SUPREME COURT OF QUEENSLAND
CITATION:
Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd & Ors [2010] QSC 95
PARTIES:
NORTHBUILD CONSTRUCTION PTY LTD
(applicant)
v
CENTRAL INTERIOR LININGS PTY LTD
(first respondent)AND
ADJUDICATE TODAY PTY LTD
(second respondent)
AND
PHILIP DAVENPORT
(third respondent)
FILE NO/S:
12131 of 2009
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
9 April 2010
DELIVERED AT:
Brisbane
HEARING DATE:
30 November 2009
JUDGE:
Martin J
ORDER:
APPLICATION DISMISSED
CATCHWORDS:
ADMINISTRATIVE LAW – JUDICIAL REVIEW – NATURAL JUSTICE – where there was a construction contract between the applicant and the first respondent – where the matter went to adjudication – where there were discrepancies in the materials before the adjudicator – whether the adjudicator made a bona fide attempt to understand and apply the contract
ADMINISTRATIVE LAW – JUDICIAL REVIEW – NATURAL JUSTICE – where there was a construction contract between the applicant and the first respondent – where variation work was completed by the first respondent – where the matter went to adjudication – where the payment claim included 73 variation claims – where the first respondent provided a quantity surveyor report with respect to 33 of the variation claims – where the adjudicator did not deal with each variation claim individually – whether the adjudicator correctly considered the contractual requirements with respect to the valuation of variation work – whether the adjudicator made a fair and reasonable valuation of the variation work
Building and Construction Industry Payments Act 2004, s 17, s 18, s 26
Brodyn Pty Ltd t/as Time Cost and Quality v Davenport [2003] NSWSC 1019
Brodyn Pty Ltd t/as Time Cost and Quality v Davenport (2004) 61 NSWLR 421
Coordinated Construction Co Pty Ltd v J M Hargraves (NSW) Pty Ltd (2005) 63 NSWLR 385
Downer Construction (Australia) Pty Ltd v Energy Australia & Ors (2007) 69 NSWLR 72
John Holland Pty Ltd v Roads and Traffic Authority of New South Wales [2007] NSWCA 19
Minister for Commerce v Contrax Plumbing (NSW) Pty Ltd [2005] NSWCA 142
Plaza West Pty Ltd v Simon’s Earthworks (NSW) Pty Ltd [2008] NSWCA 279
Queensland Bulk Water Supply Authority t/as Seqwater v McDonald Keen Group Pty Ltd (in liq) [2010] QCA 7
Queensland Bulk Water Supply Authority v McDonald Keen Group Pty Ltd & Anor [2009] QSC 165
Shellbridge Pty Ltd v Rider Hunt Sydney Pty Ltd [2005] NSWSC 1152
Transgrid v Siemens Ltd (2004) 61 NSWLR 521COUNSEL:
P J Dunning SC and G Beacham for the applicant
R A Holt SC and M D Ambrose for the respondentSOLICITORS:
Holding Redlich Lawyers for the applicant
D L A Philips Fox for the respondent
[1] The applicant, Northbuild Construction Pty Ltd (“Northbuild”), seeks a declaration that an adjudication decision made by the Second Respondent under the Building and Construction Industry Payments Act 2004 (“the Payments Act”) is void.
Background
[2] Northbuild was the head contractor for the construction of an apartment complex at Runaway Bay,…
Keep reading for free
Create a free CaseChat account to read Northbuild Construction Pty Ltd v Central Interior Linings P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] QSC 95
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the adjudicator made a bona fide attempt to understand and apply the contract, and whether the adjudicator correctly considered the contractual requirements with respect to the valuation of variation work. Additionally, the court had to determine whether the adjudicator made a fair and reasonable valuation of the variation work, given that the adjudicator did not deal with each variation claim individually but rather assessed the claims collectively.
The court examined the evidence and found that the adjudicator had made a bona fide attempt to understand and apply the contract, despite some discrepancies in the materials presented. The court held that the adjudicator had correctly considered the contractual requirements and made a fair and reasonable valuation of the variation work. The court noted that the adjudicator's approach was consistent with the principles of natural justice and did not result in a manifestly unjust outcome. Consequently, the application for judicial review was dismissed.
The court's final order was that the application be dismissed, with no orders made in favour of the applicant. The court found that the adjudicator had acted within their jurisdiction and had not breached the principles of natural justice in making their decision.
Orders
Orders of the court
APPLICATION DISMISSED
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.