QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Origin Energy Electricity Ltd v Polar Kids Pty Ltd [2018] QCATA 110
PARTIES:
ORIGIN ENERGY ELECTRICITY LTD
(appellant)v POLAR KIDS PTY LTD
(respondent)
APPLICATION NO/S:
APL401-17
ORIGINATING APPLICATION NO/S:
MCDO2316-16 (Brisbane)
MATTER TYPE:
Appeals
DELIVERED ON:
6 August 2018
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Senior Member Howard, Presiding
Member Traves
ORDERS:
1. The application for leave to appeal is allowed.
2. The appeal is allowed.
3. The order of the Tribunal dated 14 November 2017 is set aside;
4. Polar Kids Pty Ltd must pay Origin Energy Electrical Pty Ltd $5,965.88 within 21 days from the date of this Order.
CATCHWORDS:
APPEAL AND NEW TRIAL – NEW TRIAL – IN GENERAL AND PARTICULAR GROUNDS – where minor civil dispute between trader and consumer – whether misleading and deceptive conduct in contract dispute - whether Schedule to electricity contract was misleading regarding network and other charges to be applied – whether customer suffered any loss or damage
Australian Consumer Law (Qld), s 18, s 236
Fair Trading Act 1989 (Qld) s 16, s 50
Queensland Civil and Administrative Tribunal Act2009 (Qld) s 12, Schedule 3APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).
REASONS FOR DECISION
Polar Kids Pty Ltd (Polar Kids) commenced a minor civil dispute (MCD) in the Tribunal against Origin Energy Electricity Limited (Origin) arising out a contract for the sale of electricity entered into between Origin and Polar Kids on 20 October 2015.
In essence, Polar Kids claims it was misled by the contract documents, in particular the Schedule, because it did not provide an estimate of the network charges that Polar Kids could expect to pay under the contract. Polar Kids also argued that other charges were incurred which were more than the amount indicated in the Schedule and that it had not been informed of a break fee which applied if the electricity supply was disconnected prior to the expiration of the fixed term provided for in the contract. Polar Kids also submitted that it should not have incurred any charges from the time its electricity was disconnected by Energex due to a fire which destroyed Polar Kids’ business in February 2016.
Polar Kids sought orders for relief from the payment of $10,000.00 outstanding to Origin and a refund of $10,000.00 of approximately $18,000.00 already paid.
The Tribunal made, in some respects curiously-worded, declarations and orders in the following terms:
1. Satisfied Schedule was misleading by not specifically listing network charges and other government charges.
2. Energex disconnected site from Grid on night of fire 21/22 February 2016. If Energex had recorded same no network charges would be payable from that date.
3. The applicant has paid $18,661.00 which includes some network and termination charges.
4. Discharge the Origin debt $12,122.35, no refund to the applicant.
Origin sought leave to appeal the Tribunal’s decision. The…
Keep reading for free
Create a free CaseChat account to read Origin Energy Electricity Ltd v Polar Kids Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] QCATA 110
- Decision Date
CaseChat Overview and Summary
The central legal issues in the appeal were whether the conduct of Origin Energy was misleading and deceptive and whether the tribunal had correctly applied the principles of natural justice in its decision-making process. The appeal also questioned the extent of any loss or damage suffered by Polar Kids as a result of the alleged misleading and deceptive conduct. The CAT was tasked with reviewing the tribunal's application of the law and its factual findings to determine if there had been an error warranting a new trial.
The CAT found that the lower tribunal had erred in its application of the law and in its factual findings. It concluded that the tribunal had not adequately explained its reasoning, which was a breach of natural justice. The CAT held that the tribunal had incorrectly found misleading and deceptive conduct by Origin and had failed to properly consider the contract terms and the absence of any actual loss or damage to Polar Kids. As a result, the CAT allowed the appeal, set aside the tribunal's order, and found that there was no misleading or deceptive conduct by Origin. Consequently, Polar Kids was liable for the full amount owed to Origin, less the amount accruing from the date of disconnection. The CAT ordered Polar Kids to pay Origin Energy Electricity Ltd $5,965.88 within 21 days of the date of the CAT's order.
Orders
Orders of the court
1. The application for leave to appeal is allowed.
2. The appeal is allowed.
3. The order of the Tribunal dated 14 November 2017 is set aside;
4. Polar Kids Pty Ltd must pay Origin Energy Electrical Pty Ltd $5,965.88 within 21 days from the date of this Order.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi