Northbuild Constructions Pty Ltd v Napier Blakely Pty Ltd

Link copied
Case Copied 11 min read

[2006] QSC 133

SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION

BYRNE J

No 437 of 2005

NORTHBUILD CONSTRUCTION PTY LTD (ACN First Plaintiff
011 063 764)
and
BODDINGTON INVESTMENTS PTY LTD (ACN Second Plaintiff
050 578 133) AS TRUSTEE FOR THE
NORTHBUILD (IH) UNIT TRUST
v.
NAPIER BLAKELY PTY LTD (ACN 006 382 First Defendant
278)
and
RICHARD CURTIS Second Defendant
BRISBANE
..DATE 05/05/2006
JUDGMENT

WARNING: The publication of information or details likely to lead to the identification of persons in some proceedings is a criminal offence. This is so particularly in relation to the identification of children who are involved in criminal proceedings or proceedings for their protection under the Child Protection Act 1999, and complainants in criminal sexual offences, but is not limited to those categories. You may wish to seek legal advice before giving others access to the details of any person named in these proceedings.

05052006 D.1 T16/MBL (Byrne J)

HIS HONOUR: This is an application to strike out as not 1
disclosing an arguable cause of action paragraphs of a
pleading which materially make a claim for damages in tort.
The principal claim is by a builder against persons
alleged to have acted in the role of a certified quantity
surveyor under a building contract between the builder and a
principal.
10

The claim which remains for decision today relates to a contention that, in view of allegations made earlier in the pleading, a duty was owed to the builder by the quantity surveyor. The duty is alleged to be:

20

"A tortious duty of care being a duty to exercise
reasonable skill and care in or about the provision of

the quantity surveying services."

The duty, expressed in that way, is not as it ought to have

30

been, "Stated in reference to the kind of damage" that the plaintiff has allegedly suffered, (see Cole v. South Tweed Heads Rugby League Football Club Limited (2004) 217 CLR
469, at 472). But it is said for the builder the precise

content of the duty can be reformulated in a way which would leave the essential contention arguable. No doubt the claim is susceptible of reformulation in a way which might define

40

the alleged duty with the precision which would be necessary
for it to be the subject of adjudication. I therefore
propose to deal with the application to strike out on the
50
basis that (by some presently unspecified amendment) the
claimed duty can be more appropriately defined.
2 JUDGMENT 60

05052006 D.1 T16/MBL (Byrne J)

The issue therefore is whether the kind of duty alleged is 1
sufficiently arguable to justify refusal of the relief sought.

This is not the trial of a separate question. Rather, it is an interlocutory proceeding which requires attention to be given to the prospects of success of an allegation of the kind of duty that will be alleged when reformulated.

10

Many significant considerations have been urged in the comprehensive and considered submissions placed before me on both…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Northbuild Constructions Pty Ltd v Napier Blakely Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] QSC 133
Decision Date

CaseChat Overview and Summary

Northbuild Constructions Pty Ltd and Boddington Investments Pty Ltd, as trustee for the Northbuild (IH) Unit Trust, brought proceedings against Napier Blakely Pty Ltd and Richard Curtis. The plaintiffs alleged that the defendants, acting as a certified quantity surveyor under a building contract, owed a tortious duty of care that was breached, resulting in damages. The case revolved around the existence and scope of the duty of care that the quantity surveyor owed to the builder.

The legal issue before the court was whether the plaintiffs' claim for damages in tort was arguable. Specifically, the court had to determine if the plaintiffs could reformulate their claim to allege a duty of care that was sufficiently defined and related to the damages they claimed to have suffered. The court considered whether the nature of the contract, the elaborate dispute resolution mechanisms, and the considerations of proximity and vulnerability supported the existence of such a duty.

The court concluded that the plaintiffs' claim was sufficiently arguable to warrant further consideration. Although the duty of care proposed by the plaintiffs mirrored the obligations under the contract, this did not preclude the existence of a tortious duty. The court noted that previous cases had not definitively ruled out the possibility of such a duty, and there was academic support for the notion that a certifier might owe a duty of care to a contractor. The elaborate dispute resolution procedures in the contract did not necessarily exclude the possibility of a tortious duty.

The court decided to allow the plaintiffs an opportunity to replead their claim to more precisely define the alleged duty of care. The court also considered the costs of the proceeding, deciding that they should be costs in the cause to ensure that the repleaded claim was given careful attention.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established