Perkins v Cleveland Glass and Aluminium Pty Ltd

Link copied
Case Copied 20 min read

DISTRICT COURT OF QUEENSLAND

CITATION:

Perkins v Cleveland Glass & Aluminium Pty Ltd [2011] QDC 302

PARTIES:

Benjamin PERKINS

(Applicant)

-v-

CLEVELAND GLASS & ALUMINIUM PTY LTD

(Respondent)

FILE NO/S:

D152 of 2011

DIVISION:

Civil

PROCEEDING:

Originating Application

ORIGINATING COURT:

District Court, Townsville

DELIVERED ON:

06 December 2011

DELIVERED AT:

Townsville

HEARING DATE:

08 September 2011

JUDGE:

Durward SC DCJ

ORDERS:

1 Application to extend the limitation period is granted.

2 Respondent to pay the applicant’s costs of and incidental to the application on the standard basis.

CATCHWORDS:

LIMITATION OF ACTIONS – EXTENSION OR POSTPONEMENT OF LIMITATION PERIODS – EXTENSION OF TIME IN PERSONAL INJURIES MATTERS - KNOWLEDGE OF MATERIAL FACTS OF A DECISIVE CHARACTER – whether the facts were within the applicant’s means of knowledge before the critical date – where applicant had knowledge of material facts – where the decisive character of the material facts did not crystallise until the occurrence of three significant events after the critical date – where the applicant discharged the onus of proof – where the respondent was not prejudiced.   

LEGISLATION:

Limitation of Actions Act 1974 (Qld) ss 30&31; Workers' Compensation & Rehabilitation Act 2003 (Qld) s 302.

CASES:

Baillie v Creber [2010] QSC 52; Hargans v Kemenes & Suncorp [2011] QSC 15; Honour v Faminco Mining Services Pty Ltd [2009] QCA 352; Bolitho v Talbot & Anor [2010] QSC 415; Spain v Dipompo Jacs Constructions Pty Ltd & Anor [2009] QCA 323; Sugden v Crawford (1989) 1 Qd R 683; Moriarty v Sunbeam Corporation Limited (1988) 2 Qd R 325; Queensland v Stephenson (2006) 226 CLR 197; NF v State of Queensland [2005] QCA 110; Gillespie v Swift Australia Pty Ltd [2009] QCA 316; Healy v Femdale (1993) QCA 210; Greenhalgh v Bacas Training Limited & Ors [2007] QCA 327; Castillon v P & O Ports Ltd [2007] QCA 364; Watters v Queensland Rail [2001] 1 Qd R 448; HWC v The Corporation of the Synod of the Diocese of Brisbane [2009] QCA 168; Dick v University of Queensland [2000] 2 Qd R 476.

COUNSEL:

DM Cormack for the Applicant

WFS Elliott for the Respondent

SOLICITORS:

Connolly Suthers Lawyers as t/a for Hall Payne Lawyers for the Applicant

Roberts Nehmer McKee for the Respondent

  1. The applicant, so far as is relevant, sustained an injury to his lower back, which was subsequently aggravated.  This lower back injury is the subject of his application to extend the limitation period in his personal injury claim to 13 August 2010.

  1. The application is made pursuant to section 31 of the Limitations of Actions Act 1974 ("the Act"). 

Legislation

  1. Section 302 of the Workers' Compensation & Rehabilitation Act 2003 (Qld) provides for an alteration of the traditional period of limitation of three years within which to bring a proceeding for damages for personal injury:  see section 11 of the Act. 

  1. Proceedings may be brought by a claimant after the expiration of the limitation period if…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Perkins v Cleveland Glass and Aluminium Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] QDC 302
Decision Date

CaseChat Overview and Summary

Perkins brought proceedings against Cleveland Glass and Aluminium Pty Ltd in relation to personal injuries allegedly suffered as a result of the defendant's negligence. The limitation period for bringing such an action had expired, and the defendant sought to have the application dismissed on the basis that the limitation period had lapsed. Perkins applied to the court for an extension of the limitation period pursuant to the relevant statute.

The central issue before the court was whether the applicant had knowledge of material facts of a decisive character before the limitation period expired, which would trigger the operation of the statutory provisions allowing for an extension of time. The court needed to determine whether the decisive character of the material facts did not crystallise until the occurrence of three significant events after the critical date.

The court found that the decisive character of the material facts did not crystallise until the occurrence of the three significant events after the critical date, and that Perkins had discharged the onus of proving this on the balance of probabilities. The decisive character of the material facts referred to the extent of the injuries and the causal link between the injuries and the defendant's negligence. The court also found that the respondent was not prejudiced by the delay in bringing the proceedings. Accordingly, the application to extend the limitation period was granted.

The court ordered that the application to extend the limitation period be granted and that the respondent pay the applicant's costs of and incidental to the application on the standard basis.

Orders

Orders of the court

1 Application to extend the limitation period is granted.

2 Respondent to pay the applicant’s costs of and incidental to the application on the standard basis.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established