Ostroco v Department of Transport and Main Roads

Link copied
Case Copied 51 min read

LAND APPEAL COURT OF QUEENSLAND

CITATION:

Ostroco v Department of Transport and Main Roads [2013] QLAC 4

PARTIES:

OSTROCO PTY LTD
(appellant)

v

CHIEF EXECUTIVE,
DEPARTMENT OF TRANSPORT AND MAIN ROADS
(respondent)

FILE NO/S:

Appeal No. LAC001–13

Land Court No. AQL020–11

DIVISION:

Land Appeal Court of Queensland

PROCEEDING:

Appeal

ORIGINATING COURT:

Land Court at Brisbane

DELIVERED ON:

17 October 2013

DELIVERED AT:

Brisbane

HEARING DATE:

27 March 2013

THE COURT:

Peter Lyons J
PA Smith, Member
WL Cochrane, Member

ORDER:

1.   The appeal and cross-appeal are allowed. 

2.   Compensation is assessed at $553,043 for relocation costs; and $11,000 for valuation and legal fees. 

3.   Interest be awarded on valuation and legal fees, and on so much of the sum of $32,000 for Mr Bettenay’s fees as has been paid, from the dates of payment to the day immediately preceding the date upon which compensation is paid, at the interest rates identified in the decision of the Land Court. 

4.   (Costs to be determined)

CATCHWORDS:

REAL PROPERTY – COMPULSORY ACQUISITION OF LAND – COMPENSATION – ASSESSMENT – DISTURBANCE – GENERALLY – where the appellant was lessee of premises which were resumed – where the sole director and shareholder of the appellant acquired replacement premises which were leased by the appellant – where the appellant incurred costs related to the make over of the replacement premises – where the appellant claimed those costs as disturbance costs attributable to the resumption – where the Land Court accepted that many of the items included in the costs related to the make over of the replacement premises represented works ordinarily paid for by the landlord – where the rent paid by the appellant for the replacement premises was fair market rental for the premises in their condition at the time of the lease – whether the Land Court erred in finding that costs identified as landlord’s costs would not be reasonably incurred by the appellant

REAL PROPERTY – COMPULSORY ACQUISITION OF LAND – COMPENSATION – ASSESSMENT – DISTURBANCE – GENERALLY – where the appellant was lessee of premises which were resumed – where the appellant contended that the appellant’s business suffered negative impacts from pre–resumption announcements – where the appellant contended that the appellant’s business suffered negative impacts from actions associated with the resumption process – where the appellant claimed for economic loss – where the appellant’s claim related to loss prior to and after the resumption – where the Land Court concluded that it did not have jurisdiction to award compensation for losses which occurred prior to the resumption – where the Land Court concluded that no loss was established by the evidence – whether the Land Court erred in holding that it did not have jurisdiction to award compensation for losses which occurred prior to the resumption – whether the loss was a direct and natural consequence of the taking of the land – whether the Land Court erred in holding that no loss was established by the evidence

REAL PROPERTY – COMPULSORY…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ostroco v Department of Transport and Main Roads and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2013] QLAC 4
Decision Date

CaseChat Overview and Summary

Ostroco was the lessee of premises that were compulsorily acquired by the Department of Transport and Main Roads. The appellant sought compensation for the disturbance caused by the resumption, including relocation costs, costs associated with making over replacement premises, and economic losses attributable to the resumption. The Land Court awarded compensation for relocation costs and part of the make over costs, but rejected other claims. Ostroco appealed to the Court of Appeal, which allowed the appeal in part and assessed compensation at $553,043 for relocation costs and $11,000 for valuation and legal fees. The court found that the Land Court erred in excluding certain make over costs, and that it had jurisdiction to award compensation for some of the economic losses. The Department of Transport and Main Roads cross-appealed, arguing that the court should not have awarded compensation for economic losses, but the cross-appeal was dismissed.

The Land Court was required to determine whether Ostroco was entitled to compensation for the disturbance caused by the resumption of the leased premises. The court had to decide whether the costs associated with making over the replacement premises, which were ordinarily paid for by the landlord, could be claimed by Ostroco. The court also had to determine whether Ostroco's business suffered economic losses as a result of the resumption, and whether it had jurisdiction to award compensation for losses that occurred before the resumption. Finally, the court had to decide whether Ostroco was entitled to compensation for its unsuccessful attempts to sub-let the resumed premises.

The Court of Appeal held that the Land Court erred in excluding certain make over costs from the compensation assessment. The court found that the costs related to works that would have been carried out by Ostroco if it had remained in the original premises, and therefore were reasonably incurred by Ostroco as a result of the resumption. The court also held that it had jurisdiction to award compensation for some of the economic losses suffered by Ostroco, even though they occurred before the resumption. The court found that the losses were a direct and natural consequence of the taking of the land, and that Ostroco had established its case on the balance of probabilities. Finally, the court held that Ostroco was entitled to compensation for its unsuccessful attempts to sub-let the resumed premises, as the loss was a direct and natural consequence of the taking of the land.

The Court of Appeal allowed the appeal and cross-appeal, and assessed compensation at $553,043 for relocation costs and $11,000 for valuation and legal fees. Interest was awarded on valuation and legal fees, and on so much of the sum of $32,000 for Mr Bettenay's fees as had been paid, from the dates of payment to the day immediately preceding the date upon which compensation was paid, at the interest rates identified in the decision of the Land Court. Costs were to be determined.

Orders

Orders of the court

1. The appeal and cross-appeal are allowed.

2. Compensation is assessed at $553,043 for relocation costs; and $11,000 for valuation and legal fees.

3. Interest be awarded on valuation and legal fees, and on so much of the sum of $32,000 for Mr Bettenay’s fees as has been paid, from the dates of payment to the day immediately preceding the date upon which compensation is paid, at the interest rates identified in the decision of the Land Court.

4. (Costs to be determined)

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established