Supreme Court
New South Wales
Medium Neutral Citation: Najask Pty Ltd v Stow [2016] NSWSC 1511 Hearing dates: 13 September 2016 Date of orders: 01 November 2016 Decision date: 01 November 2016 Jurisdiction: Common Law Before: Wilson J Decision: 1. Appeal Dismissed.
2. Costs in favour of the defendant, stayed for 14 days to allow the parties to make any submission seeking contrary orders.
3. Any submission as to costs by the plaintiff to be filed and served within 7 days from today.
4. Any submission in reply to be filed and served within 7 days thereafter.
5. Any such submissions will be determined on the papers.Catchwords: APPEAL FROM LOCAL COURT - appeal against decision of a Magistrate in a civil claim – construction of contract - question of whether entire contract case Legislation Cited: Local Court Act 2007 (NSW)
Uniform Civil Procedure Rules 2005 (NSW)Cases Cited: Baltic Shipping Co v Dillon [1992 – 1993] 176 CLR 344; [1993] HCA 4
Steele v Tardiani (1946) 72 CLR 386; [1946] HCA 21Category: Principal judgment Parties: Najask Pty Ltd (Plaintiff)
Frances Stow (Defendant)Representation: Mr D Parish (Plaintiff)
Mr T To with Mr A Herring (Defendant)
File Number(s): 2015/342514 Publication restriction: None Decision under appeal
- Court or tribunal:
- Local Court Downing Centre
- Date of Decision:
- 26 October 2015
- Before:
- Stapleton LCM
- File Number(s):
- 2014/69585
Judgment
-
This is a case concerning payment of a disputed bill for holiday accommodation for a group of school children in an amount of a little over forty thousand dollars.
-
The plaintiff, Najask Pty Ltd, operates the Capital Country Holiday Village; the defendant conducts a travel booking agency which booked a stay for a school group at the plaintiff’s holiday accommodation. The school group found the accommodation unsatisfactory and made complaint about it. The complaints were taken up by the defendant with the plaintiff, with the former ultimately refusing to pay the account levied by the plaintiff for the accommodation (although she herself had been paid by the school group).
-
The dispute over the unpaid account came before the Local Court, with the Court ruling in favour of the defendant, and dismissing the plaintiff’s claim for the unpaid monies. The Magistrate concluded that the contract between the plaintiff and defendant should be construed as an entire contract, and failure by the plaintiff to complete the entire contract, including provision of accommodation of a particular standard, disentitled it to claim payment.
-
In an amended summons filed in the Registry of this Court on 15 April 2016, Najask Pty Ltd appeals and, insofar as is necessary, seeks leave to appeal, against the decision of Stapleton LCM of 26 October 2015.
-
The matter turns upon the proper construction of the (unwritten) contract between the plaintiff and defendant, and whether the contract for the provision of holiday accommodation was an entire contract.
The Factual Background
-
The defendant conducts a business which trades as Educational Tours Worldwide. On behalf of a private girls’ school from Western Australia she…
Continue reading Najask Pty Ltd v Stow
Sign in free to access the full text
- AGLC
- Najask Pty Ltd v Stow [2016] NSWSC 1511
- Case
- [2016] NSWSC 1511
- Decision Date
CaseChat Overview and Summary
The legal issues centred on the interpretation of the contract and whether it was an entire contract, thereby preventing the plaintiff from recovering costs unless the contract was fully executed. The plaintiff argued that the contract allowed for partial performance and recovery of costs for work done, whereas the defendant argued that the contract was an entire one, entitling the defendant to a refund of the deposit if the contract was not fully performed.
The Supreme Court found that the contract was not an entire contract, as it allowed for partial performance and the recovery of costs incurred for work done. The court held that the terms of the contract indicated that the plaintiff could recover costs for work done, even if the contract was not fully performed. Consequently, the appeal was allowed, and the decision of the Local Court Magistrate was overturned.
The Supreme Court ordered that the plaintiff was entitled to recover the costs incurred for work done under the contract, and the defendant was required to pay those costs. The court also directed that the matter be remitted to the Local Court for further proceedings in accordance with the Supreme Court's decision.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.