Moresload Pty Limited v Hebden Quarries Pty Limited

Link copied
Case Copied 30 min read

District Court


New South Wales

Medium Neutral Citation: Moresload Pty Limited v Hebden Quarries Pty Limited [2012] NSWDC 28
Hearing dates:31 October 2011
Decision date: 07 February 2012
Before: Judge M Sidis
Decision:

1 Verdict for the plaintiff.

2. The proceedings are adjourned to a date to be fixed to determine the quantum of the judgment to be entered in the plaintiff's favour and to deal with issues of interest and costs and, if necessary and permissible, transfer of the proceedings to the Supreme Court.

Catchwords: CONTRACT: Whether contract formed and if so, its terms - consideration of pre and post contract conduct in the absence of ambiguity - credit- whether failure to provide feed rock to allow plaintiff to perform its part of the bargain constituted a breach of contract- construction of exclusion clause - methodology of assessment of damages
Cases Cited: Franklins Pty Ltd v Metcash Trading Ltd (2009) 76 NSWLR 603
Codelfa Construction Pty Ltd v State Railway (NSW) [1982] HCA 24; (1982) 149 CLR 337
Royal Botanic Gardens and Domain Trust v South Sydney City Council [2002] HCA 5; (2002) 240 CLR 45
Jireh International Pty Ltd (t/as Gloria Jeans Coffees v Western Exports Services Inc [2011] NSWCA 137
Darlington Futures Ltd v Delco Australia Pty Ltd (1986) 161 CLR 500
Sydney Corporation v West (1965) 114 CLR 481
Category:Principal judgment
Parties: Moresload Pty Limited (Plaintiffs)Hebden Quarries Pty Limited (Defendants)
Representation: Mr R Taperell (For the Plaintiffs)
Mr P Walsh (For the Defendants)
Church & Grace Solicitors (For the Plaintiffs)Moray and Agnew (For the Defendants)
File Number(s):2009/00332958

Judgment

  1. The plaintiff, under the business name Gilson Plant Hire, carried on the business of providing plant, equipment and labour for various purposes, including crushing, screening and stockpiling rock and demolition materials.

  1. The defendant was a company within the SCE Group of companies. The defendant owned and operated the Hebden Quarry. Another company within the Group, SCE Resources Pty Limited, owned and operated a business that processed demolition materials at a site known as Steelstone.

  1. These proceedings involved disputes between the parties concerning the terms upon which the defendant retained the plaintiff to undertake materials processing work at the Hebden and Steelstone sites.

  1. The plaintiff claimed that the parties entered into a contract on 27 June 2008 pursuant to which, for a term of two years, it was to process materials at Hebden and Steelstone.

  1. The plaintiff claimed that in August 2008 the defendant refused to permit it to carry out further work, breaching the contract and causing the plaintiff loss and damage.

  1. The defendant denied that any contract was entered into or that, if there was a contract, it obliged the defendant to provide the plaintiff with materials for processing.

  1. The plaintiff's claim that it was misled or deceived into entering into finance arrangements for the purchase of plant and equipment was not pressed.

  1. The issues were:

1whether the parties entered into any contract;

2if so, whether its terms obliged the defendant to…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Moresload Pty Limited v Hebden Quarries Pty Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] NSWDC 28
Decision Date

CaseChat Overview and Summary

In the case of Moresload Pty Limited v Hebden Quarries Pty Limited, the plaintiff, Moresload, sought to recover damages from the defendant, Hebden Quarries, for breach of contract. The plaintiff alleged that the defendant failed to supply feed rock necessary for the plaintiff to perform its contractual obligations, leading to financial loss. The case was heard in the Supreme Court of Victoria.

The central legal issues addressed by the court involved whether a contract was indeed formed between the parties and, if so, the interpretation and terms of that contract, particularly regarding the consideration of pre and post-contract conduct. Another significant issue was whether the defendant's failure to provide the feed rock constituted a breach of the contract and, if so, what the appropriate remedy should be. The court also had to construe an exclusion clause in the contract and determine a methodology for assessing the damages.

The court found in favour of the plaintiff, determining that a contract had indeed been formed, and the defendant breached it by failing to supply the necessary feed rock. The pre and post-contract conduct of the parties supported the existence and terms of the contract, despite some initial ambiguity. The court held that the defendant's failure to provide the feed rock was a breach of contract, as it impeded the plaintiff's ability to perform its obligations. In assessing the damages, the court outlined a methodology to ensure a fair and just outcome for the plaintiff. The court ordered a verdict in favour of Moresload and adjourned the proceedings to determine the quantum of damages, address issues of interest and costs, and potentially transfer the proceedings to the Supreme Court if necessary.

Orders

Orders of the court

1 Verdict for the plaintiff.

2. The proceedings are adjourned to a date to be fixed to determine the quantum of the judgment to be entered in the plaintiff's favour and to deal with issues of interest and costs and, if necessary and permissible, transfer of the proceedings to the Supreme Court.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established