SUPREME COURT OF SOUTH AUSTRALIA
(Magistrates Appeals: Civil)
NAPPER & ANOR v BULTITUDE & ANOR
[2009] SASC 37
Judgment of The Honourable Justice Gray
20 February 2009
DAMAGES - MEASURE AND REMOTENESS OF DAMAGES IN ACTIONS FOR BREACH OF CONTRACT
MAGISTRATES - JURISDICTION AND PROCEDURE GENERALLY - PROCEDURE - THE HEARING - EVIDENCE AND COURSE OF TRIAL
PROCEDURE - JUDGMENTS AND ORDERS - IN GENERAL - STATEMENT OF REASONS FOR DECISION
Appeal against Magistrate’s award of damages for breach of contract of sale – whether defendants under contractual obligations to maintain property between date of contract and date of settlement – whether evidence sufficient to properly assess claims for damages – whether Magistrate’s reasons adequate.
Held: Appeal allowed - the scope of the obligation to maintain a property between contract and settlement considered - failure to establish a change of condition between contract and settlement with respect to a number of claims - failure to prove particular claims - Magistrate’s award of damages of $14,858.50 set aside – judgment entered for respondents for $3,705.81.
Consolidated Holdings Ltd v Ireland [1946] All ER 284; Clarke v Ramuz [1891] 2 QBD 456; Woolcock Street Investments Pty Ltd v CDG Pty Ltd (2004) 216 CLR 515; Jones v Bartlett (2000) CLR 166, considered.
NAPPER & ANOR v BULTITUDE & ANOR
[2009] SASC 37Magistrates Appeal
GRAY J.
This is an appeal against a Magistrate’s award of damages for breach of a contract of sale.
The Magistrate’s award followed a lengthy hearing in regard to a number of claims for damages in respect of what was said to be obligations to maintain a farming property between the date of contract and the date of settlement. I have reached the conclusion that the award made by the Magistrate in respect of a number of the claims should be set aside or substantially reduced.
The proper assessment of the claims, because of their nature, necessarily would require considerable detailed evidence of the precise work performed, materials supplied and associated costs. Evidence led at trial fell short of such detail in respect of many claims. As a consequence there has been some difficulty in making an assessment of loss and damage in respect of those claims which I have found to be justified.
It would be unfortunate for this appeal to result in an order for retrial. The costs of the trial and the appeal are likely to engulf the amount at issue between the parties, and accordingly, I propose to adopt a robust approach to the appeal in an attempt to bring the litigation to an end. Both parties agreed that this would be desirable, and through their counsel, facilitated this approach.
Background
Kim Robert Napper and his mother Edith Clare Napper were the vendors of a rural property known as Clover Downs. They entered into a contract for the sale and purchase of this property on 13 September 2004. Mr Napper died as a result of injuries sustained in a road accident…
Continue reading Napper & Anor v Bultitude & Anor
Sign in free to access the full text
- AGLC
- Napper & Anor v Bultitude & Anor [2009] SASC 37
- Case
- [2009] SASC 37
- Decision Date
CaseChat Overview and Summary
The legal issues in this appeal centred on the scope of the vendors' contractual obligations to maintain the property between the contract date and settlement, the sufficiency of the evidence to properly assess the claims for damages, and the adequacy of the Magistrate's reasons for the decision. The vendors argued that the evidence did not establish a change in the condition of the property and that some claims were not supported by evidence. They also contended that the Magistrate's reasons were inadequate.
The court considered the contractual obligations outlined in the special conditions of the contract. It was noted that clause 5.6.2 required the vendors to maintain the property in a proper manner so as to maintain its condition as at the date of the agreement. The court examined the evidence provided by both parties and concluded that the plaintiffs had not established a change in the condition of the property between the contract date and settlement. The court rejected the claim for fencing costs as no evidence supported the existence of a fence. It allowed a claim for some work and re-stringing of some fencing, estimating a cost of $100. The court set aside the Magistrate's award of damages of $14,858.50 and entered judgment for the plaintiffs for $3,705.81, including the $100 for re-stringing the fencing. The court agreed to hear the parties on interest and costs.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: GRAY J
Full text does not contain this section.