FEDERAL COURT OF AUSTRALIA
Nalini Asher Enterprises Pty Ltd v H&M Tracey Construction Pty Ltd [2019] FCA 2161
File number: VID 964 of 2019 Judge: MOSHINSKY J Date of judgment: 17 December 2019 Catchwords: PRACTICE AND PROCEDURE – preliminary discovery – where the prospective applicant and the first prospective respondent were both shareholders in the second prospective respondent – where there was an agreement between the shareholders as to the affairs of the second prospective respondent – where the prospective applicant contended that it may have a right to obtain relief from the first prospective applicant on the basis of breach of contract or breach of fiduciary duty and against the second prospective respondent on the basis of oppression – whether requirements for preliminary discovery satisfied Legislation: Corporations Act 2001 (Cth), ss 232, 233
Federal Court Rules 2011, rr 7.21, 7.23
Cases cited: nearmap Ltd v Spookfish Pty Ltd [2014] NSWSC 1790
ObjectiVision Pty Ltd v Visionsearch Pty Ltd (No 3) [2015] FCA 304
Pfizer Ireland Pharmaceuticals v Samsung Bioepis AU Pty Ltd (2017) 351 ALR 103
Pfizer Ireland Pharmaceuticals v Samsung Bioepis AU Pty Ltd (No 2) [2019] FCA 657
Date of hearing: 12 and 16 December 2019 Registry: Victoria Division: General Division National Practice Area: Commercial and Corporations Sub-area: Corporations and Corporate Insolvency Category: Catchwords Number of paragraphs: 52 Counsel for the Prospective Applicant: Mr DJ Briggs Solicitor for the Prospective Applicant: Mills Oakley Counsel for the First Prospective Respondent: Mr D Chandler Solicitor for the First Prospective Respondent: Lemonis Tantiprasut Lawyers Solicitor for the Second Prospective Respondent: Mr JR Ward Solicitor for the Second Prospective Respondent: Cleary Hoare Solicitors ORDERS
VID 964 of 2019 BETWEEN: NALINI ASHER ENTERPRISES PTY LTD
Prospective Applicant
AND: H&M TRACEY CONSTRUCTION PTY LTD
First Prospective Respondent
H&M TRACEY PILBARA PTY LTD
Second Prospective Respondent
JUDGE:
MOSHINSKY J
DATE OF ORDER:
17 DECEMBER 2019
THE COURT ORDERS THAT:
1.By 4.00 pm on 31 January 2020:
(a)the first prospective respondent (HMT Construction or HMTC) give discovery to the prospective applicant (NAE) of the documents matching the descriptions contained in Schedule 1 to this order; and
(b)the second prospective respondent (HMT Pilbara or HMTP) give discovery to NAE of the documents matching the descriptions contained in Schedule 2 to this order.
2.Subject to paragraph 3, NAE pay the reasonable costs of each of HMT Construction and HMT Pilbara for collating, reviewing and providing the discovered documents, such costs to be assessed if not agreed.
3.If NAE commences substantive proceedings against HMT Construction and/or HMT Pilbara by 4.00 pm on 28 February 2020, all costs incurred by that prospective respondent in providing discovery will be costs in the substantive proceeding.
4.NAE pay HMT Construction’s and HMT Pilbara’s costs of the hearing on 12 December 2019.
5.In relation to the other costs of the application for preliminary discovery as between NAE and…
Keep reading for free
Create a free CaseChat account to read Nalini Asher Enterprises Pty Ltd v H&M Tracey Construction P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2019] FCA 2161
- Decision Date
CaseChat Overview and Summary
The Court ordered that Nalini Asher Enterprises pay the costs of the adjournment and that the costs of the application be borne by the party that did not prevail in the application. The Court ordered that the documents be provided by specific dates and that the costs of providing the documents be paid by the respondents if substantive proceedings were commenced within a certain timeframe. The Court also ordered that if substantive proceedings were commenced within a certain timeframe, the costs of the application would be costs in the substantive proceeding.
Orders
Orders of the court
1. By 4.00 pm on 31 January 2020:
(a) the first prospective respondent (HMT Construction or HMTC) give discovery to the prospective applicant (NAE) of the documents matching the descriptions contained in Schedule 1 to this order; and
(b) the second prospective respondent (HMT Pilbara or HMTP) give discovery to NAE of the documents matching the descriptions contained in Schedule 2 to this order.
2. Subject to paragraph 3, NAE pay the reasonable costs of each of HMT Construction and HMT Pilbara for collating, reviewing and providing the discovered documents, such costs to be assessed if not agreed.
3. If NAE commences substantive proceedings against HMT Construction and/or HMT Pilbara by 4.00 pm on 28 February 2020, all costs incurred by that prospective respondent in providing discovery will be costs in the substantive proceeding.
4. NAE pay HMT Construction’s and HMT Pilbara’s costs of the hearing on 12 December 2019.
5. In relation to the other costs of the application for preliminary discovery as between NAE and HMT Construction:
(a) Subject to paragraph (b), each party bear its own costs.
(b) If NAE commences substantive proceedings against HMT Construction by 4.00 pm on 28 February 2020, each party’s costs of the application will be costs in the substantive proceeding.
6. In relation to the other costs of the application for preliminary discovery as between NAE and HMT Pilbara: HMT Pilbara pay NAE’s costs of the application, as agreed or assessed.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Schedule 1
DOCUMENTS FOR PRODUCTION FROM H&M TRACEY CONSTRUCTION PTY LTD
No.
Category
Documents
1.
Company books and records.
1.5
Minutes of directors’ meetings for HMTC during the period from 1 January 2018 to date referring to:
a. Any agreement with HMTP in respect of projects outside the Kimberley region,
including but not limited to the projects identified in Categories 4 and 5.
3.
Documents relating to existing contracts between Woodside and HMTC.
3.5
Tranche financial reconciliation including conciliation of payments for each tranche and tranche financial positions profit and loss sheets.
4.
Documents relating to previous or current projects tendered and/or delivered by HMTC outside the Kimberley region, since the date of the entering of the Company Agreement, being 2 December 2014, including but not limited to:
a. Onslow aircraft hangar;
b. RFDS hangar and Office, Perth;
c. North West Transitional Housing;
d. Onslow Sports Club and V Swans Office;
e. Residence at Parton Road, South Hedland;
f. 43 House Refurbishment Project, Swanbourne;
g. Lords Recreation Centre, Subiaco;
h. Kent Street, East Victoria Park Education Facility;
i. PPA Sample Station Upgrades, Boodarie;
j. EPC Community Hub, Karratha;
k. North Regional TAFE; and/or
l. 5 Huxtable Cres, Port Hedland;
4.4
Executed contracts for projects entered into by HMTC.
4.5
Financial reconciliations, including the final profit and loss position for the project.
5.
Documents relating to Corporate Overheads and Cost Recovery
5.1
Minutes of meetings confirming any agreement between HMTP and HMTC relating to corporate overhead cost recovery.
5.2
Documents, including financial documents, relating to the Pilbara region lease and office costs, including:
a. lease agreements;
b. office outgoings; and
c. cost recovery agreements between HMTP and HMTC,
in relation to the period since 22 May 2014.
Schedule 2
DOCUMENTS REQUESTED FROM H&M TRACEY PILBARA PTY LTD
No.
Category
Documents
1.
Company books and records.
Board Documents
Projects and Tenders
1.5
Agendas of directors meetings of HMTP between 1 April 2018 to date which identify as a topic for discussion:
a. existing projects (including but not limited to those identified in Categories 2 and 3); and/or
b. possible tenders (including but not limited to those identified in Category 4).
1.6
Minutes of directors meetings of HMTP from 1 April 2018 to date at which the following were discussed:
a. existing projects (including but not limited to those identified in Categories 2 and 3); and/or
b. possible tenders (including but not limited to those identified in Category 4).
Involvement of HMTC
1.10
Records of any resolutions by the board of HMTP between 1 April 2018 to date in relation to:
a. the subcontract of work to HMTC (and/or its associated entities); and/or
b. any novation or assignment of HMTP contracts to HMTC (and/or its associated entities).
Valuation
1.12
All correspondence between the director/s of HMTP (and/or their advisors) and any representative of Jarot in respect of the Valuation.
2.
Documents relating to current projects delivered within the HMTP works jurisdiction, including but not limited to:
b. RFDS hangar and Office, Perth;
c. North West Transitional Housing;
d. Onslow Sports Club and V Swans Office; and
e. Residence at Parton Road, South Hedland.
2.1
Invitations to tender received by HMTP from 1 April 2018 to date.
2.2
Final tender estimates prepared by HMTP from 1 April 2018 to date.
2.3
Tender responses submitted by HMTP from 1 April 2018 to date.
2.4
Executed contracts for projects entered into by HMTP on or after 1 April 2018.
2.5
Financial reconciliations, including the final profit and loss position for the projects identified.
3.
Documents relating to Woodside NWS Housing Panel Contract
3.1
Executed contracts between HMTP and Woodside (and/or its associated entities).
3.3
Any subcontract tender submitted to HMTP by HMTC (and/or any of its associated entities).
3.5
Any subcontract agreement entered between HMTP and HMTC (and/or any of its associated entities) in respect of any contract between HMTP and Woodside.
3.7
Tranche financial reconciliation, including profit and loss statements and conciliation of payments.
3.10
Tranche tender/pricing response issued to Woodside.
4.
Documents relating to current tenders outside the Kimberley region, including but not limited to:
b. Mount Claremont – Bus Depot D & C;
c. BHP Port Laboratory Replacement Project – Port Hedland;
d. Pilbara TAFE – Karratha Campus Facility Storage Area Stage 2; and
e. Multiple indigenous building and housing project tenders outside of the Kimberley, including Department of Housing Panel Contracts.
4.1
Invitations to tender received by HMTP from 1 April 2018 to date.
4.5
Copies of correspondence between the directors of HMTP (and/or their advisors) relating to preparing, submitting or not submitting tenders for any of the identified projects.
Background
Background to the litigation
The matter was heard in the Federal Court of Australia. NAE filed an amended originating application for preliminary discovery, which was contested by both HMT Construction and HMT Pilbara. The Court considered submissions from all parties regarding the scope of discovery, the costs associated with providing the documents, and the costs of the application itself. The Court also addressed the issue of whether the application was brought for a collateral purpose, which was denied based on the material presented. The Court determined the categories of documents to be discovered and ordered both HMT Construction and HMT Pilbara to provide the specified documents by a set deadline. Additionally, the Court ruled on the costs associated with the adjournment, the discovery process, and the application itself, determining that certain costs would be borne by NAE, while others would be paid by HMT Pilbara if substantive proceedings were initiated within a specified timeframe.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The court began by addressing the submission that the application for preliminary discovery had been brought for a collateral purpose, which it dismissed. The court found that the requirements for preliminary discovery were met based on the material presented, allowing it to order the discovery of certain documents. The court noted the agreement between the shareholders of the second prospective respondent regarding the company's affairs and the prospective applicant's contention about possible breaches of contract or fiduciary duty and potential oppression. The court carefully considered the categories of documents requested, narrowing them down based on the amended originating application, and ordered the disclosure of specific documents related to company books, records, project details, financial reconciliations, and contracts.
In determining the costs associated with the adjournment and the application, the court applied principles from previous cases, including Pfizer Ireland Pharmaceuticals v Samsung Bioepis AU Pty Ltd (No 2) and ObjectiVision Pty Ltd v Visionsearch Pty Ltd. The court reasoned that NAE should bear the costs of the adjournment due to the failure to address a request to cross-examine a witness, potentially avoiding the need for the adjournment. For the costs of the application, the court found that both NAE and HMT Construction had substantial measures of success, leading to an order for each party to bear its own costs. However, if substantive proceedings were initiated within a set timeframe, the costs of the application would become costs in the cause. Regarding HMT Pilbara, the court ordered it to pay NAE's costs of the application due to NAE's success in obtaining the discovery sought, despite the narrowing of the categories in the amended originating application.
The ratio decidendi of this decision lies in the careful balancing of costs in preliminary discovery applications, taking into account the outcome and the conduct of the parties. The court distinguished the current case from previous authorities by focusing on the specific circumstances of the application and the conduct of the parties involved.