North South Construction Services P/L v Construction Pacific Management P/L

Link copied
Case Copied 10 min read
CITATION: NORTH SOUTH CONSTRUCTION SERVICES P/L v CONSTRUCTION PACIFIC MANAGEMENT P/L [2002] NSWSC 286
CURRENT JURISDICTION: EQUITY
FILE NUMBER(S): SC 3793/01
HEARING DATE(S): 05/04/2002
JUDGMENT DATE: 5 April 2002

PARTIES :


North South Construction Services Pty Ltd - Plaintiff
Construction Pacific Management Pty Ltd - Defendant
JUDGMENT OF: Bryson J at 1
COUNSEL : R.K. Newton
S. Epstein SC
SOLICITORS: The Law Partnership - Plaintiff
Baron and Associates - Defendant
CATCHWORDS: COSTS - non-party - plaintiff's proceedings were dismissed with costs - defendant applied for order for payment of costs by Director who was principal figure in the commpany and the litigation and produced in evidence bogus documents in support of plaintiff's case held that an order could be made against the Director under SCR Pt 52A r4(2) and (5)(d) as there was an abuse of process.
CASES CITED: Knight & Anor v. FP Special Assets Ltd (1992) 174 CLR 178
DECISION: Order for costs against non-party.

IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION

BRYSON J.

FRIDAY 5 APRIL 2002

3793/01 NORTH SOUTH CONSTRUCTION v. CONSTRUCTION PACIFIC

JUDGMENT

1 HIS HONOUR: The defendant's counsel has applied orally for an order that Mr Serafino Bianco known as Phil Bianco pay to the defendant the costs of the proceedings. In my order of 6 March 2002 I gave judgment for the defendant with costs, carrying an entitlement to recover costs against the plaintiff. The order sought would extend that liability to Mr Bianco, without of course relieving the plaintiff.

2 The Court's general power to order costs is created by section 76 of the Supreme Court Act 1970, which provides to the effect, in paragraph (1)(b),

          “The Court shall have full power to determine by whom and to what extent costs are to be paid...".

3 The subsection also provides in paragraph (a),

          “Costs shall be in the discretion of the Court".

4 Part 52A r.4, provides for the powers of the Court generally with respect to costs and Subr.(2) limits the power of the Court to make an order for costs against a person who is not a party to the cases stated in subr.(5).

5 The only relevant case in Subr.(5) relates to the power of the Court to make an order

          “(d) for payment by a person who has committed contempt of court, or an abuse of process of the Court, of the whole or any part of the costs of a party to proceedings occasioned by the contempt or abuse of process;".

6 In Knight & Anor v FP Special Assets Limited (1992) 174 CLR 178 the High Court dealt with the power of the Supreme Court of Queensland under legislation of Queensland to make an order for costs against a person who was not a party to the proceedings.

7 The legislation of Queensland and the provisions of the rules of court dealing with that subject were not in the same terms as the provisions in force in New South Wales but the statutory…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read North South Construction Services P/L v Construction Pacific... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2002] NSWSC 286
Decision Date

CaseChat Overview and Summary

North South Construction Services P/L was engaged by Construction Pacific Management P/L in relation to a construction project. A dispute arose over the amount owed to North South Construction Services P/L by Construction Pacific Management P/L. The dispute was brought before the Supreme Court of Queensland. The primary issue before the court was whether the court could order a non-party to pay costs for abusing the court process. The defendant in the case applied for an order for payment of costs by the Director of North South Construction Services P/L who was the principal figure in the company and the litigation. The Director had produced evidence in support of the plaintiff's case, which was later found to be bogus. The court held that an order could be made against the Director under SCR Pt 52A r4(2) and (5)(d) as there was an abuse of process. The Director's actions were deemed to be an abuse of process as he had produced evidence in support of the plaintiff's case that was later found to be false. The court found that the Director had acted improperly, and therefore, an order could be made against him for the costs of the proceedings. The court dismissed the plaintiff's proceedings with costs.

Background

Background to the litigation

North South Construction Services P/L (plaintiff) and Construction Pacific Management P/L (defendant) were involved in a legal dispute stemming from a contract for construction services. The plaintiff alleged that the defendant had breached the contract by failing to make payments as required. The plaintiff initiated proceedings in the court against the defendant, but the proceedings were dismissed with costs awarded against the plaintiff. During the litigation, it came to light that a Director of the defendant, who was the principal figure in both the company and the litigation, had produced evidence that was later found to be fabricated. This evidence was used to support the plaintiff's case.

Following the dismissal of the plaintiff's proceedings, the defendant applied for an order under the Supreme Court Rules for the Director, who was a non-party to the proceedings, to pay the costs incurred by the defendant as a result of the plaintiff's abuse of process. The defendant argued that the Director's conduct amounted to an abuse of process as defined under SCR Pt 52A r4(2) and (5)(d).

The matter came before the court on an application by the defendant, Construction Pacific Management P/L, seeking an order for the Director, who was not a party to the proceedings, to pay the costs incurred by the defendant due to the plaintiff's alleged abuse of process. This application followed the dismissal of the plaintiff's proceedings against the defendant with costs awarded against the plaintiff. The defendant submitted that the Director's production of bogus documents during the litigation constituted an abuse of process. The court was required to determine whether such an order could be made under the relevant rules of court.

Decision

Reasons for decision

Issues
1. Can an order be made against a non-party, specifically the Director, under SCR Pt 52A r4(2) and (5)(d) for the payment of costs due to an abuse of process?
2. What constitutes an abuse of process under the Supreme Court Rules that would warrant an order for a non-party to pay costs?

Held
1. The court held that an order can be made against a non-party, specifically the Director, under SCR Pt 52A r4(2) and (5)(d) for the payment of costs due to an abuse of process.
2. The court held that the Director's production of bogus documents in support of the plaintiff's case constituted an abuse of process warranting an order for the Director to pay costs.

Ratio Decidendi

Legal Principle Established

The court examined whether an order for costs could be made against a non-party, in this case, the Director of the plaintiff's company, North South Construction Services P/L. Under SCR Pt 52A r4(2) and (5)(d), the court has the discretion to order costs against a non-party if it finds an abuse of process. The court noted that the Director was not only a principal figure in the company but also in the litigation, actively participating in the proceedings and producing evidence. The court found that the Director's actions in producing bogus documents amounted to an abuse of process. This finding was based on the clear misrepresentation of facts and the intent to mislead the court, which constituted a misuse of the court's processes. The court relied on previous case law that underscored the importance of integrity in legal proceedings and the power of the court to sanction individuals who abuse the process, regardless of their status as a party to the litigation. The ratio decidendi of this decision is that the court can order a non-party to pay costs if there is an abuse of process, and such abuse is demonstrated by the production of false evidence or other forms of misconduct in the proceedings.