Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (No 2)

Case

[2023] NSWSC 680

21 June 2023

No judgment structure available for this case.

Supreme Court


New South Wales

Medium Neutral Citation: Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (No 2) [2023] NSWSC 680
Hearing dates: On the papers; submissions received 22 May, 2 and 9 June 2023
Date of orders: 21 June 2023
Decision date: 21 June 2023
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Further finding made about two invoices; other matters not to be re-examined

Catchwords:

CIVIL PROCEDURE – whether issues raised at hearing not addressed in principal judgment – whether Hungerfords interest should also be awarded against director of builder – whether Court should have examined individual invoices to determine rectification costs – where submission now sought to be developed was not developed at trial

Legislation Cited:

Design and Building Practitioners Act 2020 (NSW)

Cases Cited:

Cavasinni v Cavasinni (No 2) [2007] NSWSC 957

Hungerfords v Walker (1989) 171 CLR 125; [1989] HCA 8

Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 [2023] NSWSC 343

The Owners – Strata Plan No 87060 v Loulach Developments Pty Ltd (No 2) [2021] NSWSC 1068

The Owners-Strata Plan 86807 v Crown Group Constructions Pty Ltd [2023] NSWSC 44

The Owners-Strata Plan No 86807 v Crown Group Constructions Pty Ltd (No 2) [2023] NSWSC 520

Category:Consequential orders
Parties: Oxford (NSW) Pty Ltd (Plaintiff/First Cross-Defendant)
KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 (First Defendant/First Cross-Claimant)
AS Coaching Pty Ltd atf Calm Properties Unit Trust ABN 19 756 796 114 trading as AK Properties Group ABN 62 971 068 965 (Second Defendant/Second Cross-Claimant)
Elankeeren Eswaran (Third Defendant/Third Cross-Claimant)
Ashay Sharma (Fourth Defendant/Fourth Cross-Claimant)
Pierre Kazzi (Second Cross-Defendant)
Representation:

A Cameron (Plaintiff/Cross-Defendants)
J Horowitz (Defendants/Cross-Claimants)

Solicitors:
Fortis Law Pty Limited (Plaintiff/Cross-Defendants)
Domain Legal Pty Limited (Defendants/Cross-Claimants)
File Number(s): 2020/7703

JUDGMENT

  1. I gave judgment in this matter on 6 April 2023. [1] I shall use the same abbreviations here.

    1. Oxford (NSW) Pty Ltd v KR Properties Global Pty Ltd trading as AK Properties Group ABN 62 971 068 965 [2023] NSWSC 343.

  2. I will refer to paragraphs in that judgment thus: “[Jxxx]”.

  3. At [J360], I directed the parties to confer and agree on whether any other matters in dispute required resolution and as to the orders that should be made to give effect to my reasons.

  4. The Owners contend that I have failed to deal with three matters that were raised by the Owners during the hearing but were not addressed by me in the judgment.

  5. The Owners point to the observations made by Young CJ in Eq (as his Honour then was) in Cavasinni v Cavasinni (No 2) [2] that:

“… it is far better where there is a problem seen about a judgment and where the order has not been entered, for the trial judge to deal with the matter rather than let either or both parties appeal the case.”[3]

The Owners’ Hungerfords v Walker interest claim against Mr Kazzi

2. [2007] NSWSC 957.

3. At [8].

  1. The Owners sought Hungerfords v Walker [4] interest against both the Builder and Mr Kazzi.

    4. (1989) 171 CLR 125; [1989] HCA 8.

  2. I found that the Owners were entitled to Hungerfords interest against the Builder. [5]

    5. At [J298]-[J326].

  3. The Owners contend that I did not address their claim for Hungerfords interest against Mr Kazzi.

  4. It is true that I did not, in terms, address the Owners’ Hungerfords interest claim against Mr Kazzi. But that was because I did not accept that the Owners had succeeded in establishing their case against Mr Kazzi under the Design and Building Practitioners Act 2020 (NSW) (“the DBP Act”). I dealt with that issue at [J327] to [J352].

  5. I rejected that claim on the basis that the Owners had not clearly developed submissions as to how Mr Kazzi’s alleged breach of the statutory duty created by s 37 of the DBP Act arose. [6]

    6. At [J339]-[J346].

  6. I also rejected the Owners’ claim on the basis that, based on the evidence of Mr Mahedy, the architect that designed the Building, the Owners had not proved what component of the expenses they had incurred related to the cost of rectifying the Builder’s defective work, as opposed to completing the work that the Builder failed to complete. [7]

    7. At [J347]-[J351].

  7. As the Builder has pointed out, it is not sufficient in a claim under the DBP Act for a claimant simply to assert a defect and allege that the relevant person was liable for failing to ensure the defect was not present. [8]

    8. See my decision in The Owners – Strata Plan No 87060 v Loulach Developments Pty Ltd (No 2) [2021] NSWSC 1068 at [42]-[44].

  8. Rather, as the Builder has submitted, a claimant must persuade the Court that the relevant defendant failed to take the precautions that a reasonable person in his or her position would have taken and must prove “how it is said” that the defendant was negligent. [9]

    9. The Owners-Strata Plan 86807 v Crown Group Constructions Pty Ltd [2023] NSWSC 44 at [23] (Ball J) and The Owners-Strata Plan No 86807 v Crown Group Constructions Pty Ltd (No 2) [2023] NSWSC 520 at [18] (Ball J).

  9. I found that the Owners had not established these matters. No cause to consider Hungerfords interest against Mr Kazzi arose for consideration.

Additional invoices

  1. The Owners also submitted, I think correctly, that I overlooked dealing with their claim for payment of an invoice of 30 June 2017 from Jay Designs Pty Ltd (the draftsperson engaged by the Builder to prepare the s 96 application referred to in the judgment) and an invoice that the Builder issued on 22 November 2017 for attending meetings with the local Council engineer and coordinating the works necessary to rectify the entry foyer.

  2. The only response offered by the Builder to the Owners’ submission that I should now deal with this issue was that the Owners’ claim in respect of these invoices was not pleaded or particularised. That is not correct. The claim was clearly pleaded. And the Builder dealt with it in its written submissions.

  3. I allow the Owners’ claim in respect of the invoices, but only against the Builder, the Owners’ claim against Mr Kazzi having failed for the reasons I have set out.

Other rectification costs “apparent from the face of the invoice”

  1. An issue arose in the proceedings as to whether costs incurred by the Owners were attributable to work done to complete construction of the Building, as opposed to work done to rectify defects in the Building.

  2. I dealt with the methodology adopted by the Owners to prove their loss at [J250].

  3. That methodology was to engage Mr Mahedy to prepare the document called “Appendix C” that I attached to my reasons. [10]

    10. At [J251].

  4. As I said at [J252]:

“In Appendix C, Mr Mahedy set out all of the invoices received and paid by the Owners concerning the completion and rectification of the works, together with an allocation of the amount of those invoices to three categories:

(a)   incomplete works relating to Stages 2 to 8;

(b)   incomplete works relating to Stages 9 and 10; and

(c)   rectification works.”

  1. I concluded:

“I am prepared to accept Mr Mahedy’s evidence as providing a basis for which to come to a conclusion on the total cost of completing and rectifying the work.

Thus, I am satisfied that the Owners, using Mr Mahedy’s methodology, have established that the amount they have expended, as set out in Appendix C, should be accepted as representing the total of the reasonable costs of completing the works and rectifying the defective work.

I am not, however, persuaded that the evidence enables me to come to any conclusion as to what proportion of that total amount in Appendix C should be attributed to the cost of rectifying defective work, as opposed to completing the works. Mr Mahedy has not exposed his reasoning process on that question and, as the Builder submitted, were I simply to accept his conclusions, I too would come to an unreasoned conclusion.” [11] (Emphasis in original.)

11. At [J289]-[J291].

  1. The Owners now submit that they:

“… made the submission that it was possible to tell which invoices were in respect of rectification costs [i.e., as opposed to completion costs] from what was written on the invoice. The Court did not address this submission in the Judgment.”

  1. The proposition appears to be that, had I looked beyond Mr Mahedy’s methodology and myself inspected each of the invoices in the Court Book, it would have been possible for me to ascertain what work was attributable to rectification of the Building and what work was attributable to the cost of completing the Building.

  2. I was not invited to take this course during the hearing. It is true that Mr Horowitz, who appeared for the Owners, referred in closing oral submissions, on a number of occasions, to particular invoices that he submitted related only to rectification costs.

  3. It is also true that, at my request, he provided me with an updated form of Mr Mahedy’s Appendix C which contained, in the far right hand column, references to where the relevant invoices could be found in the Court Book. At one point during submissions, I said that if such a column was added to the Schedule “if I want to do a check, I can see where they are”. [12] The form of Appendix C annexed to my reasons contains that last column.

    12. T443.16.

  4. But Mr Horowitz did not suggest I should examine each invoice and reach a conclusion as to which did, and did not, refer to rectification costs.

  5. In support of his post-judgment submission that an inspection of the invoices would reveal whether or not they are attributable to rectification costs, Mr Horowitz provided a 10-page schedule headed “Defect Rectification Costs Apparent From the Face of the Invoice”. That schedule lists a large number of invoices and specifies, in relation to some 75 of them, the amounts that are said to be, on the face on the invoices, attributable to defect rectification. The schedule concludes by stating that the “total defect rectification costs in the schedule” is $123,657.68.

  6. Mr Horowitz provided no such document to me during the course of the hearing. I think the Builder is correct to submit that, in now so doing, Mr Horowitz is seeking to re-open the Owners’ case to argue this point on a basis that was different from that articulated during the hearing.

  7. Mr Horowitz identified five passages from the transcript of final closing submissions as bespeaking the proposition that the Owners’ case was that it was possible to tell which invoices were in respect of rectification costs from what was written on the invoice.

  8. But there are other passages from the transcript which show that I repeatedly asked Mr Horowitz to explain what Mr Mahedy’s explanation was for his attribution of expenses to rectification as opposed to completion costs. There was also an issue about what expenses incurred by the Owners could be attributed to each of the 16 building defects the subject of the Owners’ allegations. Mr Horowitz accepted that, because some expenses had been incurred in relation to one or more of those defects, it was not possible to make any such attribution.

  9. It was in that context, in a passage to which Mr Horowitz did not refer, that we had this exchange:

“HIS HONOUR: I think that what Mr Lynch and Ms Cameron are saying in their submissions, and I’m going to say this now so they can respond later if this is not right, is when they say there’s no evidence of the money spent, they’re referring to Mr Mahedy’s affidavits where they say he doesn’t in terms say that particular money was spent in relation to particular defects. I think that’s what they say. But your answer to that, in part, is that may be right, but all the money that was spent is summarised in this appendix. The fact that the money was spent is not disputed. It may not be possible to allocate these expenses all to one of the categories B1 to B16, but all the expenses are there, and you say I should accept as good enough that allocation mechanism that Mr Mahedy has described.

HOROWITZ: Yes, your Honour.

HIS HONOUR: Because that’s the best that can be done, you say, in the real world.

HOROWITZ: Yes, your Honour. That’s better put than I could put it.”

  1. It is true that that exchange occurred in the context of debate as to whether the Owners’ expenses could be attributed to a particular defect, as opposed to the question of whether the expenses were for rectification as opposed to completion. It is also true that, immediately after that exchange, Mr Horowitz made submissions that, speaking generally, it was possible to identify some invoices as relating to rectification work.

  2. However, as I have said, Mr Horowitz did not invite me to conduct my own review of the very large number of invoices in the Court Book to reach my own conclusion, independently of Mr Mahedy’s analysis, on this question.

  3. Had that submission been made, I would have directed the Owners to prepare a document in the nature of a Redfern Schedule setting out exactly how it was said that the invoices, on their face, bespoke rectification as opposed to completion work. That would no doubt have led to a document along the lines of the document that Mr Horowitz submitted, following delivery of judgment, and in support of the present application.

  4. I would then have given the Builder an opportunity to respond.

  5. That is not how the case was run.

  6. It is clear from the Builder’s submissions on this application that its position would have been that what was to be drawn from the face of the invoices was, in many cases, contestable. Indeed, Mr Horowitz accepted during the hearing that questions of inference might arise as to what was to be made of the invoices.

  7. In these circumstances, my conclusion is that it is not now open to the Owners to seek to reagitate its case on this basis.

Conclusion

  1. The parties should now confer and agree on the orders necessary to give effect to my reasons.

**********

Endnotes

Decision last updated: 21 June 2023