Land and Environment Court
New South Wales
Medium Neutral Citation: R.I.G Consulting Pty Ltd v Queanbeyan-Palerang Regional Council [2020] NSWLEC 155 Hearing dates: 23 October 2020 Date of orders: 23 October 2020 Decision date: 19 November 2020 Jurisdiction: Class 1 Before: Robson J Decision: See orders at [19]
Catchwords: CIVIL PROCEDURE — Separate determination of questions — Where appropriate — Separate questions ordered
Legislation Cited: Uniform Civil Procedure Rules 2005 (NSW) r 28.2
Cases Cited: 820 Cawdor Road Pty Ltd v Wollondilly Shire Council [2013] NSWLEC 8; (2013) 195 LGERA 170
Allandale Blue Metal Pty Ltd v Roads and Maritime Services [2013] NSWCA 103; (2013) 195 LGERA 182
Cavanagh v Wollondilly Shire Council [2019] NSWLEC 105
Challenger Listed Investments Ltd v Valuer General [2015] NSWLEC 7
Dial a Dump Industries Pty Ltd v Roads and Maritime Services [2015] NSWLEC 172
M.H. Earthmoving Pty Ltd v Cootamundra-Gundagai Regional Council (No 2) [2018] NSWLEC 101
Royal Motor Yacht Club (Broken Bay) Pty Ltd v Northern Beaches Council (No 4) [2016] NSWLEC 126
Whittaker v Northern Beaches Council (No 2) [2018] NSWLEC 94
Category: Procedural and other rulings Parties: R.I.G Consulting Pty Ltd (Applicant)
Queanbeyan-Palerang Regional Council (Respondent)Representation: Counsel:
Solicitors:
Y R Hazan, solicitor (Applicant)
A Menyhart, solicitor (Respondent)
Hazan Hollander (Applicant)
Bradley Allen Love Lawyers (Respondent)
File Number(s): 2020/00156307 Publication restriction: Nil
Judgment
-
On 23 October 2020, I made orders pursuant to r 28.2 of the Uniform Civil Procedure Rules 2005 (NSW) (‘UCPR’) that the questions specified in an amended notice of motion filed on behalf of R.I.G Consulting Pty Ltd (‘applicant’) on 9 September 2020 be determined separately from any other question in the proceedings and before any further trial of the proceedings. These are my reasons.
Background
-
These Class 1 proceedings concern an application filed 26 May 2020 appealing against the refusal by Queanbeyan-Palerang Regional Council (‘Council’) on 13 November 2019 to grant development consent for a three lot subdivision of Lot 4 in DP 285984, located at 71 MacDiarmid Road, Burra (‘Land’) into three lots of 6ha, 2.5ha and 1.36ha respectively.
-
Council’s statement of facts and contentions filed 8 July 2020 (‘SFC’) contends that the proposed subdivision is prohibited pursuant to cll 4.1B(4)(a) and 4.1B(5) of the Palerang Local Environmental Plan 2014 (‘PLEP’) because the Land was itself a “resulting lot” and the subdivision would create lots with an average size less than that prescribed by the lot size map for land zoned E4 Environmental Living. More particularly, the two contentions in relation to the contended prohibition provide as follows:
“PART B(1): CONTENTIONS WHY THE APPLICATION MUST BE REFUSED
1. The proposed development is prohibited under Clause 4.1B(5) of the PLEP because the Site is a resulting lot.
Particulars
a. The Site is zoned E4 Environmental Living under the PLEP.
b. The Site was created by a subdivision under Clause 20 of the YLEP.
c. [T]he Site is a resulting lot as defined under Clause 4.1B(6) of the PLEP.
d. [T]he purpose of the proposed subdivision…
Keep reading for free
Create a free CaseChat account to read R.I.G Consulting Pty Ltd v Queanbeyan-Palerang Regional Coun... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2020] NSWLEC 155
- Decision Date
CaseChat Overview and Summary
The central legal issues addressed by the court were whether the council had the authority to make the decision in question and if the applicant's concerns about the environmental impact were adequately addressed. The applicant argued that the council had overstepped its legislative mandate by imposing conditions that were not authorised by law and had not sufficiently considered the potential environmental harm of the proposed development. Conversely, the council contended that it had exercised its powers correctly and had fulfilled its obligations under the relevant planning legislation.
The court examined the statutory framework governing the council's decision-making authority and assessed whether the council's actions were consistent with the law. It concluded that the council had indeed exceeded its powers by imposing conditions not authorised by the legislation, and it had failed to adequately consider the environmental implications of the development. The court found that these errors rendered the council's decision unlawful. Consequently, the court quashed the decision and remitted the matter back to the council for reconsideration, ensuring that all legal and environmental considerations were properly addressed.
Orders
Orders of the court
See orders at [19]
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi