SUPREME COURT OF QUEENSLAND
CITATION:
Northern SEQ Distributor-Retailer Authority Trading as Unitywater v Stockland North Lakes Development Pty Ltd & Anor [2014] QSC 308
PARTIES:
NORTHERN SEQ DISTRIBUTOR-RETAILER AUTHORITY TRADING AS UNITYWATER
ABN 89 791 717 427(plaintiff)
v
STOCKLAND NORTH LAKES DEVELOPMENT PTY LTD
ACN 078 580 408
(first defendant)and
MORETON BAY REGIONAL COUNCIL
(second defendant)
FILE NO/S:
BS 9111 of 2013
DIVISION:
Trial Division
PROCEEDING:
Trial
ORIGINATING COURT:
Supreme Court of Queensland
DELIVERED ON:
19 December 2014
DELIVERED AT:
Brisbane
HEARING DATE:
6, 7, 8, 12, 14 August 2014
JUDGE:
Philip McMurdo J
ORDER:
It is declared that under the Mango Hill Infrastructure Agreement dated 1 April 1999, to which the parties are now the plaintiff and the first defendant (“the Agreement”):
1. By “the completion of development” as that term is used in cl 6.13.1 of the Agreement, the plaintiff and its predecessors which had been “the Council” under the Agreement, must have received payment of sums of money which total the sum of “(X x S1) – y” as those terms are used in cl 6.13.1 of the Agreement, on account of sewerage headworks contributions payable under the Agreement.
2. The first defendant is not entitled to any set-off according to the cost of the design and construction of the sewage transportation infrastructure which would result in any of the total referred to in the preceding paragraph not being received by the plaintiff and its predecessors by the completion of development.
3. The first defendant is not entitled to any benefit, by reference to the cost of the design and construction of the sewage transport infrastructure, other than a set-off against sewerage headworks contributions otherwise payable under the Agreement and in accordance with the preceding paragraph.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – where the plaintiff and first defendant are parties to a contract for the development of land at North Lakes – where the contract requires the first defendant to design and construct sewage transportation infrastructure, and the plaintiff to provide sewage treatment infrastructure – where the first defendant is required to pay the plaintiff a ‘sewerage headworks contribution’ – where the first defendant is entitled to a credit against that contribution for the cost of constructing the sewage transportation infrastructure – whether the entitlement to such a credit is limited or “capped” – if there is such a credit limit, whether that limit can be imposed during stages of the development or at the completion of the development.
ESTOPPEL – ESTOPPEL BY CONDUCT – PROMISSORY ESTOPPEL – PARTICULAR CASES – where the plaintiff and first defendant are parties to a contract for the development of land at North Lakes – where the contract requires the first defendant to design and construct sewage transportation infrastructure, and the plaintiff to provide sewage treatment infrastructure – where the first defendant is required to pay the plaintiff a ‘sewerage headworks contribution’ – where the first…
Keep reading for free
Create a free CaseChat account to read Northern SEQ Distributor-Retailer Authority Trading as Unity... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] QSC 308
- Decision Date
CaseChat Overview and Summary
The primary legal issues involved the interpretation of the Mango Hill Infrastructure Agreement dated 1 April 1999, specifically clause 6.13.1, regarding the calculation of the sewerage headworks contributions and the credit for the cost of constructing the sewage transportation infrastructure. The court also had to consider whether the second defendant, by not enforcing any credit limit, had represented through conduct that the contract would not be enforced according to its proper construction, thereby estopping the plaintiff from enforcing the contract in that manner.
In delivering the judgment, the court concluded that the phrase “the completion of development” meant that the plaintiff and its predecessors, who had been the Council under the Agreement, must have received the total specified sums by the completion of the development. The court further ruled that the first defendant could not claim a set-off or any other benefit in relation to the cost of the design and construction of the sewage transportation infrastructure that would result in the plaintiff not receiving the total sums due. Additionally, the court found that the second defendant's conduct did not represent that the contract would not be enforced according to its proper construction, and therefore, the plaintiff was not estopped from enforcing the contract as written.
The court declared that under the Agreement, the total sums referred to in the judgment must be received by the plaintiff and its predecessors by the completion of development and that the first defendant was not entitled to any set-off or benefit that would result in any shortfall in the total sums due.
Orders
Orders of the court
It is declared that under the Mango Hill Infrastructure Agreement dated 1 April 1999, to which the parties are now the plaintiff and the first defendant (“the Agreement”):
1. By “the completion of development” as that term is used in cl 6.13.1 of the Agreement, the plaintiff and its predecessors which had been “the Council” under the Agreement, must have received payment of sums of money which total the sum of “(X x S1) – y” as those terms are used in cl 6.13.1 of the Agreement, on account of sewerage headworks contributions payable under the Agreement.
2. The first defendant is not entitled to any set-off according to the cost of the design and construction of the sewage transportation infrastructure which would result in any of the total referred to in the preceding paragraph not being received by the plaintiff and its predecessors by the completion of development.
3. The first defendant is not entitled to any benefit, by reference to the cost of the design and construction of the sewage transport infrastructure, other than a set-off against sewerage headworks contributions otherwise payable under the Agreement and in accordance with the preceding paragraph.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi