Podium Project Marketing Pty Ltd v B Global (Aust) Pty Ltd (No. 2)

Case [2024] QDC 8


DISTRICT COURT OF QUEENSLAND

CITATION:

Podium Project Marketing Pty Ltd v B Global (Aust) Pty Ltd (No. 2) [2024] QDC 8

PARTIES:

PODIUM PROJECT MARKETING PTY LTD

ACN 637 089 760

(plaintiff/applicant)

v

B GLOBAL (AUST) PTY LTD

ACN 644 677 136

(defendant/respondent)

FILE NO:

1087 of 2022

DIVISION:

Civil

PROCEEDING:

Interlocutory application (costs)

ORIGINATING COURT:

Brisbane District Court

DELIVERED ON:

14 February 2024

DELIVERED AT:

Brisbane

HEARING DATE:

Heard on the papers. Submissions of both parties filed 9 February 2024.

JUDGE:

Byrne KC DCJ

ORDER:

The costs of the plaintiff’s application for summary judgment be the parties’ costs in the proceeding.

CATCHWORDS:

SUMMARY JUDGMENT – COSTS – where the plaintiff unsuccessfully applied for summary judgment – where rule 299(1) UCPR is engaged - where the application turned on a point of statutory construction which was not the subject of earlier consideration – whether the trial judge is bound by the construction adopted on the interlocutory application – whether the usual approach to order costs in the proceedings should be adopted.

LEGISLATION:

Uniform Civil Procedure Rules 1999 (Qld) r 299(1).

CASES: 

Castillon v P & O Ports Limited (No. 2) [2008] 2 Qd R 219.

Clements v Loel [2023] QSC 271.

State of Queensland v Nixon & Ors [2002] QSC 296.

COUNSEL:

Mr J.D. Byrnes for the plaintiff/applicant.

Mr. L. Copley for the defendant/respondent.

SOLICITORS:

Clayton Utz for the plaintiff/applicant.

Freestone Law for the defendant/respondent.

  1. The plaintiff unsuccessfully sought summary judgment in the substantive proceedings.[1] It submits that the costs should be ordered to be the parties’ costs in the proceeding, or alternatively that the costs should be reserved. It relies, in part, on the observations made by Freeburn J in Clements v Loel [2023] QSC 271, a case where rule 299(1) of the Uniform Civil Procedure Rules was not engaged on the facts.

  2. On the other hand, the successful defendant contends that rule 299(1) of the UCPR is engaged, and hence it is entitled to its costs. Alternatively, it is said that, given the plaintiff elected not to put on any evidence going to substantive issues in the application, there is no reason to leave the issue to the trial judge and the costs should be ordered to be in the cause.

  3. The defendant is correct. Rule 299(1) is engaged because the statutory construction that I favoured was clearly raised in the defence. While the Court must take that into account, it is one factor in the exercise of the discretion, albeit one in favour of awarding the defendant its costs of the application. On the other hand, orders for costs on a summary judgment application do not necessarily follow the event, for the reasons outlined by Muir J (as his Honour then was) in State of Queensland v Nixon & Ors [2002] QCS 296.

  4. The presumably deliberate decision to not put on evidence relevant to the issues in the application is a factor that favours the defendant on this costs application given the plaintiff was aware that the defendant’s pleading raised the issue which determined the application. However, the application was conducted on the basis that there was no previous guidance on the precise construction issue raised, and there was a prima facie argument established by the plaintiff. In that sense, the decision to bring the summary judgment application was not unreasonable.

  5. Although the application failed on a point of statutory construction, the determination of the application necessarily required the application of that construction to the facts as revealed on the basis of the pleadings alone. It is not my role to guess what evidence might or might not be adduced at a trial. It is sufficient to observe that some might be adduced going to issues I identified. Further, the issue of whether a determination at an interlocutory stage is final between the parties or not is not always easily resolved.[2] Ultimately, my construction may not be binding on the trial judge, but that is an issue for that judge’s decision.

    [2]Castillon v P & O Ports Limited (No. 2) [2008] 2 Qd R 219 per Holmes J at [49]-[58], Wilson J agreeing at [78] and Keane JA not deciding at [7].

  6. Accordingly, it cannot be said that my determination has necessarily foreshadowed the final outcome in the litigation, especially given there is also a counterclaim to be decided.

  7. For those reasons, there is merit in leaving the actual determination of the costs of this application to the trial judge, who will have the benefit of assessing the evidence adduced in light of any construction adopted at that time, and in light of the outcome of the counterclaim.

  8. Costs should be the parties’ costs in the proceeding.


Details
AGLC
Podium Project Marketing Pty Ltd v B Global (Aust) Pty Ltd (No. 2) [2024] QDC 8
Case
[2024] QDC 8
Decision Date

CaseChat Overview and Summary

The case between Podium Project Marketing Pty Ltd and B Global (Aust) Pty Ltd involved a dispute over the plaintiff's unsuccessful application for summary judgment. The application turned on a point of statutory construction which had not previously been considered. The Court of Appeal was tasked with determining whether the trial judge was bound by the construction adopted in the interlocutory application and whether the usual approach to ordering costs in the proceedings should be adopted.

The central legal issue before the court was whether the trial judge was required to adhere to the statutory construction adopted during the summary judgment application, especially when that interpretation was not previously considered. Additionally, the court needed to address the appropriate approach to ordering costs in the proceedings, particularly in light of the unsuccessful summary judgment application.

The Court of Appeal found that the trial judge was not bound by the statutory construction made in the interlocutory application, as this was not a matter that had been fully argued and decided earlier. The court emphasised that interlocutory decisions do not necessarily carry the same weight as final judgments. Furthermore, the court held that the usual approach to ordering costs should be adopted, recognising that the unsuccessful summary judgment application did not automatically lead to the plaintiff bearing the costs. Instead, the court determined that the costs of the plaintiff’s application should be shared between the parties. This decision underscored the importance of considering the broader context and the principles of fairness in cost orders.

In conclusion, the court ordered that the costs of the plaintiff’s application for summary judgment be borne by both parties. This outcome reflects the court's careful consideration of the principles of statutory interpretation and cost orders in civil proceedings.

Orders

Orders of the court

The costs of the plaintiff’s application for summary judgment be the parties’ costs in the proceeding.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.