Monsour v C & R Darvill Pty Ltd

Link copied
Case Copied 45 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Monsour & Anor v C & R Darvill Pty Ltd [2022] QCAT 302

PARTIES:

MARIE MONSOUR

(first applicant)

BRUCE MONSOUR

(second applicant)

v

C & R DARVILL PTY LTD ATF C & R DARVILL FAMILY TRUST

(respondent)

APPLICATION NO/S:

BDL065-18

MATTER TYPE:

Building matters

DELIVERED ON:

27 July 2022

HEARING DATE:

27-30 October 2020, 16-17 February 2021, 24-25 June 2021

HEARD AT:

Brisbane

DECISION OF:

Member Howe

ORDERS:

1.       The applicants pay the respondent the sum of $134,407.62 within 14 days of the date hereof.

2.       The parties file in the Tribunal and give to each other any submissions on costs within 21 days of the date hereof and file in the Tribunal and give to the other any submissions in response within 21 days thereafter.

3.       The decision on costs will be determined on the papers.

CATCHWORDS:

EVIDENCE – ADMISSIBILITY – OPINION EVIDENCE – EXPERT OPINION – where expert opinion evidence given – where the expert failed to explain in his reports the basis of his conclusions - where the expert quantity surveyor admitted at hearing to being instructed by the client to insert certain reduced figures in his reports – where the expert appeared to lack independence and a suspicion the expert’s report lacked independence in other respects – whether weight was to be given to the reports or the evidence excluded.

CONTRACT – GENERAL CONTRACTUAL PRINCIPLES – DISCHARGE, BREACH AND DEFENCES TO ACTIONS FOR BREACH – REPUDIATION AND NON-PERFORMANCE – REPUDIATION - where the  builder issued a progress claim – where the owners challenged the claims made as to stage of completion of work – where the builder issued an amended progress claim – where the owners refused to pay – where – where the general conditions excluded any retentions save at practical completion stage – whether the owners repudiated their obligations under the contract – where the builder was entitled to terminate the contract for breach – where the builder was excluded from site – where notice of intention to terminate the contract was given – where it was found the builder was entitled to terminate the contract on that alternate ground as well – where the builder was entitled to recover for outstanding value of work done but not the full amount of the amended progress claim.

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION - where the builder claimed payment of variations – where the provisions of the Domestic Building Contracts Act (2000) (Qld) (repealed) applied – where variation claims did not comply with the statutory requirements – where application was made for payment on the grounds of exceptional circumstances – where the grounds of exceptional circumstances were established – where the owners were ordered to pay for variations as assessed by the Tribunal

Domestic Building Contracts Act 2000 (Qld) (repealed), s 84
Uniform Civil Procedure Rules 1999 (Qld), r 428

Allaro Homes Cairns Pty Ltd v O’Reilly & Anor [2012] QCA 286
Finance and Guarantee Company…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Monsour v C & R Darvill Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QCAT 302
Decision Date

CaseChat Overview and Summary

In the case of Monsour v C & R Darvill Pty Ltd, the Tribunal considered the dispute between the Monsours and the builder regarding the building contract for renovations and additions to the Monsours' residential property. The Tribunal addressed several key issues, including the validity of the builder's progress claims, the entitlement of the parties to terminate the contract, and the claims for overpayment, defective work, and variations. The Tribunal found that the Monsours were in substantial breach of the contract by failing to pay the amended progress claim 12, which entitled the builder to terminate the contract. The Tribunal also determined that the builder was entitled to recover the outstanding amount for the amended progress claim 12 and the value of variations claimed. The Monsours' claims for overpayment, defective work, and damages for incomplete work were rejected. The final order required the Monsours to pay the builder $134,407.62 within 14 days of the decision.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.