CITATION: Rahme Civil Pty Ltd v Zeater & Sons Pty Ltd [2010] NSWDC 161 HEARING DATE(S): 17 - 21 May and 24 June 2010
JUDGMENT DATE:
6 August 2010JURISDICTION: Civil JUDGMENT OF: Hungerford ADCJ DECISION: (1) Verdict for the plaintiff against the defendant on the claim in the amount of $31,662.45.
(2) Verdict for the defendant/cross-claimant against the plaintiff/cross-defendant on the cross-claim in the amount of $10,000.00.
(3) Judgment for the plaintiff/cross-defendant against the defendant/cross claimant in the proceedings by way of a set-off of the respective verdicts in the amount of $21,662.45.
(4) Defendant/cross-claimant to pay 50% of the plaintiff's/cross/defendant's costs of the proceedings on the ordinary basis in an amount as agreed or assessed.CATCHWORDS: BUILDING CONTRACTS - Construction contract for residential units - Demolition/excavation work - Damage to building by contractor's truck - Negligence of truck driver - Payment claims - Multiple payment claims - Need for a payment schedule to dispute claim - Statutory debt - Unlicensed contractor - Whether contract enforceable - Quantum meruit - Status of contractor's unpaid progress claims - Cross-claim by builder - Cost of rectification work to building - Whether damage to building caused by truck incident - Whether additional work causally related to truck incident - Set-off of separate verdicts - Costs LEGISLATION CITED: Builders Licensing Act 1971, s 45
Building and Construction Industry Security of Payment Act 1999, ss 3(3)(c), 8, 11(1), 13, 14, 15(2), 17(1), 17(2), 32 and Div 1 of Pt 3
Civil Procedure Act 2005, s 90(2)
Home Building Act 1989, ss 4(1) and 10(1)
Occupational Health and Safety (Demolition Licensing) Regulation 2001CASES CITED: Brodyn Pty Ltd t/as Time Cost and Quality v Davenport [2003] NSWSC 1019
Falgat Constructions Pty Ltd v Equity Australia Corporation Pty Ltd [2005] NSWCA 49
Grosvenor Constructions (NSW) Pty Ltd (in administration) v Musico [2004] NSWSC 344
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140
Musico v Davenport [2003] NSWSC 977
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221
Riverside Motors Pty Ltd v Abrahams [1945] VLR 45
Rojo Building Pty Ltd v Jillcris Pty Ltd [2006] NSWSC 309
Rojo Building Pty Ltd v Jillcris Pty Ltd [2007] NSWSC 880
Stallion Civil Group Pty Ltd v Tresedar Pty Ltd [2009] NSWDC 125PARTIES: Rahme Civil Pty Limited - Plaintiff/Cross-Defendant
Zeater &Sons Pty Limited - Defendant/Cross-ClaimantFILE NUMBER(S): 00337563 of 2009 COUNSEL: Mr TO Bland for Plaintiff/Cross-Defendant
Mr MH Southwick for Defendant/Cross-ClaimantSOLICITORS: C & M Lawyers for Plaintiff/Cross-Defendant
Macquarie Lawyers for Defendant/Cross-Claimant
JUDGMENT
1 The construction of residential townhouses at 208 Bridge Road, Glebe required the demolition of an old brick factory on the site and the excavation for an undercover car park. As part of the demolition, it seems for heritage reasons imposed by the Council of the City of Sydney as the local government authority, the facade was to be maintained together with side walls in accordance with the approved development application. The demolition/ excavation sub-contractor commenced work on the site in early-June…
Keep reading for free
Create a free CaseChat account to read Rahme Civil Pty Ltd v Zeater and Sons Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] NSWDC 161
- Decision Date
CaseChat Overview and Summary
The legal issues before the court encompassed whether the contract was enforceable given the contractor's lack of a license, the status of the unpaid progress claims, and the extent of liability for damages. Additionally, the court had to determine if the additional rectification work was causally related to the truck incident and the viability of set-off between the parties' respective claims.
In its reasoning, the court found that the contract was enforceable despite the contractor's unlicensed status. It held that the damage to the building was indeed caused by the truck incident. The court also concluded that the additional work was not causally related to the incident. Regarding the set-off, the court allowed the defendant to offset their verdict against the plaintiff's verdict, resulting in a net judgment for the plaintiff. The court awarded the plaintiff damages and ordered the defendant to pay half of the plaintiff's costs.
The final orders included a verdict in favour of the plaintiff for $31,662.45, a verdict in favour of the defendant on the cross-claim for $10,000.00, and a judgment for the plaintiff after set-off in the amount of $21,662.45. The defendant was also ordered to pay 50% of the plaintiff's costs.
Orders
Orders of the court
(1) Verdict for the plaintiff against the defendant on the claim in the amount of $31,662.45.
(2) Verdict for the defendant/cross-claimant against the plaintiff/cross-defendant on the cross-claim in the amount of $10,000.00.
(3) Judgment for the plaintiff/cross-defendant against the defendant/cross claimant in the proceedings by way of a set-off of the respective verdicts in the amount of $21,662.45.
(4) Defendant/cross-claimant to pay 50% of the plaintiff's/cross/defendant's costs of the proceedings on the ordinary basis in an amount as agreed or assessed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi