QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
| CITATION: | Nagra v Mowen [2025] QCAT 336 | ||||||
| PARTIES: |
| ||||||
| v | |||||||
| |||||||
| APPLICATION NO/S: | BDL221-23 | ||||||
| MATTER TYPE: | Building matters | ||||||
| DELIVERED ON: | 8 September 2025 | ||||||
| HEARING DATE: | 29 August 2025 | ||||||
| HEARD AT: | Brisbane | ||||||
| DECISION OF: | Member Howe | ||||||
| ORDERS: | Conor Alexander Mowen pay Ravinder Kaur Nagra the sum of $24,265 for claim plus costs of $379.50 within 7 days of Order. | ||||||
| CATCHWORDS: | CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – where the first respondent agreed to construct retaining walls for the applicant – where there was no contract in writing entered into and therefore no effective contract between the parties – where the first respondent was not licensed to do building work – where the first respondent was not entitled to retain the monetary consideration paid by the applicant for the work – where the work was performed poorly – where the applicant was entitled to claim damages for economic loss caused by the first respondent’s negligent performance of building work Queensland Building and Construction Commission Act 1991 (Qld), s 42, s 93, Schedule 1B s 14 Queensland Civil and Administrative Tribunal Rules 2009 (Qld), r 41 Chau’s & Sons Pty Ltd t/as Holiday Air Conditioning and Refrigeration Qld v Karam [2024] QCAT 476 Cook’s Construction Pty Ltd v SFS 007.298.633 Pty Ltd [2009] QCA 75 | ||||||
| |||||||
Second Respondent: | No appearance | ||||||
REASONS FOR DECISION
On 17 April 2023 Ms Nagra (‘the applicant’) obtained a quotation from Conor Mowen (‘the first respondent’) trading as Optimal Landscaping Solutions for landscaping work to be performed at her property at Narangba.
The work involved building a steel post and sleeper retaining wall and a separate concrete block retaining wall, the laying of turf and the removal of certain structures in the yard.
The quoted cost of the work was $28,500.
The applicant paid a deposit of $8,000 on 19 April 2023 then further amounts of $6,250 on 22 April 2023 and $7,125 on 24 April 2023, in total $21,375.
The first respondent started work on the retaining walls with his brother, the second respondent, on 21 April 2023.
The applicant became concerned with the quality of the work being done including the depth of the galvanised posts and use of chipped, broken and cracked retaining wall blocks of inconsistent size and the wrong colour.
The first respondent was asked to adhere to the quoted work. In response the first respondent demanded payment of the balance of $7,125 not due until completion of the work. That money was not paid and the two respondents started removing retaining wall blocks and turf until police were called.
The respondents left the site and have not returned.
The applicant filed a domestic building dispute application against both respondents claiming $25,000 damages.
The proceedings
Neither respondent has engaged in the proceedings. Neither respondent filed a response to the claim served on…
Keep reading for free
Create a free CaseChat account to read Nagra v Mowen and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] QCAT 336
- Decision Date
CaseChat Overview and Summary
The court found that there was no written contract between the parties, and therefore, no effective contract existed. As Mowen was not licensed to perform building work, he was not entitled to retain the monetary consideration paid by Nagra. The court held that Nagra was entitled to claim damages for the economic loss caused by Mowen's negligent performance of building work. The court found that Mowen's work was performed poorly, and the resulting damage to Nagra's property was a direct result of Mowen's negligence. The court held that Nagra was entitled to recover the sum of $24,265 for the cost of building retaining walls, plus costs of $379.50.
The court ordered that Mowen pay Nagra the sum of $24,265 for the claim, plus costs of $379.50 within 7 days of the order. The court did not find it necessary to make any further orders. The decision of the court is a reminder to builders and contractors that they must have a written contract and be licensed to perform building work before entering into an agreement with a client. Failure to do so may result in the loss of any monetary consideration paid by the client, as well as liability for damages caused by the poor quality of work performed.
Orders
Orders of the court
Conor Alexander Mowen pay Ravinder Kaur Nagra the sum of $24,265 for claim plus costs of $379.50 within 7 days of Order.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.