JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: MSP ENGINEERING PTY LTD -v- TIANQI LITHIUM KWINANA PTY LTD [No 2] [2021] WASC 39
CORAM: MASTER SANDERSON
HEARD: 24 SEPTEMBER 2020
DELIVERED : 18 FEBRUARY 2021
PUBLISHED : 18 FEBRUARY 2021
FILE NO/S: CIV 1318 of 2020
BETWEEN: MSP ENGINEERING PTY LTD
Plaintiff
AND
TIANQI LITHIUM KWINANA PTY LTD
Defendant
FILE NO/S: CIV 1319 of 2020
BETWEEN: MSP ENGINEERING PTY LTD
Plaintiff
AND
TIANQI LITHIUM KWINANA PTY LTD
Defendant
Catchwords:
Construction contract - Whether summary judgment available in relation to program certificates when contract terminated
Legislation:
Nil
Result:
Application granted
Category: A
Representation:
CIV 1318 of 2020
Counsel:
| Plaintiff | : | G R Donaldson SC & J Sippe |
| Defendant | : | J K Taylor SC & A Pieniazek |
Solicitors:
| Plaintiff | : | Squire Patton Boggs |
| Defendant | : | Clayton Utz |
CIV 1319 of 2020
Counsel:
| Plaintiff | : | G R Donaldson SC & J Sippe |
| Defendant | : | J K Taylor SC & A Pieniazek |
Solicitors:
| Plaintiff | : | Squire Patton Boggs |
| Defendant | : | Clayton Utz |
Case(s) referred to in decision(s):
Aquatec‑Maxcon Pty Ltd v Minson Nacap Pty Ltd (2004) 8 VR 16
MSP Engineering Pty Ltd v Tianqui Lithium Kwinana Pty Ltd [2020] WASC 251
Munchies Management Pty Ltd v Belperio (1988) 58 FCR 274
Queensland University of Technology v Project Construction (Aust) Pty Ltd (In liq) (2003) 1 Qd R 259
Tianqui Lithium Kwinana Pty Ltd v MSP Engineering Pty Ltd [No 2] [2020] WASCA 201
MASTER SANDERSON:
In both of these actions the plaintiff applies for summary judgment. Although both actions are separate and distinct they are inter‑related and can conveniently be dealt with together.
The matter has a history. In each action the defendant applied for a stay of the summary judgment application essentially on the grounds the matter should be dealt with by an arbitrator pursuant to notices of dispute issued by the defendant. I dismissed that application: MSP Engineering Pty Ltd v Tianqui Lithium Kwinana Pty Ltd [2020] WASC 251. The Court of Appeal upheld that decision: Tianqui Lithium Kwinana Pty Ltd v MSP Engineering Pty Ltd [No 2] [2020] WASCA 201. At the conclusion of their reasons, the Court of Appeal had this to say:
154We note that, at the time of preparing these reasons, there was an undetermined summary judgment application pending in the primary proceedings. That application may raise issues which were not before the master when dealing with the application made under s 8 of the Arbitration Act. In the event that the court hearing that application were to determine that Tianqi had raised a triable issue and refused MSP's summary judgment application, it would then also have in effect determined that the action was brought in a matter which the arbitration agreement required be referred to arbitration. That is, it would have determined that MSP's claim in the primary proceedings was not capable of summary determination.
155In that event, while Tianqi's application under s 8 of the Arbitration Act has been…
Keep reading for free
Create a free CaseChat account to read MSP Engineering Pty Ltd v Tianqi Lithium Kwinana Pty Ltd [No... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] WASC 39
- Decision Date
CaseChat Overview and Summary
The court found that the defendant's reliance on clause 39.10 of the contracts for set-off was misplaced, as it only permitted deduction of certain specified amounts. The court also held that the termination of the contract did not remove the bar on equitable set-off, which was not available in this case due to the lack of a close connection between the claims. Furthermore, the court rejected the argument that the contracts should be set aside, as it would not result in a just outcome.
The court concluded that the plaintiff was entitled to summary judgment as the issues between the parties were not complex enough to warrant a full trial. The court emphasised the importance of resolving the issues summarily, as it was an essential aspect of construction contracts.
The court will hear the parties on the form of orders and costs. If the parties cannot reach an agreement, they must file short submissions and a minute of proposed orders within seven days of the publication of the reasons.
Background
Background to the litigation
This case involves two separate actions before the Supreme Court of Western Australia. The plaintiff applied for summary judgment in both actions, seeking payment of the amounts certified under the progress certificates. The defendant opposed the summary judgment applications, arguing that it had rights of set-off and that the contracts may be set aside. The matter has previously been before the court, with the defendant's application for a stay of the summary judgment application dismissed by the court and upheld by the Court of Appeal. The Court of Appeal noted that the primary court may still refer the matter to arbitration if it found the plaintiff's claim not capable of summary determination.
Decision
Reasons for decision
1. Whether the defendant can set off potential damages claims against the amounts owed under the progress certificates.
2. Whether the contracts can be set aside or avoided, and if so, whether this affects the defendant's obligation to pay the amounts certified under the progress certificates.
3. Whether the court should grant summary judgment in favour of the plaintiff for the amounts certified under the progress certificates.
Held
1. The defendant cannot set off potential damages claims against the amounts owed under the progress certificates. The court found that clause 39.10 of the contracts does not allow for the deduction of unspecified amounts that may become due after arbitration.
2. The contracts cannot be set aside or avoided, and this does not affect the defendant's obligation to pay the amounts certified under the progress certificates. The court determined that it was not arguable that the contracts would be set aside, and even if they were, any amounts owed by the plaintiff to the defendant could be set off against the amounts paid under the progress certificates.
3. The court granted summary judgment in favour of the plaintiff for the amounts certified under the progress certificates. The court concluded that the plaintiff was entitled to the judgment it seeks and that the issues should be resolved summarily if possible.
Ratio Decidendi
Legal Principle Established
The court examined the defendant's arguments against granting summary judgment, focusing on whether the defendant had rights of set-off against the amounts claimed by the plaintiff and whether the contracts could be set aside or avoided. The court found that clause 39.10 of the contracts did not allow the defendant to deduct unspecified amounts that may become due after arbitration, and therefore, the defendant could not set off potential damages claims against the amounts owed under the progress certificates. Furthermore, the court held that it was not arguable that the contracts would be set aside or avoided, and even if they were, any amounts owed by the plaintiff to the defendant could be set off against the amounts paid under the progress certificates.
The court also addressed the defendant's argument that termination of the contract removed the restraint on equitable set-off. While the court acknowledged that termination of the contract may remove the restraint on equitable set-off, it found that the facts and circumstances of this case did not give rise to a fairly arguable claim for equitable set-off. The court emphasised that progress certificates were issued under the contract which was then on foot, and it was not offensive in equity to require the defendant to honour its undertaking to pay those progress certificates.
Ultimately, the court granted summary judgment in favour of the plaintiff for the amounts certified under the progress certificates, emphasising the importance of resolving these issues summarily to maintain the integrity of construction contracts. The court invited the parties to confer on the precise form of orders and costs, with a deadline for filing short submissions if an agreement could not be reached.