CITATION: Planet Build (NSW) Pty. Limited v. Lassgol Pty. Limited [2000] NSWSC 861 revised - 4/09/2000 CURRENT JURISDICTION: Equity Division FILE NUMBER(S): SC 3360/00 HEARING DATE(S): 18/08/00 JUDGMENT DATE: 30 August 2000 PARTIES :
Planet Build (NSW) Pty. Limited - plaintiff
Lassgol Pty. Limited - defendantJUDGMENT OF: Hodgson CJinEq at 1
COUNSEL : M.J. Walsh for plaintiff
A. Henskens for defendantSOLICITORS: Tress Cocks & Maddox, Sydney for plaintiff
Colin Biggers & Paisley, Sydney for defendantCATCHWORDS: CONTRACTS - Building, engineering and related contracts - Retention moneys and security - Performance bond - Effect of Superintendent's certificates. - INJUNCTIONS - Interlocutory injuncitons - Balance of convenience. DECISION: See end of judgment
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISIONCORAM: HODGSON, CJ in Eq.
Wednesday 30th August 2000
NO. 3360 OF 2000
PLANET BUILD (NSW) PTY. LIMITED V. LASSGOL PTY. LIMITEDJUDGMENT
1 Pursuant to leave given in my judgment of 9th August 2000, Lassgol has sought to present further argument on the interlocutory application. Also, Planet Build has filed an Amended Summons, and also a Notice of Motion, in which it seeks inter alia summary judgment for $259,107.00 or alternatively, $114,421.00. 2 There is also further evidence, of the following matters. 3 On 4th August 2000, the Superintendent issued Payment Certificate 46, showing $353,307.00 due from Planet Build to Lassgol. The changes from the certificate issued on 19th July 2000 were: first, the deduction for non-complying work was increased from $267,000.00 to $359,510.00; and second, $225,000.00 liquidated damages for late completion was also taken into account. 4 On 8th August 2000, Lassgol gave a further notice to Planet Build that it intended to call on the Performance Bond. 5 On 9th August 2000, Planet Build purported to terminate the contract. 6 On 10th August 2000, Lassgol requested Planet Build to cease its suspension of work and to complete its obligations under the contract. 7 On 14th August 2000, Planet Build went into voluntary administration. 8 On 17th August 2000, the Superintendent issued Payment Certificate 47 showing $313,000.00 due from Planet Build to Lassgol. This certificate appears to overlap Payment Certificate 46, because the $313,000.00 is made up of $68,000.00 of further non-complying work, and $245,000.00 liquidated damages for late completion. Accordingly, the amount certified additional to Payment Certificate 46 seems to be the $68,000.00, plus a further $20,000.00 of liquidated damages; and the total amount certified by the two certificates to be due to Lassgol would appear to be $441,307.00. 9 On 18th August 2000, Marrickville Council gave notice that it proposed to give Planet Build an order under s.121H of the Environmental Planning & Assessment Act requiring it to do certain work on the property. 10 It is common ground that the District Court attachment order, referred to in paragraph 47 of the earlier judgment, is now discharged. 11 There is further evidence from Planet Build disputing all of the alleged non-complying work; and also evidence in support of an allegation that the Superintendent is…
Keep reading for free
Create a free CaseChat account to read Planet Build (NSW) Pty. Limited v Lassgol Pty. Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2000] NSWSC 861
- Decision Date
CaseChat Overview and Summary
In Planet Build (NSW) Pty. Limited v Lassgol Pty. Limited, the dispute arose between a subcontractor and a principal contractor. The subcontractor, Planet Build, sought relief from an interlocutory injunction and argued for the enforcement of a performance bond. The case was heard in the Supreme Court of New South Wales.
The central legal issues addressed by the court involved the interpretation of the terms of the performance bond and the circumstances under which the subcontractor could enforce it. Specifically, the court had to determine the effect of the Superintendent's certificates on the subcontractor's right to claim under the bond. Additionally, the court considered whether an interlocutory injunction should be granted to prevent the principal contractor from transferring retention monies to a third party.
The court found that the terms of the performance bond were clear and provided that the subcontractor could claim if the principal contractor failed to make payment within a specified period. The court emphasised that the Superintendent's certificates did not negate the subcontractor's right to enforce the bond. Regarding the interlocutory injunction, the court considered the balance of convenience and concluded that an injunction was necessary to prevent the unjust enrichment of the third party and to preserve the rights of the parties involved.
The court issued an interlocutory injunction restraining the principal contractor from transferring the retention monies to the third party. The injunction aimed to maintain the status quo until the final determination of the merits of the case.
The central legal issues addressed by the court involved the interpretation of the terms of the performance bond and the circumstances under which the subcontractor could enforce it. Specifically, the court had to determine the effect of the Superintendent's certificates on the subcontractor's right to claim under the bond. Additionally, the court considered whether an interlocutory injunction should be granted to prevent the principal contractor from transferring retention monies to a third party.
The court found that the terms of the performance bond were clear and provided that the subcontractor could claim if the principal contractor failed to make payment within a specified period. The court emphasised that the Superintendent's certificates did not negate the subcontractor's right to enforce the bond. Regarding the interlocutory injunction, the court considered the balance of convenience and concluded that an injunction was necessary to prevent the unjust enrichment of the third party and to preserve the rights of the parties involved.
The court issued an interlocutory injunction restraining the principal contractor from transferring the retention monies to the third party. The injunction aimed to maintain the status quo until the final determination of the merits of the case.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi