SUPREME COURT OF SOUTH AUSTRALIA
(Civil: Application)
NANTONG DRAYSON COMPOSITE MATERIAL CO LTD v GREYCO PTY LTD
[2023] SASC 52
Judgment of the Honourable Justice Stein
ARBITRATION - RECOGNITION AND ENFORCEMENT OF AWARDS - ENFORCING AWARDS - FOREIGN AWARDS
The applicant sought to register and enforce a foreign award. The respondent opposed registration and enforcement.
Held: The pre-requisites for registration and enforcement were proved and no exceptions were established. Application granted.
Uniform Civil Rules 2020 (SA) r 25.6(3); International Arbitration Act 1974 (Cth) ss 8, 9, 16, 39, referred to.
Tianjin Jishengtai Investment Consulting Partnership Enterprise v Huang [2020] FCA 767; Guoao Holding Group Co Ltd v Xue (No 2) [2022] FCA 1584; TCL Air Conditioner (Zhongshan) Co Ltd v Judges of the Federal Court of Australia (2013) 251 CLR 533; Beijing Jishi Venture Capital Fund (Ltd Partnership) v Liu [2021] FCA 477, applied.
NANTONG DRAYSON COMPOSITE MATERIAL CO LTD v GREYCO PTY LTD
[2023] SASC 52Civil: Application
STEIN J: From about 2016, the respondent, now called Greyco Pty Ltd but previously known as Sustainable Infrastructure Systems (Aust) Pty Ltd, bought various products from the applicant, Nantong Drayson Composite Material Co Ltd (“Nantong Drayson”). The respondent paid some amounts for the delivered products, but a balance remained outstanding. On 18 March 2019, Nantong Drayson and the respondent executed a contract providing for payment of the outstanding amount by 30 September 2019 and for arbitration of any disputes. After the respondent failed to pay, Nantong Drayson commenced arbitration proceedings in the People’s Republic of China and an award was delivered. Nantong Drayson thereafter commenced proceedings in this Court to seek registration and enforcement of the award of the Chinese International Economic and Trade Arbitration Commission Jiangsu Arbitration Centre (“CIETAC”) dated 4 March 2022 (“Award”) in the matter of an arbitration between Nantong Drayson and the respondent.
Background
In early 2019, the parties entered into discussions to address the payment of amounts outstanding in relation to eight agreements for the supply of products. Emails from the respondent in late February 2019 indicated the respondent would instruct its lawyers to have an arrangement set out in a legally enforceable contract in any jurisdiction chosen by Nantong Drayson to demonstrate the respondent’s commitment to the arrangement. Emails included a proposal to resolve issues on a basis which involved Nantong Drayson shipping further goods to the respondent. Versions of a draft agreement were exchanged and a written contract was executed by both parties on 18 March 2019 (“Contract”). Correspondence from the respondent concerning the payment of outstanding amounts did not deny the obligation to pay or raise any issues said to justify non-payment, such as the goods being of poor quality. Email correspondence from the respondent referred to the respondent working on a payment plan for the amount owing and also to a guarantee that the payment problem could be solved.
Contract
The Contract states that the parties entered into the agreement…
Keep reading for free
Create a free CaseChat account to read Nantong Drayson Composite Material Co Ltd v Greyco Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] SASC 52
- Decision Date
CaseChat Overview and Summary
The court found that the respondent had been properly served with all necessary arbitration documents, including the notice of arbitration, the CIETAC Arbitration Rules, and Nantong Drayson’s arbitration documents, both in Chinese and English. The service was conducted by China Express International Express (TNT), and the records indicated successful delivery to the respondent’s registered address. Despite this, the respondent failed to appear at the arbitration hearing and did not provide any explanation for their non-appearance. The court noted that the arbitrator proceeded with the hearing in the respondent’s absence, following the CIETAC Arbitration Rules. The respondent also failed to submit any materials for the arbitration or request a further hearing, leading the arbitrator to make the award based on the facts presented by Nantong Drayson. The court held that the arbitration process was conducted in accordance with the contractual agreement and the CIETAC rules, and that the award was valid and binding.
Given the findings, the court granted the application by Nantong Drayson to enforce the arbitral award in Australia. The court determined that the award was enforceable under the relevant Australian legislation, as it was a foreign award made in a contracting state to the New York Convention. The court also confirmed that the respondent’s objections to the enforceability of the award were without merit.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
The Contract provides that the respondent would pay the Payment Amount before 30 September 2019 and contains a provision for payment of a penalty in the event of failure to pay on time. The Contract provides that the parties agree that all disputes under the Contract will be governed by the law of the People’s Republic of China. The Contract contains a clause providing for any dispute arising from, or in connection with the Contract, to be submitted to CIETAC for arbitration to occur in Nantong, with such arbitration to be conducted in accordance with the CIETAC arbitration rules. The Contract provides that any arbitral award made by CIETAC is final and binding upon both parties. Arbitration process Following the respondent’s continued failure to pay, Nantong Drayson commenced an arbitration process in China. An Award was made. The Award states that the arbitration was conducted in accordance with the CIETAC Arbitration Rules. The Award states that all arbitration documents, notice of the arbitration and materials were effectively delivered to both parties in accordance with the Arbitration Rules. The Award sets out the procedure which was adopted by CIETAC to notify the respondent of the arbitration. That process included sending to the respondent, in both Chinese and English, the notice of arbitration, Arbitration Rules and Nantong Drayson’s arbitration documents. The documents were sent and served by China Express International Express (“TNT”). Thereafter, CIETAC sent to and served further documents on the respondent which included requests to the respondent to express opinions on the arbitration application. The respondent failed to respond. A notice of hearing of the arbitration was not formally served on the respondent before the hearing date and consequently the hearing was rescheduled. After a further notice of the hearing was returned by TNT, the hearing was further postponed and notice of the hearing was re-sent to the respondent’s registered address.TNT documents indicate that notice was served successfully. The respondent failed to appear at the hearing and failed to give a reason for non-appearance. The arbitrator determined to proceed in the absence of the respondent in accordance with the CIETAC Arbitration Rules. Materials provided by Nantong Drayson to the arbitrator were served on the respondent and the arbitrator informed the respondent of the hearing and gave the respondent further time to submit documents or request another hearing. The respondent failed to submit any materials for the arbitration or request a further hearing. The time limit for making an award was then extended. The arbitrator thereafter determined to make the Award in the absence of the respondent based on the facts ascertained through hearing.Award The Award sets out the facts found by the arbitrator and the reasons for the Award. The arbitrator found that Nantong Drayson delivered goods to the respondent but there was a failure by the respondent to pay the full amount owing and the Contract was thereafter executed by both parties to address the arrears of payment. The arbitrator concluded the Contract was valid and the respondent was in breach of the Contract.