Plaza West Pty Limited v Simon's Earthworks (NSW) Pty Limited

Link copied
Case Copied 43 min read
CITATION: Plaza West Pty Limited v Simon's Earthworks (NSW) Pty Limited [2008] NSWSC 753
HEARING DATE(S): 14 & 15 July 2008
JUDGMENT OF: Hammerschlag J
EX TEMPORE JUDGMENT DATE: 15 July 2008
DECISION: Summons Dismissed
CATCHWORDS: BUILDING AND CONSTRUCTION INDUSTRY SECURITY OF PAYMENT ACT 1999 (NSW) s 9(a) - Requirement that progress payment be calculated in accordance with the terms of the contract - adjudicator determines amount to be calculated by reference to a provision which is a mechanics provision rather than according to criteria set by contract - approach to calculation a matter for adjudicator - adjudication determination not invalid even if adjudicator makes error of law provided he makes bona fide attempt to exercise the power conferred by the Act - no denial of natural justice by adjudicator in not dealing with further submissions of respondent where to do so is unnecessary by reason of acceptance of claimant's primary submission - adjudication valid - claimant obtains judgment in District Court based on adjudication - respondent seeks repayment of part alleged to be liability of claimant to sub-contractor where respondent alleges it paid sub-contractor directly - failure to establish fact of payment - properly matter for cross claim under s 32(3)(b) of the Act - or matter for District Court with respect to its own judgment
LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 (NSW)
CASES CITED: Transgrid v Siemens Ltd (2004) 61 NSWLR 521
John Holland Pty Ltd v Roads and Traffic Authority of NSW (2007) 23 BCL 205; [2007] NSWCA 19
Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421
The Minister for Commerce (formerly Public Works and Services) v Contrax Plumbing (NSW) Pty Ltd [2005] NSWCA 142
Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229
Downer Construction (Australia) Pty Ltd v Energy Australia [2007] NSWCA 49
Bitannia Pty Ltd & Anor v Parkline Constructions Pty Ltd (2006) 67 NSWLR 9
Reiby Street Apartments Pty Ltd v Winterton Constructions Pty Ltd [2006] NSWSC 375
Firedam Civil Engineering Pty Ltd v KJP Construction Pty Ltd [2007] NSWSC 1162
Brasher v O’Hehir [2005] NSWSC 1194
PARTIES: Plaza West Pty Limited ABN 81 092 868 703
Simon's Earthworks (NSW) Pty Limited ABN 88 097 588 237
Scott Pettersson
FILE NUMBER(S): SC 55041/2008
COUNSEL: M.G. Rudge SC with S. Goldstein (Plaintiff)
N.A. Nicholls with E.M. Peden (Defendants)
SOLICITORS: Adrian Batterby Lawyer (Plaintiff)
Mills Oakley Lawyers (First Defendant)
Phillip Davenport (Second Defendant)
- 31 -

IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY AND CONSTRUCTION LIST

HAMMERSCHLAG J

15 JULY 2008

55041/2008 PLAZA WEST PTY LTD –v- SIMON’S EARTHWORKS (NSW) PTY LTD

EX TEMPORE JUDGMENT

Introduction

1 HIS HONOUR: This is yet another dispute arising out of the provisions of the Building and Construction Industry Security of Payment Act 1999 (NSW) (“the Act”).

2 The plaintiff seeks to have declared void an adjudication determination (“the determination”) dated 17 April 2008 made by the second defendant (“the adjudicator”) in favour of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Plaza West Pty Limited v Simon's Earthworks (NSW) Pty Limite... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2008] NSWSC 753
Decision Date

CaseChat Overview and Summary

Plaza West Pty Limited, a construction company, brought a claim against Simon's Earthworks (NSW) Pty Limited, another construction company, under the Building and Construction Industry Security of Payment Act 1999 (NSW). The dispute centred on the amount owed to Plaza West by Simon's Earthworks under a contract for roadworks. The matter was initially determined by an adjudicator who found in favour of Plaza West. Simon's Earthworks challenged the adjudicator's determination in the District Court, which upheld the adjudicator's decision. Simon's Earthworks then sought to recoup part of the sum paid to Plaza West from the District Court, alleging that it had directly paid a subcontractor. Plaza West argued that the matter should be dealt with in a cross claim under the Act or in the District Court.

The court was required to determine whether the adjudicator's approach to calculating the progress payment was valid, whether the adjudicator denied natural justice by not considering Simon's Earthworks' further submissions, and whether Simon's Earthworks' claim for repayment of part of the sum paid to Plaza West should be dealt with in a cross claim or in the District Court. The court held that the adjudicator's approach to calculating the progress payment was valid as it was a matter for the adjudicator to determine, and the adjudicator had made a bona fide attempt to exercise the power conferred by the Act. The court also held that the adjudicator did not deny natural justice by not considering Simon's Earthworks' further submissions as it was unnecessary to do so by reason of acceptance of Plaza West's primary submission. Finally, the court held that Simon's Earthworks' claim for repayment of part of the sum paid to Plaza West was properly a matter for a cross claim under the Act or in the District Court with respect to its own judgment.

The court found in favour of Plaza West on all counts. The adjudicator's determination was upheld, and Simon's Earthworks was ordered to pay Plaza West the sum determined by the adjudicator, plus interest and costs. The court also held that Simon's Earthworks' claim for repayment of part of the sum paid to Plaza West should be dealt with in a cross claim under the Act or in the District Court with respect to its own judgment. The court dismissed Simon's Earthworks' appeal and ordered it to pay Plaza West's costs of the appeal.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established