| CITATION: | Lewis v Netcon Pty Ltd [2011] QCAT 295 |
| PARTIES: | Mrs Virginia Lewis |
| v | |
| Netcon Pty Ltd |
| APPLICATION NUMBER: | BDL214-10 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 31 March and 1 April 2011 |
| HEARD AT: | Cairns |
| DECISION OF: | Ms Joanne R Browne, Member |
| DELIVERED ON: | 29 June 2011 |
| DELIVERED AT: | Cairns |
| ORDERS MADE: | The Respondent pay to the Applicant the amount of $15,268.00 by 4.00pm on 25 July 2011. |
| CATCHWORDS: | Whether contract lawfully terminated – failure to pay final progress claims – due diligence – defective and incomplete work Section 77 Queensland Building Services Authority Act 1991 |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Mrs Virginia Lewis (self-represented) |
| RESPONDENT: | Mr Jack Welten appeared for Netcon Pty Ltd (self-represented) |
REASONS FOR DECISION
Introduction
Mrs Virginia Lewis engaged the services of Netcon Pty Ltd (“the Builder”) to conduct renovation work to her house at 90 MacIlwraith Street, Manoora (“the house”). The renovation work was performed by Mr Jack Welten and his son Mr Michael Welten (Michael) who are both directors of Netcon Pty Ltd. Mrs Lewis lived in her house throughout the renovations. The Builder was in the course of completing the renovation works at the house when this dispute arose. The essence of the dispute was whether the work performed by the Builder was satisfactory and whether Mrs Lewis owed the Builder money for work performed.
The work performed by the Builder was to be completed in three (3) stages and for the purposes of section 17A of the Domestic Building Contracts Act 2000 (“the DBCA”), the domestic building work carried out by the Builder is taken to be a single contract. Mrs Lewis informed the Tribunal at the commencement of the hearing that she had not been provided with a copy of the standard terms and general conditions of the contract despite a direction being made that Netcon Pty Ltd provide a complete copy of the contract. Mr Welten provided a copy of the standard terms and general conditions to Mrs Lewis and the Tribunal at the hearing however the copy of the standard terms provided was incomplete.
The parties signed three (3) Master Builders Minor Works contracts in respect of the following renovation works at the house:
i) Balcony – the contract was signed on 4 June 2009 and the works to commence on 22 June 2009. The works to be performed were described “as per drawings V2009 – OT04 dated 17-04-09 proposed balcony only” to be completed by 1 September 2009 in the amount of $47,288.00. The work was to be performed in “stages” including laying the deck, laying the roof, hand rails and soffit.
ii) Downstairs – the contract was signed on 10 August 2009 and the works to commence on 12 August 2009. The works to be performed were described as “renovations to downstairs area including stairs” with work to be completed in stages (including frame, lockup) by 7 October 2009 in the amount of $30,900.00.
iii) Upstairs – the contract was…
Continue reading Lewis v Netcon Pty Ltd
Sign in free to access the full text
- AGLC
- Lewis v Netcon Pty Ltd [2011] QCAT 295
- Case
- [2011] QCAT 295
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the tribunal was whether the Respondent had lawfully terminated the contract. This involved determining whether the Respondent had exercised due diligence in assessing the final progress claims and whether there was a valid reason to terminate the contract due to defective and incomplete work. The tribunal also had to consider the effect of the termination on the Applicant's entitlement to payment for the final progress claims.
The tribunal found that the Respondent had not exercised due diligence in assessing the final progress claims. It was determined that the Respondent had not provided adequate reasons for rejecting the final progress claims and had failed to properly account for the defective and incomplete work. The tribunal held that the termination of the contract was therefore unlawful. As a result, the tribunal ordered the Respondent to pay the Applicant the amount of $15,268.00 by 4.00pm on 25 July 2011.
Orders
Orders of the court
The Respondent pay to the Applicant the amount of $15,268.00 by 4.00pm on 25 July 2011.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.