JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
ACT: BUILDING SERVICES (COMPLAINT RESOLUTION AND ADMINISTRATION) ACT 2011 (WA)
CITATION: OWNERS OF STRATA PLAN 65323 and PALAZZO HOMES PTY LTD [2020] WASAT 57
MEMBER: MS C BARTON, MEMBER
MS S CHURN, SESSIONAL MEMBER
HEARD: 11 - 13 NOVEMBER 2019 AND 4 MARCH 2020
DELIVERED : 28 MAY 2020
FILE NO/S: CC 888 of 2019
BETWEEN: OWNERS OF STRATA PLAN 65323
Applicant
AND
PALAZZO HOMES PTY LTD
Respondent
FILE NO/S: CC 889 of 2019
BETWEEN: ALLSET INVESTMENTS PTY LTD
Applicant
AND
PALAZZO HOMES PTY LTD
Respondent
Catchwords:
Building service complaint - Meaning of 'carried out' a regulated building service - Nature of building contract - Contract specifications varied - Deficiencies in tiling system - Effect of acoustic mat on tiling system - Form of building remedy order
Legislation:
Building Act 2011 (WA), s 3
Building Regulations 1989 (WA), reg 13(1)(d)
Building Services (Complaint Resolution and Administration) Act 2011 (WA), s 3, s 5(1), s 11, s 11(d), s 36(1), s 36(1)(a), s 36(2), s 37(1), s 38(1), s 49
Building Services (Complaint Resolution and Administration) Regulations 2011 (WA), reg 5
Local Government (Miscellaneous Provisions) Act 1960 (WA), s 374
State Administrative Tribunal Act 2004 (WA), s 51(1)(b)
Building Services Registration Act 2011 (WA)
Result:
Applicants successful in relation to conceded items, reimbursement items and items the Tribunal identified as unsatisfactory
Applicants otherwise unsuccessful
Category: B
Representation:
CC 888 of 2019
Counsel:
| Applicant | : | Mr PA Monaco & Ms D Lazarou |
| Respondent | : | Mr CS Gough & Mr JW Daly |
Solicitors:
| Applicant | : | GV Lawyers |
| Respondent | : | Mills Oakley |
CC 889 of 2019
Counsel:
| Applicant | : | Mr PA Monaco & Ms D Lazarou |
| Respondent | : | Mr CS Gough & Mr JW Daly |
Solicitors:
| Applicant | : | GV Lawyers |
| Respondent | : | Mills Oakley |
Case(s) referred to in decision(s):
Diploma Construction (WA) Pty Ltd v South Central WA Pty Ltd [2015] WASC 289
Gemmill v Sanders [2018] WASC 179
Hawke and Ennis [2018] WASAT 118
Jones v Dunkel (1959) 101 CLR 298
Lewis and Waco Pty Ltd [2016] WASAT 127
Primrose Meadows Pty Ltd v River View Pty Ltd [2019] VSC 263
Shami and Teo [2017] WASAT 73
Shaw v McLeod (unreported, WASC, Library No 4707, 8 November 1982)
The Owners of One Brighton Strata Plan 51948 and Pindan Pty Ltd [No 2] [2020] WASAT 3
REASONS FOR DECISION OF THE TRIBUNAL:
Introduction
A dispute arose between the parties concerning a building service carried out at two apartment buildings in South Perth known as 'Prestige Towers' (Prestige) and 'Moritz Towers' (Moritz).
The applicant in CC 888 of 2019 is The Owners of Strata Plan 65323 (Strata Company). The applicant in CC 889 of 2019 is the developer of the Prestige and the Moritz, Allset Investments Pty Ltd (Principal). The respondent in both proceedings is Palazzo Homes Pty Ltd (Palazzo Homes).
In April 2019, the Strata Company and Principal (applicants) respectively lodged a building service complaint with…
Keep reading for free
Create a free CaseChat account to read OWNERS OF STRATA PLAN 65323 and PALAZZO HOMES PTY LTD and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] WASAT 57
- Decision Date
CaseChat Overview and Summary
The primary legal issues the Tribunal needed to address were whether Palazzo Homes Pty Ltd had properly executed the tiling and waterproofing work as per the contract specifications, and if the acoustic mat installed affected the integrity of the tiling system. The Tribunal also had to determine the appropriate remedy for the identified deficiencies and whether the existing building contract terms and industry standards had been met.
The Tribunal found that Palazzo Homes Pty Ltd had not fulfilled its contractual obligations regarding the tiling and waterproofing work. The Tribunal noted that while the builder had installed an acoustic mat, this did not excuse the substandard tiling work. The Tribunal concluded that the presence of the acoustic mat did not affect the requirement to install a proper tiling system and that the builder's work fell short of the contractual specifications and industry standards. Consequently, the Tribunal ordered the builder to remedy specific items listed in the Scott Schedule by specified deadlines, including payment for particular works. Additionally, certain complaints were dismissed as they were withdrawn or did not meet the statutory criteria for a remedy order.
In summary, the Tribunal's orders mandated the builder to undertake specific remedial actions and make financial compensation to the applicants. The builder was also required to address any damages caused during the remedial works. Both parties were granted the right to apply for costs, with strict timelines for filing and replying to such applications.
Orders
Orders of the court
In matter CC 888 of 2019, the Tribunal orders:
1. By 5.00 pm on 30 June 2020, pursuant to s 36(1)(b) of the Building Services (Complaint Resolution and Administration) Act 2011 (WA), the respondent is to pay the applicant the amount of $16,838.80 (inclusive of GST) to remedy complaint items 95, 111 and 135.
2. By 5.00 pm on 31 July 2020, pursuant to s 36(1)(a) of the Building Services (Complaint Resolution and Administration) Act 2011 (WA), the respondent is to carry out remedial work in relation to the following items:
(a) the items it has agreed to remedy in Annexure A being items 10(a), 16, 17, 23, 24, 32, 33, 34, 35, 39, 43, 49, 50, 51, 54, 55, 58, 61, 62, 64, 65, 66, 69, 70, 72, 74, 77, 78, 82(b)-(e), 84, 85, 86, 92, 93, 118, and 126 of the Scott Schedule; and
(b) the items in Annexure B that the Tribunal has identified as unsatisfactory being items 7, 20, 21, 25, 30, 37, 38(b), 38(c), 41, 47, 48, 53, 63, 71, 76, 82(a), 87, 88, 89, 90, 91, 96, 99, 100, 103 of the Scott Schedule.
3. By 5.00 pm on 30 September 2020, pursuant to s 36(1)(a) of the Building Services (Complaint Resolution and Administration) Act 2011 (WA), the respondent is to remedy the unsatisfactory tiling and waterproofing system in respect of items 11, 13, 14, 18, 19, 27, 28, 56, 59, 60, 80, 81, 83, 106, 109, 110, 112, 114, 115, 116, 117, 120, 121, 122, 123, 124, 125 and 127 of the Scott Schedule.
4. Pursuant to s 46(1) of the State Administrative Tribunal Act 2004 (WA), the applicant has leave to withdraw complaint items 1, 3, 4, 5, 6, 8, 9, 10(b), 12, 15, 22, 26, 42, 44, 67, 68, 73, 104, 107, 108, 113, 119, 128, 131, 137, 138, 139, 140, and 141 of the Scott Schedule in CC 888 of 2019 and these items are dismissed pursuant to s 46(2) of the State Administrative Tribunal Act 2004 (WA).
5. Pursuant to s 38(1)(b) of the Building Services (Complaint Resolution and Administration) Act 2011 (WA), the Tribunal otherwise declines to make a building remedy order for the remaining items of the Scott Schedule and these items are dismissed pursuant to s 46(2) of the State Administrative Tribunal Act 2004 (WA).
6. The respondent is to make good any damage caused by the carrying out of the remedial work the subject of these orders.
7. Both parties have liberty to apply within 21 days from the date of this order to file with the Tribunal and serve an application for costs, including written submissions and any supporting documentation.
8. If a party elects to make an application for costs, the other party has 14 days from the date of the application to file with the Tribunal and serve written submissions and any supporting documentation in reply.
9. Subject to any further order, any application for costs will be determined entirely on the documents pursuant to s 60(2) of the State Administrative Tribunal Act 2004 (WA).
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi