FEDERAL COURT OF AUSTRALIA

Noorton Pty Ltd v Construction, Forestry and Maritime Employees Union [2025] FCAFC 120

Appeal from: Construction, Forestry, Maritime, Mining and Energy Union v Noorton Pty Ltd (No 2) [2024] FedCFamC2G 568
File number: NSD 893 of 2024
Judgment of: RAPER, HATCHER AND YOUNAN JJ
Date of judgment: 2 September 2025
Catchwords: INDUSTRIAL LAW – appeal from decision of Federal Circuit and Family Court of Australia (Division 2) – where respondents alleged the appellant contravened s 45 of the Fair Work Act 2009 (Cth) – whether the Ports, Harbours and Enclosed Water Vessels Award 2010 applied to the second respondent – where FCFCOA found appellant to have contravened the Fair Work Act – second respondent found not to have been paid certain entitlements under award – appellant alleges award did not apply to second respondent on two alternative basis – primary judge erred in the construction of “commercial vessel” in relevant agreements – primary judge misconstrued coverage provisions in the Marine Tourism and Charter Vessels Award 2010 – PHEWV applicable to the second respondent – MTCV award not applicable to the second respondent – appeal allowed in part
Legislation:

Fair Work Act 2009 (Cth) ss 45, 46(1), 47(1), 48(1), 545, 546, 547

Fair Work (Transitional Provisions and Consequential Amendments) Act 2009 (Cth) Sch 3

Federal Court of Australia Act 1976 (Cth) s 24(1A)

Workplace Relations Act 1996 (Cth) Sch 15, ss 344, 346D, 346E, 346L

Workplace Relations Amendment (Work Choices) Act 2005 (Cth)

Industrial Relations Act 1996 (NSW)

Marine Charter Vessels (State) Award cll 2, 7.1

Marine Tourism and Charter Vessels Award 2010 cll 3.1, 4.1, 4.2, 4.7, 10.3 13, 14.5, 14.6, 20.5, Sch B

Motor Ferries (State) Award 2001

Ports, Harbours and Enclosed Water Vessels Award 2010 cls 3.1, 4.1, 4.9, 13, 21.1

Cases cited:

Amcor Limited v Construction, Forestry, Mining and Energy Union (2005) 222 CLR 241; [2005] HCA 10

Bis Industries Limited v Construction, Forestry, Maritime, Mining and Energy Union [2021] FCA 1374
Health Services Union v Catering Industries (NSW) Pty Ltd (2023) 324 IR 337; [2023] FCAFC 82

City of Wanneroo v Holmes (1989) 30 IR 362; [1989] FCA 369

Construction, Forestry, Mining and Energy Union v Anglo Coal (Callide Management) Pty Ltd [2015] FCA 696

Construction, Forestry, Maritime, Mining and Energy Union v Fantasea Pty Limited; The Australian Maritime Officers' Union [2020] FWCFB 4443

Construction, Forestry, Maritime, Mining and Energy Union v Noorton Pty Ltd [2022] FedCFamC2G 699

Construction, Forestry, Maritime, Mining and Energy Union v Noorton Pty Ltd (No 2) [2024] FedCFamC2G 568

Davidson v Official Receiver (2021) 286 FCR 148; [2021] FCAFC 73

Federal Commissioner of Taxation v Consolidated Media Holdings Ltd (2012) 250 CLR 503; [2012] HCA 55

King v Melbourne Vicentre Swimming Club Inc [2020] FCA 1173

Monash Health v Singh [2023] FCAFC 166

Short v FW Hercus Pty Ltd (1993) 40 FCR 511; [1993] FCA 72

Soliman v University of Technology, Sydney [2009] FCAFC 159

Transport Workers’ Union of Australia v Coles…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Noorton Pty Ltd v Construction, Forestry and Maritime Employ... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] FCAFC 120
Decision Date

CaseChat Overview and Summary

Noorton Pty Ltd sought leave to appeal the decision of the Full Court of the Federal Circuit and Family Court of Australia (Division 2) (FCFCOA) concerning a dispute with the Construction, Forestry and Maritime Employees Union. The respondents, who were represented by the Union, alleged that Noorton had contravened section 45 of the Fair Work Act 2009 (Cth) by not paying certain entitlements to an employee, Mr Chippindale, under the Ports, Harbours and Enclosed Water Vessels Award 2010 (PHEWV Award). Noorton argued that the PHEWV Award did not apply to Mr Chippindale on two alternative bases: first, that the primary judge erred in the construction of "commercial vessel" in relevant agreements, and second, that the primary judge misconstrued the coverage provisions in the Marine Tourism and Charter Vessels Award 2010 (MTCV Award). The appeal raised questions about the applicability of these awards to the employment context and whether the primary judge's interpretation of the relevant awards was correct.

The court examined whether the primary judge's interpretation of "commercial vessel" and the coverage provisions in the awards was correct. The court concluded that there was sufficient doubt to warrant appellate reconsideration because of the potential impact on Noorton, including the likelihood of penalties and irrecoverable costs if the decision was in error. The court allowed the appeal in part, finding that the primary judge's interpretation of the relevant awards was incorrect. Consequently, the parties were required to provide agreed orders within 28 days to substitute for those made by the primary judge, or their respective proposed orders together with any supporting written submissions.

Orders

Orders of the court

1. The appeal be allowed in part.

2. The parties provide, within 28 days, agreed orders to substitute for those made by the primary judge, or their respective proposed orders together with any supporting written submission (of no more than two pages), to give effect to the reasons for judgment.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

For the reasons which follow, we consider that the initial judgment is attended by sufficient doubt as to justify appellate reconsideration. Substantial injustice to Noorton will result if leave is not granted because of the likelihood of the imposition of penalties and the need to expend further costs which are likely to be irrecoverable. Leave to appeal should therefore be granted. FACTUAL BACKGROUND Mr Chippindale was employed by Noorton on a casual basis from 25 May 2015 until 10 October 2018. He was initially employed as a GPH. By February 2017, he had obtained the qualifications to work as a Master and commenced working shifts as a Master as well as a GPH. From August 2017, he worked exclusively as a Master. During the period of his employment, Mr Chippindale performed work in or near Sydney Harbour on vessels operated by Noorton to conduct the following five types of services:(1)The MFF Service: This was a service operated by Manly Fast Ferry Pty Ltd (MFF P/L), a corporation related to Noorton, under contract with the NSW Government from early 2015. The MFF service consisted of a high-speed commuter service operating between Circular Quay and Manly from 6:15 am to 9:30 pm Monday to Friday, and from 10:00 am to 8:30 pm on weekends and public holidays. Noorton employed the crews for the MFF service and on-hired them to MFF, and also hired the vessels used to provide the service to MFF. There was also another service, the Manly Fast Ferry Flyer Service, which was the same as the MFF service except that it took slightly longer to complete a journey. For the purpose of this decision, we will treat it as part of the MFF Service.(2)Hopper Service: This was a “hop on/hop off” loop service which ran between various, primarily touristic, locations on Sydney harbour including the Sydney Aquarium, Circular Quay, Luna Park, Fort Denison, Taronga Zoo, Watsons Bay, the Quarantine Station and Manly. The Hopper service operated outside of peak commuting hours seven days per week. In addition, there was a “Beaches Run” which looped between Rose Bay, Watson’s Bay and Manly, and operated only on weekends and public holidays. The Hopper Service was operated in accordance with a timetable, and passengers could pre-book tickets, buy tickets on board or use an Opal card. There were a number of ticket options, including for 24 or 48-hour use of the service, a one or two-hour sightseeing loop, or for trips to and from specific locations. Tickets could be purchased combined with entry to certain tourist attractions located near the harbour stops such as Taronga Zoo. Information was provided to passengers on board about points of interest, history, and key sights on Sydney Harbour.(3)MDH service: This was a commuter ferry service which ran between Manly and Darling Harbour during AM and PM peak hours.(4)Whale watching cruises: These were operated twice daily, subject to weather conditions, every day from May to November.(5)Noorton also operated charter services for weddings, family, business and other functions, and conducted special event cruises for events such as New Year's Eve, the Sydney to Hobart yacht race, Australia Day, and Vivid.

Evidence

Evidence Before The Court

Decision

Reasons for decision

The matter was heard in the FCFCOA on 15 and 16 September 2021 and, on 26 August 2022, the primary judge issued reasons for judgment (initial judgment or IJ): Construction, Forestry, Maritime, Mining and Energy Union v Noorton Pty Ltd [2022] FedCFamC2G 699. The primary judge made findings that the PHEWV Award applied to Mr Chippindale’s employment with Noorton to the extent that he performed work as a GPH or Master on or in relation to vessels operated by Noorton to provide the following services:·the Manly Fast Ferry service (MFF service), including the Manly Fast Ferry Flyer Service;·the Sydney Harbour Eco Hopper service (Hopper service);·the Manly – Darling Harbour Ferry service (MDH service); and·the whale‑watching service. The primary judge found that the GPH Agreement or the Officers Agreement only applied to Mr Chippindale when he was engaged on or in relation to vessels used by Noorton to provide charter services and special event services. His Honour also made findings as to the quantification of the alleged underpayments under the PHEWV Award, which are not presently relevant, and ordered that the proceeding be listed for a directions hearing for the purpose of programming a further hearing as to the final relief to be ordered. After a further hearing on 6 December 2022, the primary judge issued further reasons for judgment on 27 June 2024 and made orders declaring that Noorton had contravened s 45 of the FW Act by failing to pay Mr Chippindale shift allowances provided for by cl 21.1 of the PHEWV Award and requiring Noorton to pay him a sum of $12,301.91 pursuant to ss 545(1) and 547 of the FW Act: Construction, Forestry, Maritime, Mining and Energy Union v Noorton Pty Ltd (No 2) [2024] FedCFamC2G 568. The matter was listed for a directions hearing to deal with the final question of penalty. On 9 July 2024, Noorton filed an application for leave to appeal the orders made on 27 June 2024 together with a draft notice of appeal and an affidavit identifying the substantive prejudice which, it was contended, would ensue were leave not to be granted.Leave to appeal The appeal is one against an interlocutory judgment because the orders made by the primary judge on 27 June 2024, which did not deal with the question of penalty, did not conclusively determine the rights and liabilities of the parties: Monash Health v Singh [2023] FCAFC 166. Leave to appeal is therefore required under s 24(1A) of the Federal Court of Australia Act 1976 (Cth). The grant of leave will depend on whether the decision is attended by sufficient doubt to warrant appellate reconsideration and whether substantial injustice would result from a refusal of leave if the decision is in error: Davidson v Official Receiver (2021) 286 FCR 148; [2021] FCAFC 73 at [15]. The respondents oppose the grant of leave because they contend that the findings in the initial judgment which are the subject of the proposed appeal grounds are not attended by sufficient doubt to warrant reconsideration and the prospect of substantial injustice has not been demonstrated.

Ratio Decidendi

Legal Principle Established