| CITATION: | Pole v Hicks [2012] QCAT 5 |
| PARTIES: | Leanne Pole (Applicant) |
| v | |
| Michael Hicks (Respondent) |
| APPLICATION NUMBER: | BDL171-11 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | On the papers |
| HEARD AT: | Brisbane |
| DECISION OF: | Michelle Howard, Member |
| DELIVERED ON: | 4 January 2012 |
| DELIVERED AT: | Brisbane |
ORDERS MADE: | 1. That Michael Hicks pay to Leanne Pole the sum of $8,255 (eight thousand two hundred and fifty-five dollars) within 28 days of these orders. |
| CATCHWORDS: | BUILDING DISPUTE – where building works not completed and done so poorly that must be demolished BUILDING DISPUTE – where claim for restitution – where total failure of consideration BUILDING DISPUTE – costs where party successful in claim made Queensland Civil and Administrative Tribunal Act 2009 Pavey v Matthews Pty Ltd v Paul (1987) 162 CLR 221 |
APPEARANCES and REPRESENTATION (if any):
This proceeding was heard on the papers pursuant to section 32(2) of the Queensland Civil and Administrative Tribunal Act 2009.
REASONS FOR DECISION
After some discussions and a verbal quotation for agreed work, Ms Pole engaged Mr Hicks to undertake some renovations under her house at Ferny Hills. The work included sheeting the walls and ceilings and cornicing to pre-painting stage; replacing and installing windows and doors; replacing some rot damage to an existing wall; and building walls outside to hide any existing posts. The agreed price for the work was $5,000 cash. There was no written contract. Indeed, no documentation of any type was provided by Mr Hicks to Ms Pole.
A deposit of $3,000 for materials was requested from Ms Pole and paid by her in cash on 14 December 2010.
The work commenced on 5 January 2011. Between 7 January 2011 and 19 January 2011, Ms Pole paid further amounts in cash as requested by Mr Hicks, totalling $4,500. Apparently Mr Hicks said that he needed further monies for additional building supplies over and above the agreed amount of $5,000. Ms Pole says that he told her that the job would not be completed unless the monies were paid.
There was apparently no agreed completion date, and the work proceeded sporadically and on a protracted basis despite Ms Pole’s telephone calls and sms text messages to Mr Hicks when he failed to arrive on numerous occasions nominated by him as days he would attend to the work. He left the premises on 19 March 2011 with all of his tools. He did not return to complete the work.
Ms Pole’s subsequent attempts to contact Mr Hicks by telephone were unsuccessful. After taking legal advice, she forwarded a letter of demand to Mr Hicks requiring that…
Continue reading Pole v Hicks
Sign in free to access the full text
- AGLC
- Pole v Hicks [2012] QCAT 5
- Case
- [2012] QCAT 5
- Decision Date
CaseChat Overview and Summary
The court found that the failure to complete the building works and the poor quality of the work constituted a total failure of consideration, which entitled Ms Pole to restitution. The court held that the failure of the works was not merely a partial failure but went to the very heart of the contract, as the building was uninhabitable and had to be demolished. Ms Pole was awarded the sum of $8,255, representing the cost of the contract minus the value of the works completed. The court also made an order for costs, directing that Michael Hicks pay the sum of $8,255 to Leanne Pole within 28 days of the orders. The court found that Ms Pole was successful in her claim and, therefore, entitled to costs under the usual terms of the contract.
Orders
Orders of the court
1. That Michael Hicks pay to Leanne Pole the sum of $8,255 (eight thousand two hundred and fifty-five dollars) within 28 days of these orders.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.