| CITATION: | Randall and Anor v Domestic Maintenance Pty Ltd [2012] QCAT 266 |
| PARTIES: | Peter Randall Selinda Randall (Applicants) |
| v | |
| Domestic Maintenance Pty Ltd (Respondent) |
| APPLICATION NUMBER: | BDL399-10 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 18 April 2012 |
| HEARD AT: | Brisbane |
| DECISION OF: | William LeMass, Member |
| DELIVERED ON: | 28 June 2012 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The respondent pay to the applicants the sum of $18,068.00 within 30 days. |
| CATCHWORDS: | Domestic Building Contracts Act 2000, s 44 |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Mr and Mrs Randall |
| RESPONDENT: | Mr and Mrs Jackson |
REASONS FOR DECISION
This matter concerns the construction of paving works upon a concrete slab surrounding a pool at the applicants’ residence at Upper Kedron in Brisbane.
The works have failed catastrophically, can not be repaired and must be removed at substantial cost.
The works render the pool unsafe to be used further necessitating removal.
The nature of the failure of the works is that the slab and paving have sunk below the level of the pool coping to the extent of some 200mm causing substantial cracking, trip hazards and the pool gate to permanently remain unlocked.
The applicants contend that the respondent is liable for the repayment of the whole of the contract price for the works and the payment of the costs of removal of the works and replacement of associated works.
It is fundamental to understand why the works have failed and whom if anyone should have taken account of the reason for the failure in order to prevent that failure.
Reasons for failure
The evidence before the Tribunal universally accepted that the cause of the collapse of the works is at its most basic, the downwards vertical movement of the land directly under the slab as measured against the height of the pool which has remained (more or less) at its original level.
There are many hypotheses as to why the ground would move and these are contained in the experts’ reports, however again it is universally accepted that at least a substantial contributing factor is that such ground is uncompacted fill.
The evidence of Mr Beal, engineer, in his report exhibit 2 at page 5 clause 2.1.1 is as follows:
“Self evidently, the drop in the paving has occurred due to the settlement of the ground supporting the paving relative to non settlement or at least lesser settlement of the pool coping and the pool structure, the latter having been provided with some form of more deeply founded footing system.”
Mr Beal then goes on to outline 5 possible reasons for the ground settlement which may have acted he says either alone or in combination.
The evidence of Mr Fox, engineer, at exhibit 9 page 6 paragraph 4.3 is as follows:
“In my opinion there is no doubt that the ground on which the concourse slab was cast was unstable, and the ground under its own weight would have settled vertically and displaced sideways to the north, irrespective of whether or…
Keep reading for free
Create a free CaseChat account to read Randall v Domestic Maintenance Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] QCAT 266
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the tribunal was whether the respondent had breached the terms of the contract by failing to provide a product and service that met the standards required by the Domestic Building Contracts Act 2000. Specifically, the tribunal had to determine whether the respondent had complied with section 44 of the Act, which requires that building work be performed with due care and skill. The tribunal also considered the extent of the respondent's liability for the alleged defects and whether any of the applicant's claims were statute-barred.
In delivering its decision, the tribunal found that the respondent had indeed breached the contract by failing to perform the work to a reasonable standard. The tribunal held that the respondent's workmanship was substandard, resulting in significant issues that impacted the structural integrity of Mr Randall's home. The tribunal rejected the respondent's argument that external factors were responsible for the defects, finding that the respondent had not taken reasonable steps to mitigate these issues. The tribunal ordered the respondent to pay the applicant the sum of $18,068.00 within 30 days to cover the costs of rectifying the defects and any other associated expenses. The tribunal also found that none of the applicant's claims were statute-barred, as the defects were discovered within a reasonable time after the work was completed.
Orders
Orders of the court
1. The respondent pay to the applicants the sum of $18,068.00 within 30 days.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.