did not operate as a waiver of the original claim. The court held that a subsequent certificate which omits items included in the original claim does not necessarily amount to a waiver of the original claim. Rather, the builder was entitled to the additional payment claimed, subject to certain conditions. The court further held that the builder could still be entitled to the additional payment, even if the subsequent certificate was inconsistent with the original claim, provided that the builder could demonstrate that it had provided the additional work or materials claimed. The court ultimately found in favour of the builder and ordered the trustee for the Unit Trust to pay the additional amount claimed by the builder.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established