| Pulitano v Mikescapes Pty Ltd [2010] QCAT 248 |
| PARTIES: | Filip & Anna Pulitano |
| v | |
| Mikescapes Pty Ltd |
| APPLICATION NUMBER: | BD218-08 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | On the papers |
| HEARD AT: | Brisbane |
| DECISION OF: | Dr Bridget Cullen Mandikos |
| DELIVERED ON: | 7 June 2010 |
| DELIVERED AT: | Brisbane |
ORDERS MADE: | The Respondent, Mikescapes Pty Ltd, to pay the Applicants’ Filip and Anna Pulitano, the sum of $12,012.00 no later than 4:00 pm on Friday, 9 July 2010. |
| CATCHWORDS : | Rectification of defective building work pursuant to contract, measure of quantum, Bellgrove v Eldridge (1954) 90 CLR 613; Tabcorp Holdings Limited v Bowen Investments Pty Ltd [2009] HCA 8. |
APPEARANCES and REPRESENTATION (if any):
| Decision on the papers. |
REASONS FOR DECISION
Background
The Applicants in this matter, Filip and Anna Pulitano (“The Pulitanos”), entered into a contract with the Respondent, Mikescapes Pty Ltd (“Mikescapes”) for landscaping works at their Jasmine Crescent, Shailer Park, property.
Following an oral hearing on 15 April 2010, I delivered an ex tempore decision in the Pulitano's favour, and ordered that the parties make written submissions as to the appropriate quantum of loss, with respect to the paving works that took place at the property. The reason for the matter being part-heard with regard to the issue concerning quantum was that I was not satisfied with the material before QCAT on this issue.
Although there were allegations raised in the Pulitano’s Statement of Claim relating to a retaining wall and the proper planting of plants, at hearing, the matters that were disputed related to the paving works that took place at the property. It was alleged that:
Pavers
1. Pavers used in the works were broken, chipped and cracked;
2. Mikescapes' workmanship was uneven, pavers were loose or became loose over time;
3. Grout washing not completed in initial stages of the works;
4. Grout washing completed in March 2007 was ineffective and failed to rectify the cracked pavers;
Driveway
1. The works completed on the driveway at the worksite were uneven;
2. Concrete laid on the surface of the driveway was uneven;
3. Pavers laid on driveway were uneven, chipped and broken;
4. Pavers on the driveway are not secure, and move when walked or driven on.
I have now received submissions on the issue of quantum from both parties.
The Pulitano's annex to their solicitor's covering letter the affidavit of Mr Jason Flynn, of Brisbane's Prestige Walls, sworn to on 13 May 2010, together with one exhibit consisting of a quotation to "renew paved driveway and make good".
Mikescapes submission consists of a solicitor's covering letter, a solicitor's affidavit sworn to on 14 May 2010, and an exhibit from ADA Paving and Landscaping, in the form of a paving quote.
Appropriate measure of quantum
Prior to receipt of the parties' submissions on quantum, and following the hearing on 15 April 2010, I advised the parties that it was my view that the appropriate measure of loss in this matter would be the cost of rectification,…
Continue reading Pulitano v Mikescapes Pty Ltd
Sign in free to access the full text
- AGLC
- Pulitano v Mikescapes Pty Ltd [2010] QCAT 248
- Case
- [2010] QCAT 248
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was the measure of damages for the defective work. The Applicants sought to establish the correct quantum of compensation, relying on precedents such as Bellgrove v Eldridge and Tabcorp Holdings Limited v Bowen Investments Pty Ltd. The Applicants argued that the Respondent's failure to deliver a building that met the contractual specifications entitled them to full rectification costs. The Respondent, however, contended that the Applicants' claims were excessive and not in line with the actual extent of the defects. The court had to weigh the evidence and the applicable legal principles to determine a fair and reasonable compensation.
In its decision, the court examined the contractual obligations and the extent of the defects. The court found that the Respondent did indeed fail to meet the contractual standards, leading to identifiable defects that warranted rectification. The court then assessed the appropriate quantum of damages, taking into account the severity of the defects and the reasonable costs associated with their rectification. After reviewing the evidence, the court concluded that the Applicants were entitled to the sum of $12,012.00 as compensation for the defective work. The Respondent was ordered to pay this amount to the Applicants by 4:00 pm on Friday, 9 July 2010.
Orders
Orders of the court
The Respondent, Mikescapes Pty Ltd, to pay the Applicants’ Filip and Anna Pulitano, the sum of $12,012.00 no later than 4:00 pm on Friday, 9 July 2010.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.