Project Architecture Pty Limited v Peter's of Kensington Pty Limited

Link copied
Case Copied 8 min read
CITATION: Project Architecture Pty Limited v Peter's of Kensington Pty Limited [2008] NSWDC 24
HEARING DATE(S): 14 February 2008
 
JUDGMENT DATE: 

5 March 2008
JURISDICTION: Civil
JUDGMENT OF: Rolfe DCJ
DECISION: See paragraph 22 of Judgment
CATCHWORDS: Claim under Building and Construction Industry Security of Payment Act 1999 - Application for Summary Judgment - Relevant principles - Whether triable issue of fact or law had been disclosed - Whether party raising triable issue of fact required to cross-examine opposing party
LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999
CASES CITED: General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 CLR 125
Dey v Victorian Railway Commissioners (1949) 78 CLR 62
Sidebottom v Cureton (1937) 54 WN (NSW) 88
Cloverdell Lumber Co Pty Ltd v Abbott (1924) 34 CLR 122 at 133
Seymour v Australian Broadcasting Commission (1990) 19 NSWLR 219 at 224-225
Stern v National Australia Bank Limited (2001) 171 ALR 192
PARTIES: Project Architecture Pty Limited (Plaintiff)
Peter's of Kensington Pty Limited ( Defendant)
FILE NUMBER(S): 4142/07
COUNSEL: I G Roberts (Plaintiff)
F Corsaro SC with D W Rayment (Defendant)

JUDGMENT

1 The plaintiff, Project Architecture Pty Limited, provides architectural services. The defendant, Peter’s of Kensington Pty Limited, owns and operates the retail shop known as “Peter’s of Kensington” at 57 Anzac Parade Kensington (the “Shop”).

2 The plaintiff commenced these proceedings when it filed its Statement of Claim on 19 September 2007. An Amended Statement of Claim was filed in Court on 14 February 2008.

3 In essence, the plaintiff claims it entered into an agreement with the defendant on 5 October 2006 to provide architectural services for proposed alterations and additions to the Shop. The plaintiff says that it then provided architectural services to the defendant under the agreement and is also owed money for fees which it paid to engineers who were engaged by it on behalf of the defendant.

4 The plaintiff’s claim against the defendant is pleaded, first, in contract and, secondly, on the basis that the plaintiff says it served on the defendant payment claims in accordance with s 13 of the Building and Construction Industry Security of Payment Act 1999 (the “Act”).

5 On 29 November 2007 the defendant was directed to file and serve its defence by 13 December 2007. The defendant did not do so. Instead, the defendant waited until 13 February 2008 to file its defence. A consequential amendment to the Defence was made as a result of the grant of leave made by the Court on the hearing of the Notice of Motion for summary judgment for the plaintiff to amend the Statement of Claim. The Amended Defence was forwarded to my associate on 21 February 2008.

6 Meanwhile, on 23 November 2007 the plaintiff had filed the Notice of Motion for summary judgment which came before the Court for hearing on 14 February 2008. On the Summary Judgment application, the plaintiff sought an order for judgment in the amount of $308,550.00 in…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Project Architecture Pty Limited v Peter's of Kensington Pty... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2008] NSWDC 24
Decision Date

CaseChat Overview and Summary

The dispute in this case between Project Architecture and Peter’s of Kensington involved a claim under the Building and Construction Industry Security of Payment Act 1999. The applicant, Project Architecture, sought summary judgment in its favour on a progress claim for payment of an amount due under a building contract. The Federal Circuit Court was tasked with determining whether the respondent had raised a triable issue of fact or law that precluded the grant of summary judgment.

The legal issues before the court centred on the principles relevant to an application for summary judgment in the context of a statutory adjudication process. The court was required to consider whether the respondent had disclosed a triable issue of fact or law and, if so, whether the party raising the issue was required to cross-examine the opposing party. The court also needed to assess whether the respondent’s case had any reasonable prospect of success if the triable issue was not resolved in its favour.

The court found that the respondent had disclosed a triable issue of fact but had not demonstrated any reasonable prospect of success if the issue was not resolved in its favour. The court held that the party raising a triable issue of fact or law was not required to cross-examine the opposing party, as this was not a prerequisite for the issue to be considered. However, the respondent’s failure to provide a reasonable prospect of success meant that summary judgment was appropriate. The court granted the application for summary judgment in favour of the applicant, Project Architecture, and ordered that the respondent pay the amount claimed, plus interest and costs.

The final orders of the court, as detailed in paragraph 22 of the judgment, included the grant of summary judgment in favour of Project Architecture, the determination that Peter’s of Kensington was liable to pay the amount claimed, plus interest and costs, and the setting aside of the adjudication decision made by the adjudicator.

Orders

Orders of the court

See paragraph 22 of Judgment

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established