SUPREME COURT OF QUEENSLAND
CITATION:
Northern SEQ Distributor-Retailer Authority t/a Unitywater v Monadelphous Engineering Pty Ltd [2025] QSC 253
PARTIES:
NORTHERN SEQ DISTRIBUTOR-RETAILER AUTHORITY TRADING AS UNITYWATER (ABN 89 791 717 472)
(plaintiff)v
MONADELPHOUS ENGINEERING PTY LTD (ABN 43 010 305 923)
(first defendant)ACCIONA AGUA AUSTRALIA PTY LTD (ACN 128 531 742)
(second defendant)FILE NO/S:
BS 8948/22
DIVISION:
Trial division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
7 October 2025
DELIVERED AT:
Brisbane
HEARING DATE:
29 August 2025
JUDGE:
Cooper J
ORDER:
1. The interlocutory application filed by the first defendant on 4 July 2025 is dismissed.
2. On the interlocutory application filed by the plaintiff on 19 August 2025, it is ordered that the following amendments made in the Second Further Amended Statement of Claim filed on 26 June 2025 take effect against the first defendant for limitation purposes from the date the proceeding commenced:
a. paragraphs 190I(b), 190S(b)(iv), and Parts L, M and N; and
b. to the extent they are relied upon in the claim against the first defendant, paragraphs 282 to 420.
CATCHWORDS:
PROCEDURE – JOINDER OF CAUSES OF ACTION AND OF PARTIES – MATTERS RELATING TO LIMITATION PERIOD – where the plaintiff amended their claim and statement of claim – where the first defendant applied for an order that certain amendments were to take effect against the first defendant for limitation purposes from the date the amended claim and statement of claim was filed – where the plaintiff applied for an order that the amendments take effect from the date when the proceeding commenced – where r 376(4) of the Uniform Civil Procedure Rules 1999 (Qld) (‘UCPR’) permits a party to make an amendment to include a new cause of action which, whilst current at the date the proceeding was started, had ended – where, if a document is amended in accordance with the requirements of r 376(4), the amendment takes effect on and from the date of the document being amended under r 387(1) of the UCPR – whether the amendments in the amended claim and statement of claim were made in accordance with the requirements r 376(4) of the UCPR – whether, if the amendments in the amended claim and statement of claim were not made in accordance with the requirements of r 376(4), the amendments should take effect from some other time to preserve a possible limitation defence
Allonnor Pty Ltd v Doran [1998] QCA 372, cited
Aon Risk Services Australia Ltd v Australian National University (2009) 239 CLR 175; [2009] HCA 27, cited
Brisbane Airport Corporation Pty Ltd v Arup Pty Ltd [2017] QSC 232, cited
Brisbane South Regional Health Authority v Taylor (1996) 186 CLR 541; [1996] HCA 25, cited
Draney v Barry [2002] 1 Qd R 145; [1999] QCA 491, cited
Hartnett v Hynes [2009] QSC 225, cited
Menegazzo v Pricewaterhousecoopers (A Firm) [2016] QSC 94, cited
Mokrzecki v Popham [2013] QSC 123,…
Keep reading for free
Create a free CaseChat account to read Northern SEQ Distributor-Retailer Authority t/a Unitywater v... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] QSC 253
- Decision Date
CaseChat Overview and Summary
The court held that it was appropriate for the contentious amendments to take effect against MEPL from the time the proceeding commenced. The court was satisfied that a fair trial could occur despite the time Unitywater took to make the contentious amendments. It was also satisfied that MEPL would not be unduly prejudiced if the contentious amendments were to take effect from the commencement of the proceeding. The court further found that this would not inappropriately undermine the rationales for the imposition of limitation periods. Therefore, the amendments in the amended claim and statement of claim were to take effect against MEPL for limitation purposes from the date the proceeding commenced.
The court dismissed MEPL’s application and granted the relief sought on Unitywater’s application. It ordered that the amendments in the Second Further Amended Statement of Claim filed on 26 June 2025 take effect against MEPL for limitation purposes from the date the proceeding commenced. The court also ordered that the parties were to be heard as to costs.
Orders
Orders of the court
1. The interlocutory application filed by the first defendant on 4 July 2025 is dismissed.
2. On the interlocutory application filed by the plaintiff on 19 August 2025, it is ordered that the following amendments made in the Second Further Amended Statement of Claim filed on 26 June 2025 take effect against the first defendant for limitation purposes from the date the proceeding commenced:
a. paragraphs 190I(b), 190S(b)(iv), and Parts L, M and N; and
b. to the extent they are relied upon in the claim against the first defendant, paragraphs 282 to 420.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Finally, Unitywater pleads that MEPL’s breaches arising from the PLST Allegations caused it loss or damage because of the need to design and construct a balance tank to achieve the design treatment capacity of 200,000 EP and ensure compliance with the Environmental Authority and the EP Act.[45][45]2FASOC, paragraphs 277 and 412(a).Consideration As Unitywater accepts, the PLST Allegations plead new material facts; specifically, the design assumption concerning the removal of organic loads by the PLST, the alleged deficiency in that design assumption, the consequences of that design deficiency, and MEPL’s responsibility under the Contract and in negligence for the consequences of that design deficiency. MEPL submits that the PLST Allegations are unconnected to allegations in the earlier pleading about problems with the biomass on the media in the MBBRs. Although the PLST forms part of the overall sewage treatment process, it does not contain the media which is the subject of complaint in the earlier pleading. It is a separate piece of equipment which performs a different part of the treatment process to the MBBRs. Consequently, MEPL submits that new causes of action pleaded by the PLST Allegations depend upon establishing that the MBBRs are receiving a higher level of organic loads than intended, and this higher than intended level of organic loads is the reason the Plant is not achieving the design treatment capacity of 200,000 EP and not complying with the effluent quality criteria for ammonia levels. Proof of that case does not require that Unitywater prove the existence of problems in the design of the MBBRs themselves, or the specification of the media used in the MBBRs, which are the subject of complaint in the earlier pleading. On that basis, MEPL argues that none of the allegations in the earlier pleading, save for the ultimate effect on the performance of the Plant, appear to have anything to do with the new story which Unitywater seeks to tell with the PLST Allegations. In the circumstances of this proceeding, I do not accept MEPL’s submission that the design and operation of the PLST should be characterised as entirely distinct and independent from the design and operation of the MBBRs. Nor do I consider that the breaches the subject of the PLST Allegations should be treated as entirely separate and independent from the breaches pleaded in the earlier pleading. In both cases, the breaches concern an alleged failure to design components of the Plant to achieve the minimum treatment capacity and effluent quality required under the Contract. The PLST is not itself involved in the biological wastewater treatment process. However, by the PLST Allegations, Unitywater pleads that, because of the unreasonable design assumption regarding the performance of the PLST, the influent which passed through to the MBBRs contained a higher level of organic loads than was contemplated in the design. This is alleged to have overloaded the MBBRs leading to a reduction in their treatment capacity and to them being unable to remove sufficient ammonia to comply with the effluent quality criteria prescribed by the PPR and the Environmental Authority.