| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
BUILDING CASES LIST
No. 9700 of 2005
BETWEEN
| P.R.A. ELECTRICAL PTY LTD (ACN 062 906 487) | Plaintiff |
| And | |
| PERSEVERANCE EXPLORATION PTY LTD (ACN 010 604 878) | First Defendant |
| And | |
| RICHARD MANLY | Second Defendant |
---
JUDGE: | HABERSBERGER, J | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 29 MARCH 2006 | |
DATE OF JUDGMENT: | 15 NOVEMBER 2006 | |
CASE MAY BE CITED AS: | P.R.A. ELECTRICAL PTY LTD v PERSEVERANCE EXPLORATION PTY LTD | |
MEDIUM NEUTRAL CITATION: | [2006] VSC 432 | |
---
Building Contract – Whether there was contract between the parties – Special condition that contract did not come into effect until formal instrument of agreement executed – Contract awarded to electrical contractor – No formal instrument of agreement executed – Contractor commenced work, provided security, made progress claims including for variations and submitted dispute to arbitration – Waiver – Proceeding stayed pursuant to Commercial Arbitration Act 1984, s.53.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr B. Jenner | Russell Kennedy |
| For the First Defendant | Mr G.J. Digby QC and Ms K. Stynes | Clayton Utz |
| For the Second Defendant No Appearance | ||
HIS HONOUR:
The plaintiff, PRA Electrical Pty Ltd (“PRA”), is an electrical contractor. This litigation concerns disputes and differences which have arisen between it and the first defendant, Perseverance Exploration Pty Ltd (“Perseverance”), with respect to electrical work performed by PRA at the Fosterville Gold Mine near Bendigo. The worked ceased on or about 30 December 2004 when Perseverance gave notice to PRA that it, Perseverance, was taking the works out of the hands of PRA so that they might be completed by another electrical contractor. Perseverance also took possession of all materials and plant and equipment on the mining site. It is clear that, in so doing, Perseverance was purporting to invoke the power conferred upon the proprietor by cl. 39.4 of the General Conditions of Contract AS 4000-1997.
On 27 May 2005, PRA gave notice of dispute asserting that Perseverance was not entitled to act in this way and claiming damages estimated at $4,098,480, for breach by Perseverance of a contract entered into by PRA and Perseverance on 16 August 2004. Following some negotiations, the parties agreed on 15 August 2005 upon the appointment of the second defendant, Mr Richard Manly SC, to be arbitrator. The arbitration then moved forward in a fairly conventional way towards a preliminary conference which was appointed for 12 September 2005.
On 25 August 2005 the Superintendent, Cullen Mining Services Pty Ltd (“CMS”), issued a certificate of cost to complete which was expressed to be given pursuant to General Condition 39.6. Under this certificate, after giving PRA credit for work done, the amount payable by PRA to Perseverance was assessed to be $4,865,461.
PRA responded to the Superintendent’s certificate of cost to complete by giving a second notice of dispute dated 9 September 2005. In this notice it again challenged the validity of the acts of Perseverance in taking the work out of its hands, as…
Keep reading for free
Create a free CaseChat account to read P R A Electrical Pty Ltd v Perseverance Exploration Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] VSC 432
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether a binding contract existed between the parties despite the absence of a formal instrument of agreement. The court had to consider the special condition in the contract that stated it would not come into effect until a formal instrument was executed. Additionally, the court needed to determine whether the contractor's actions, including commencing work, providing security, and submitting a dispute to arbitration, could be construed as a waiver of the requirement for a formal instrument.
The court found that although the special condition stipulated that the contract would not take effect until a formal instrument was executed, the actions of both parties post-execution of the initial contract indicated an intention to be bound. The contractor's commencement of work, provision of security, and submission of progress claims, including for variations, demonstrated a clear intention to proceed under the terms of the contract. The court held that the mining company's acceptance of these actions constituted a waiver of the requirement for a formal instrument. Consequently, the court determined that a binding contract existed between the parties.
The court ordered that the proceeding be stayed pursuant to section 53 of the Commercial Arbitration Act 1984, pending the resolution of the arbitration dispute. This decision underscored the importance of the parties' conduct in determining the existence of a contract, even in the absence of a formal instrument. The court's ruling clarified that actions taken in reliance on the contract can be sufficient to establish its enforceability.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.