DISTRICT COURT OF QUEENSLAND
CITATION:
Nortask Pty Ltd v Clarke Energy Australia Pty Ltd (No. 2) [2017] QDC 284
PARTIES:
NORTASK PTY LTD
(plaintiff)v
CLARKE ENERGY AUSTRALIA PTY LTD
(defendant)FILE NO/S:
D 179/2013
DIVISION:
PROCEEDING:
Civil trial - costs
ORIGINATING COURT:
District Court at Brisbane
DELIVERED ON:
30 November 2017
DELIVERED AT:
Brisbane
HEARING DATE:
Submissions in writing
JUDGE:
McGill SC, DCJ
ORDER:
The defendant pay the plaintiff’s costs of the proceeding assessed on the indemnity basis.
CATCHWORDS:
COSTS – Offer to settle – offer under rules – whether other order appropriate – costs on indemnity basis.
UCPR r 360.
Balnaves v Smith [2012] QSC 408 – cited.
Bulsey v State of Queensland [2016] QCA 158 – cited.
Cameron v Nominal Defendant [2001] 1 Qd R 476 – cited.
Castro v Hillery [2003] 1 Qd R 651 – cited.
Chandler v Silwood [2016] QSC 120 – cited.
Davies v Fay [1995] 1 Qd R 509 – cited.
Ibbs v Woodrow [2002] QCA 298 – cited.
Yamaguchi v Phipps [2016] QSC 170 – cited.Yara Nipro Pty Ltd v Interfert Australia Pty Ltd [2010] QCA 164 – cited.
COUNSEL:
S J Armitage for the plaintiff
N H Ferrett for the defendantSOLICITORS:
Clifford Gouldson Lawyers for the plaintiff
HopgoodGanim for the defendant
In this matter the trial took place before me in October and November 2016. Judgment was delivered on 3 November 2017, that the defendant pay the plaintiff $500,666.06 including $148,093.35 by way of interest. Written submissions were invited on the question of costs if the parties were unable to agree on the appropriate order. Written submissions have now been made by both parties. The plaintiff seeks the costs of the proceeding on the indemnity basis pursuant to UCPR r 360. In the alternative, the plaintiff seeks costs on the indemnity basis from 8 September 2012, immediately after the making of an offer to settle on Calderbank principles. The defendant concedes that the plaintiff is entitled to costs but submits that they should be on the standard basis only.
The proceeding arose out of a dispute over the plaintiff’s claims for various extras alleged to be payable in respect of civil construction work undertaken by the plaintiff for the defendant at a site near Mt Isa in 2007. The proceeding commenced on 15 January 2013, claiming $476,267 as money owing under the subcontract or in the alternative as damages for breach of contract; there were some further alternative claims advanced, and there was also a claim for interest. An amended statement of claim was filed on 6 February 2013, before the notice of intention to defend and defence were filed on 12 June 2013. There was a further amended statement of claim filed on 29 October 2015, the pleading on which the plaintiff went to trial, though the total amount claimed as money due under the subcontract or as damages for breach of contract remained the same; there was a difference in the quantum claimed in the alternative…
Keep reading for free
Create a free CaseChat account to read Nortask Pty Ltd v Clarke Energy Australia Pty Ltd (No. 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QDC 284
- Decision Date
CaseChat Overview and Summary
The legal issues before the court centred around the appropriateness of ordering costs on an indemnity basis in light of the defendant's offer to settle. The court had to assess whether the offer to settle under the Uniform Civil Procedure Rules was adequate and whether any other order for costs would be more appropriate. The focus was on whether the settlement offer aligned with the court’s discretion in determining the costs outcome.
The court meticulously evaluated the circumstances surrounding the settlement offer, considering the timing, the nature of the offer, and the overall conduct of the parties during the litigation. Ultimately, the court concluded that the defendant's offer to settle did not adequately reflect the plaintiff’s costs and legal efforts. Consequently, the court deemed it appropriate to order the defendant to pay the plaintiff’s costs on an indemnity basis, reflecting the full extent of the plaintiff’s litigation expenses. This decision underscores the court's duty to ensure a just outcome in cost determinations, particularly when the settlement offer falls short of the plaintiff's incurred costs.
Orders
Orders of the court
The defendant pay the plaintiff’s costs of the proceeding assessed on the indemnity basis.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi