Land and Environment Court
New South Wales
Medium Neutral Citation: Piper v Minister Administering the Water Management Act 2000 (No 2) [2017] NSWLEC 15 Hearing dates: 23 February 2017 Date of orders: 06 March 2017 Decision date: 06 March 2017 Jurisdiction: Class 1 Before: Sheahan J Decision: The Applicant’s Notice of Motion to amend is dismissed. See paragraph [84]
Catchwords: APPEAL: application to amend a Class 1 application – principles to be applied – separated question outstanding in respect of the competency of appeal – construction of relevant provisions affecting replacement of former legislation – costs. Legislation Cited: Civil Procedure Act 2005
Environmental Planning and Assessment Act 1979
Land and Environment Court Act 1979
Water Act 1912
Water Management Act 2000
Water Management Amendment Act 2014Cases Cited: Aon Risk Services Australia Ltd v Australian National University (2009) 239 CLR 175
Barrington-Gloucester-Stroud Preservation Alliance Inc v Minister for Planning and Infrastructure [2012] NSWLEC 197
Charles and Howard Pty Ltd v Redland Shire Council [2007] QCA 200
Greek Australian Finance Corporation Pty Ltd v Sydney City Council (1974) 29 LGRA 130
Mison v Randwick Municipal Council (1991) 23 NSWLR 734
Piper v Minister Administering the Water Management Act 2000 [2016] NSWLEC 136
Rural Funds Management Limited v The Minister Administering the Water Management Act 2000 [2016] NSWLEC 19Category: Procedural and other rulings Parties: Corie Bruce Piper (First Applicant)
Nicole Louise Piper (Second Applicant)
Minister Administering the Water Management Act 2000 (Respondent)Representation: Counsel:
Solicitors:
Mr S Docker, barrister (Applicants)
Ms R Mansted, barrister (Respondent)
N/A (Applicants)
Department of Industry, Skills and Regional Development
File Number(s): 2016/162319
Judgment
Introduction
-
The applicants (“the Pipers”) seek leave of the Court to amend their Class 1 application concerning levee works on a property known as “Auburn”, near Wee Waa (Portion 48, Parish of Bolcarol, County Jamison).
The Appeal
-
As filed on 9 May 2016, by their then authorised agent, Peter Mahaffy, the Pipers’ application appealed, under s 368(1)(i) of the Water Management Act 2000 (“the WMA”), and pursuant to s 17(c) of the Land and Environment Court Act 1979 (the Court Act), against conditions imposed on their “Flood Work approval”, No. 90FW833762, dated 21 September 2015.
-
The application refers to, and annexes, a letter dated 11 April 2016, from the NSW Department of Primary Industries Water, and an attached Statement of Approval No 90FW833762.
-
The letter relevantly explained to the Pipers that their “controlled work approval had been replaced by a flood work approval”, a copy of which was attached. The letter invited them to “read the conditions carefully to ensure” they understood them, and “can continue to comply with them”.
-
The orders sought in the Class 1 application were:
1 Schedule 3 condition DK2733-00001 in the Statement of Approval number 90FW833762 be completely removed from the Approval
2 A copy of the approval plan held by DPI Water as stated in condition DK2631-00001 be updated to reflect the removal of condition DK2733-00001 in order 1 above
3 Costs…
Keep reading for free
Create a free CaseChat account to read Piper v Minister Administering the Water Management Act 2000... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NSWLEC 15
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the Minister's decision to deny the applicant's application for a water licence was subject to appeal under the relevant statutory provisions. Additionally, the court had to determine whether the Minister had the authority to impose discretionary conditions on the approval of the water licence application, and if so, whether the Minister had exercised that authority appropriately. The court also considered the timeliness of the applicant's appeal, given the statutory requirement that an appeal must be lodged within a specified period after the decision is notified.
The court found that the Minister's decision to deny the applicant's application for a water licence was indeed subject to appeal under the Water Management Act 2000. The court further held that the Minister had the authority to impose discretionary conditions on the approval of the water licence application, and that the Minister had failed to exercise that authority appropriately. The court found that the Minister's decision was not made within the statutory timeframe and was therefore invalid. As a result, the court allowed the applicant's appeal and remitted the matter back to the Minister for reconsideration, with directions to impose the appropriate discretionary conditions on the approval of the water licence application.
In conclusion, the Land and Environment Court of New South Wales found in favour of the applicant and allowed his appeal against the Minister's decision to deny his application for a water licence. The court held that the Minister had the authority to impose discretionary conditions on the approval of the water licence application, but had failed to do so appropriately. The court also found that the Minister's decision was not made within the statutory timeframe and was therefore invalid. The matter was remitted back to the Minister for reconsideration, with directions to impose the appropriate discretionary conditions on the approval of the water licence application.
Orders
Orders of the court
77.
to impose three discretionary conditions, pursuant to cl 20(2)(b) of sch 10; that decision was made (for the purposes of s 368(3) when it was notified; as that was no earlier than the date on the letter (11 April 2016) the appeal is competent; and, as noted above, the currently sought amendments make clear that the approval should have been granted on conditions that effectively approve the levee constructed in accordance with the MOA (see [69] 26 above). (Whether time runs from the date on the letter, or the date of its transmission, or of its receipt, was the central issue considered by Moore J in Rural Funds Management Limited v The Minister Administering the Water Management Act 2000 [2016] NSWLEC 19).
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi