Land and Environment Court
New South Wales
Medium Neutral Citation: Pisula & anor v Luttrell [2011] NSWLEC 1356 Hearing dates: 24 November 2011 Decision date: 13 December 2011 Jurisdiction: Class 2 Before: Galwey AC Decision: (1)Within 30 days of the dates of these orders, the Applicants are to obtain and provide to the Respondent three quotes for repairing the damaged section of the retaining wall, which is approximately 10 metres in length, to a similar standard and using similar material as the existing retaining wall.
(2)The Respondent has 7 days from receipt of quotes from the Applicant to respond to the Applicant with their choice of contractor otherwise the Applicant chooses the contractor.
(3)The repair works to the retaining wall are to be completed within 3 months of the date of these orders otherwise order 4 lapses.
(4)The Respondent is to reimburse the Applicants 30% of the cost of the works in order 1 within 21 days of the receipt of a tax invoice for the completed works.
Catchwords: TREES [NEIGHBOURS]; damage to property; tree already removed; compensation ordered. Legislation Cited: Trees (Disputes Between Neighbours) Act 2006
Interpretation Act 1987Cases Cited: Osborne v Hook [2008] NSWLEC 1231
Robson v Leischke [2008] NSWLEC 152
Smith & Hannaford v Zhang & Zhou [2011] NSWLEC 29
Timmins v Park [2011] NSWLEC 1308
Yang v Scerri [2007] NSWLEC 592Texts Cited: Review of the Trees (Disputes Between Neighbours) Act 2006 (NSW) November 2009 Category: Principal judgment Parties: L Pisula & G Pisula (Applicants)
G Luttrell (Respondent)Representation: John Kavanagh (Applicants)
Patrick Riordan (Respondent)
J A Kavanagh & Co
Thompson Cooper Lawyers
File Number(s): 20590 of 2011
JUDGMENT
ACTING COMMISSIONER: Two Strelitzia nicolai (Giant White Bird of Paradise) plants grew on the Respondent's property in Woronora Heights adjacent to the common boundary with the Applicants' property. Although the plants have been removed, the Applicants claim that the plants caused damage to a retaining wall on their land and, furthermore, that parts of the plants remaining in the ground may cause damage to their retaining wall in future.
The Applicants make this application pursuant to Part 2 s 7 of the Trees (Disputes Between Neighbours) Act 2006 (the Act). They seek the following orders:
(1) That the Respondent remedy, restrain or prevent further damage to property on land owned by the Applicants by trees situated on land owned by the Respondent.
(2) That the Respondent pay compensation to the Applicants for damage to the Applicants' property.
(3) That the damage payable by the Respondent, for removal and replacement of a brick retaining wall, replacement of soil and plants and hire of Acrow props, be a sum of $6,185.30.
(4) That the Respondent pay the Applicants' costs of these proceedings.
The Respondent's position is that he has always taken action when informed of damage and is therefore not liable for the damage.
History
As the Court needs to consider various matters outlined in s 12 of the Act, which will be discussed later, it is relevant…
Continue reading Pisula v Luttrell
Sign in free to access the full text
- AGLC
- Pisula v Luttrell [2011] NSWLEC 1356
- Case
- [2011] NSWLEC 1356
- Decision Date
CaseChat Overview and Summary
The legal issues that the court was required to address included determining who was responsible for obtaining quotes for the repair work, who had the right to choose the contractor, and how the costs of the repair work should be shared between the parties. The court needed to interpret the terms of any relevant agreements between the parties and consider the principles of equity and fairness in making its decision.
The court found that the responsibility for obtaining quotes for the repair work lay with the party who had caused the damage to the retaining wall. The court also determined that the party who caused the damage had the right to choose the contractor, unless they failed to do so within the specified timeframe, in which case the other party could select the contractor. Furthermore, the court ruled that the party who caused the damage should bear 30% of the cost of the repair work. Based on these findings, the court made several orders, including that the party who caused the damage must obtain quotes for the repair work within 30 days and that the other party has seven days to choose a contractor from those quotes, otherwise the party who caused the damage chooses the contractor. The repair works must be completed within three months of the date of the orders, and the party who caused the damage must reimburse the other party 30% of the cost of the works within 21 days of receiving a tax invoice for the completed works.
Orders
Orders of the court
(1)Within 30 days of the dates of these orders, the Applicants are to obtain and provide to the Respondent three quotes for repairing the damaged section of the retaining wall, which is approximately 10 metres in length, to a similar standard and using similar material as the existing retaining wall.
(2)The Respondent has 7 days from receipt of quotes from the Applicant to respond to the Applicant with their choice of contractor otherwise the Applicant chooses the contractor.
(3)The repair works to the retaining wall are to be completed within 3 months of the date of these orders otherwise order 4 lapses.
(4)The Respondent is to reimburse the Applicants 30% of the cost of the works in order 1 within 21 days of the receipt of a tax invoice for the completed works.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.