LAND COURT OF QUEENSLAND
CITATION: Pryce v Struber & Anor [2016] QLC 1 PARTIES: Malcolm Scott Pryce
(applicant)v Stephen Struber and Dianne Wilson-Struber
(respondents)FILE NO:
MRA029-15 PROCEEDINGS: Determination of compensation payable for grant of mining leases. DELIVERED ON: 14 January 2016 DELIVERED AT: Brisbane HEARD ON: Submissions closed 30 November 2015 HEARD AT: Heard on the papers JUDICIAL REGISTRAR: G J Smith
ORDERS: 1. In respect of ML 20719 compensation is determined in the total sum of $1130.00 per annum.
2. The miner pay compensation to the Public Trustee of Queensland on behalf of the landowners the amount set out in order 1 within two months from notification of the issue of the mining lease by the Department of Natural Resources and Mines and thereafter on the anniversary of the renewal of the mining lease.
CATCHWORDS: MINING LEASE – grant – access – determination of compensation – use of Court judgments for determination purposes.
Mineral Resources Act 1989, ss 279, 281
Public Trustee Act 1978 Part 7Aurelius v Terry [2010] QLC 0010
Eacham Abrasive Blasting Pty Ltd v Gundersen & Anor [2014] QLC 38
Fitzgerald & Anor v Struber & Ors [2014] QLC 0029Fitzgerald & Anor v Struber & Anor [2009] QLC 0076
Kelly v Struber & Ors [2012] QLC 0074
Palmer River Pty Ltd v Kingsley [2011] QLC 0019
Pryce v Struber [2013] QLC 32Saxby v Struber & Ors [2012] QLC 0049
Unimin Australia Limited v Freeman [2007] QLC 76
Wills v Minerva Coal Pty Ltd [No.2] (1998) 19 QCLR 297
APPEARANCES:
Not applicable
These proceedings concern a referral to the Land Court by the Chief Executive, Department of Natural Resources and Mines pursuant to s 279(5) of the Mineral Resources Act 1989 (MRA) for the determination of compensation in respect of the grant of mining lease 20719. The referral was filed in the Land Court on 20 January 2015.
Background
The applicant, Malcolm Scott Pryce, (the miner) seeks the grant of mining lease ML 20719. The Mining Lease Area of 94.3914 ha and a 28 km access track is situated on land described as Lot 14 on SP250040. This property, known as the Palmerville Station, is owned by the respondents Stephen Struber and Dianne Wilson Struber (the landowners).
The property is located in the Cook Shire Local Government area and is used for grazing purposes.
The specific Land Court references and individual lease and tenure details are set out as follows:
Court Reference Tenure ID Area Term Lease Purpose MRA029-15 20719 94.3914 ha 15 years Goldmining
On 29 September 2014 a Certificate of Application for Mining Lease 20719 was issued by the Mining Registrar at Mareeba.
Relevant Legislation
Section 279 of the MRA provides that a mining lease shall not be granted or renewed unless an agreement in relation to compensation has been filed or, in the absence of such an agreement, a determination of compensation has…
Continue reading Pryce v Struber
Sign in free to access the full text
- AGLC
- Pryce v Struber [2016] QLC 1
- Case
- [2016] QLC 1
- Decision Date
CaseChat Overview and Summary
The court was required to interpret the relevant provisions of the Mining Act and determine the appropriate annual compensation payable. This involved considering the use of previous court judgments in similar matters to determine a fair compensation amount. The court found that the compensation should be set at $1130.00 per annum, based on the precedent set in earlier judgments.
The court held that the compensation should be paid to the Public Trustee of Queensland on behalf of the landowners. This payment is to be made within two months of the mining lease being issued by the Department of Natural Resources and Mines, and subsequently on the anniversary of the renewal of the mining lease. The court's decision was based on a careful consideration of the relevant legislation and previous judicial decisions.
Orders
Orders of the court
1. In respect of ML 20719 compensation is determined in the total sum of $1130.00 per annum.
2. The miner pay compensation to the Public Trustee of Queensland on behalf of the landowners the amount set out in order 1 within two months from notification of the issue of the mining lease by the Department of Natural Resources and Mines and thereafter on the anniversary of the renewal of the mining lease.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.