District Court
New South Wales
Medium Neutral Citation: Morrison v Moss (No. 3) [2020] NSWDC 136 Hearing dates: 23 April 2020 Date of orders: 23 April 2020 Decision date: 23 April 2020 Jurisdiction: Civil Before: Abadee DCJ Decision: See paragraphs 45-48
Catchwords: BUILDING AND CONSTRUCTION – referral of question of rectification costs for defective works to referee – whether referee’s approach should be wholly or partly adopted – whether a conclusion by referee contrary to evidence Legislation Cited: Uniform Civil Procedure Rules 2005 (NSW) Cases Cited: Bellevarde Constructions Pty Ltd v CPC Energy Pty Ltd [2008] NSWCA 228
BestCare Foods v Origin Energy [2012] NSWSC 574
Chocolate Factory Apartments Pty Ltd v Westpoint Finance Pty Ltd [2005] NSWSC 784
Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 310 ALR 113
Morrison v Moss & Anor [2019] NSWDC 746
Super Pty Ltd v SJP Formwork (Aust) Pty Ltd (1992) 29 NSWLR 549Texts Cited: Rawlinsons Australian Construction Handbook, 38th edition (2020) Category: Principal judgment Parties: Mr J Morrison (Plaintiff)
Mr A Moss (Defendant)
Ms E Moss (Defendant)Representation: Counsel:
Solicitors:
Mr T Bland for the Plaintiff
Defendants appeared in person
Osborn Law for the Plaintiff
File Number(s): 2018/121395 Publication restriction: Nil
Judgment
BACKGROUND
-
This proceeding concerns construction work at a dwelling at Murrays Beach, near Lake Macquarie. On 12 December 2019, I delivered reasons for judgment[1] . A summary of the findings appeared at [463] of the Earlier Reasons. I do not propose to repeat them here. The gist of the findings was to the effect that the defendants (the ‘Builders’) were entitled to receive payment for the sum of $56,470.56 (incl. GST) plus interest at the contractual rate. This entitlement was, however, subject to the entitlement of the plaintiff (the ‘Owner’) to recover damages for defective works in various respects set out in the Earlier Reasons. Specifically, (at [311]-[408]) I made detailed findings as to each of the contested items and whether they amounted to defects and, if they did, indicated my view as to the appropriate scope of rectification works.
1. Morrison v Moss & Anor [2019] NSWDC 746 (hereafter ‘the Earlier Reasons’).
-
I directed that the quantum of the rectification costs for the defective works be referred to a referee. On 21 February 2020, I appointed Mr David Madden, of the firm MBMpl Pty Ltd, as that referee. On that occasion, Mr Madden was one of two nominees proposed as referee by the Owner, without objection from the Builders.
-
The terms of reference for that referral were set out in a Schedule appended to the Earlier Reasons (at [466]) which the referee reproduced at Annexure B of his report.
PROCEDURAL DIRECTIONS
-
On 27 March 2020, Mr Madden sent to the Court his report (the ‘Madden Report’). Copies of the report were hereafter supplied to the parties’ solicitors on 3 April 2020 by email from my Associate (at about 2:46pm).
-
On 6 April 2020, in a directions hearing before me (in the ‘Virtual Courtroom’, in respect to which…
Continue reading Morrison v Moss (No. 3)
Sign in free to access the full text
- AGLC
- Morrison v Moss (No. 3) [2020] NSWDC 136
- Case
- [2020] NSWDC 136
- Decision Date
CaseChat Overview and Summary
The court had to consider the methodology employed by the referee in assessing the rectification costs, particularly whether the referee's approach was consistent with established legal principles and the evidence provided. The court also had to determine if the referee had erred in reaching conclusions that were contrary to the evidence. Given that the referee had made findings that were not supported by the evidence, the court needed to decide the extent to which these findings should influence the final determination of the costs.
After careful consideration, the court found that the referee's approach to the rectification costs needed to be revised. The court held that the referee's conclusions were not supported by the evidence and thus, the referee's findings should not be adopted. The court provided detailed reasoning on how the costs should be assessed, ensuring that the new approach was both legally sound and evidence-based. The final orders, as outlined in paragraphs 45-48, mandated the recalculation of the rectification costs according to the court's guidelines, ensuring a fair and just resolution to the dispute.
Orders
Orders of the court
See paragraphs 45-48
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.