QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: NTL Constructions Pty Ltd v Queensland Building and Construction Commission [2021] QCAT 329
PARTIES: NTL CONSTRUCTIONS PTY LTD (applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (respondent)
APPLICATION NO/S:
GAR153-20
MATTER TYPE:
General administrative review matters
DELIVERED ON:
28 September 2021
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Member Lember
ORDERS:
1. The application to extend time, filed by NTL Constructions Pty Ltd on 1 May 2020, is dismissed.
2. The application to review a decision, filed by NTL Constructions Pty Ltd on 1 May 2020, is struck out.
CATCHWORDS:
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – ENDING PROCEEDINGS EARLY – SUMMARY DISPOSAL – OTHER MATTERS – whether extension of time to file application for review can be granted under s 61 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) – effect of s 86F(1)(c) of the Queensland Building and Construction Commission Act 1991 (Qld) – whether Tribunal has jurisdiction to hear the matter – whether time should be extended for filing an application for review
Queensland Building and Construction Commission Act 1991 (Qld), s 86F, 87
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 4, s 9(1), s 13, s 17(1), s 33, s 47, s 61, 62(1)Anderson-Barr vQueensland Building and Construction Commission [2018] QCAT 438
Aon Risk Services Australia Ltd v Australian National University (2009) 239 CLR 175
Bein v Queensland Building and Construction Commission [2021] QCAT 109
Body Corporate for Alto Gladstone v Queensland Building and Construction Commission & Anor [2020] QCATA 6
Campaigntrack Victoria Pty Ltd v The Chief Executive,
Department of Justice and Attorney-General & Ors [2016] QCA 37
Childs v Queensland Building and Construction Commission [2019] QCAT 281
Coppens v Water Wise Design Pty Ltd[1] [2013] QCATA 285
Creek v Raine & Horne Real Estate Mossman [2011] QCATA 226
Dey v Victorian Railways Commissioners [1949] 78 CLR 62
Gallagher v QBSA [2010] QCAT 383
Jensen v Queensland Building and Construction Commission [2017] QCATA 232
McCrystal v Queensland Building and Construction Commission [2018] QCAT 207
Pavlovic v Queensland Building and Construction Commission [2020] QCAT 128
Yeo v Brisbane Polo Club Inc [2013] QCAT 261APPEARANCES & REPRESENTATION:
Applicant:
Self-represented
Respondent:
QBCC Legal Services
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
[1][2013] QCATA 285 at [13]–[14].
REASONS FOR DECISION
The tribunal has jurisdiction to deal with matters if empowered to do so by the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (“QCAT Act”) or by an enabling Act.[2]
[2]QCAT Act, s 9(1).
The tribunal’s review jurisdiction is the jurisdiction conferred upon it by the enabling Act to “review a decision made or taken to have been made by another entity under that Act”.[3]
[3]QCAT Act, s 17(1).
Section 87 of the Queensland Building and Construction Commission Act 1991 (Qld) (“QBCC Act”) provides that an…
Keep reading for free
Create a free CaseChat account to read NTL Constructions Pty Ltd v Queensland Building and Construc... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] QCAT 329
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether the Tribunal had the power to grant an extension of time for filing an application for review, and whether the Tribunal had jurisdiction to hear the matter. The court considered the effect of section 86F(1)(c) of the Queensland Building and Construction Commission Act 1991, which provides that an application for review must be made within a certain time frame. The court also considered whether the Tribunal had the power to grant an extension of time under section 61 of the Queensland Civil and Administrative Tribunal Act 2009.
The court found that the Tribunal did not have the power to grant an extension of time for filing an application for review under section 61 of the Queensland Civil and Administrative Tribunal Act 2009. The court also found that the Tribunal did not have jurisdiction to hear the matter because the application for review was filed outside the statutory time limit. The court dismissed the application to extend time and struck out the application to review. The court held that the strict time limits for filing an application for review were necessary to ensure that decisions were reviewed in a timely and efficient manner, and that the Tribunal could not grant an extension of time in this case.
The final orders of the court were that the application to extend time, filed by NTL Constructions Pty Ltd on 1 May 2020, was dismissed. The application to review a decision, filed by NTL Constructions Pty Ltd on 1 May 2020, was also struck out. The court's decision highlights the importance of strict adherence to statutory time limits for filing applications for review, and the limited power of the Tribunal to grant extensions of time in such cases.
Orders
Orders of the court
1. The application to extend time, filed by NTL Constructions Pty Ltd on 1 May 2020, is dismissed.
2. The application to review a decision, filed by NTL Constructions Pty Ltd on 1 May 2020, is struck out.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.