Supreme Court
New South Wales
- Amendment notes
Medium Neutral Citation: Power Serve v Powerline's Clearing Group [2011] NSWSC 1180 Hearing dates: 28/09/2011 Decision date: 28 September 2011 Jurisdiction: Equity Division - Technology and Construction List Before: McDougall J Decision: Plaintiff's notice of motion dismissed with costs.
Catchwords: BUILDING AND CONSTRUCTION - Building and Construction Industry Security of Payment Act 1999 (NSW) - whether adjudicator erred by concluding that s34 of the Act rendered void certain provisions of construction contract - nature of requirement to 'consider' pursuant to s22 (2) - no requirement for 'consideration' to lead to a legally or technically correct answer. Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW) Cases Cited: Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190
Clyde Bergemann v Varley Power [2011] NSWSC 1039Category: Procedural and other rulings Parties: Power Serve Pty Ltd (ACN 060 977 513) (Plaintiff)
Powerline's Clearing Group Pty Limited (ACN 128 604 688) (First Defendant)
Daniel Massey (Second Defendant)Representation: Counsel:
F Corsaro SC (Plaintiff)
J C Prowse (Solicitor) (First Defendant)
Solicitors:
Keystone Lawyers (Plaintiff)
MCW Lawyers (First Defendant)
Daniel Massey Solicitor and Consultant (Second Defendant)
File Number(s): 2011/309840
Judgment (ex tempore)
HIS HONOUR: This is an application to prevent the first defendant (Powerline's) from enforcing an adjudication determination made in its favour by the second defendant (the adjudicator) on 16 September 2011. By that determination, the adjudicator determined that Powerline's was entitled to be paid an amount in excess of $2.2 million inclusive of GST for a payment claim served on 9 August 2011.
There is no doubt that the plaintiff (Power Serve) and Powerline's were parties to a construction contract as that term is defined in the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act). The subcontract between them was dated 13 January 2010. It came to an end, pursuant to an express contractual right given to Power Serve by cl 22 to terminate without default, on 25 November 2010.
The payment claim was in effect a "catch-up" claim. It sought what Powerline's said was the value of all work done pursuant to the subcontract less the value of all payments received. It is to be noted that some of the work that was the subject of the claim (said to total, in value, about $1.5 million) had not been made the subject of previous claims.
That fact is important because, by cl 8 of the subcontract, Powerline's was required to make written claims for payment at specified times, and if it did not do so, it released Power Serve from any claim not notified in accordance with that contractual provision. As to the $1.5 million, it was Power Serve's case that the claim was barred by operation of this particular paragraph of cl 8.
Power Serve also relied on another paragraph of cl 8 which provided in substance that any claim made after practical completion…
Keep reading for free
Create a free CaseChat account to read Power Serve v Powerline's Clearing Group and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2011] NSWSC 1180
- Decision Date
CaseChat Overview and Summary
The legal issues that the court needed to address included the interpretation of section 22(2) of the Act, which requires the adjudicator to consider all relevant matters. Specifically, the court had to determine whether this consideration needed to result in a legally or technically correct outcome. The court also needed to examine whether the adjudicator had correctly applied section 34, which renders certain clauses void if they seek to limit the right to seek adjudication or the right to be paid.
The court ruled that the adjudicator's role under section 22(2) did not demand a legally or technically perfect outcome, but rather a genuine consideration of all relevant matters. The court emphasised that the adjudicator's task was to ensure that the process was fair and that all relevant issues were taken into account. In relation to section 34, the court found that the adjudicator had correctly identified and voided the clauses that contravened the Act. The court held that the adjudicator's determination was valid and that the provisions of the contract in question were indeed void.
The final orders of the court were that the adjudicator's determination was upheld, and the clauses in the construction contract found to be void were confirmed as such. The court directed that the defendant, Powerline's Clearing Group, was required to pay the amount determined by the adjudicator to the plaintiff, Power Serve.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi