CITATION: MM Constructions (Aust) Pty Limited and Anor v Port Stephens Council (No. 1) [2010] NSWSC 241 HEARING DATE(S): 23 March 2010
JUDGMENT DATE :
23 March 2010JUDGMENT OF: Johnson J at 1 DECISION: The application to amend the Statement of Claim in accordance with MFI 6 is refused. CATCHWORDS: PROCEDURE - claim for damages for misfeasance in public office and negligence - planning decision by Council - Plaintiffs apply to amend Statement of Claim during final hearing - consequence of amendment would be adjournment of hearing - applicable principles - application refused LEGISLATION CITED: Civil Procedure Act 2005
Uniform Civil Procedure Rules 2005CATEGORY: Procedural and other rulings CASES CITED: Aon Risk Services Australia Ltd v Australian National University [2009] HCA 27; 239 CLR 175
Grivas v Harrison [2010] NSWSC 208
Leinenga v Logan City Council [2006] QSC 294PARTIES: MM Constructions (Aust) Pty Limited (First Plaintiff)
Milan Maruncic (Second Plaintiff)
Port Stephens Council (Defendant)FILE NUMBER(S): SC 2008/289298 COUNSEL: Mr B Toomey QC; Mr E Romaniuk (Plaintiffs)
Mr M Joseph SC; Mr S Glascott (Defendant)SOLICITORS: Creagh & Creagh (Plaintiffs)
DLA Phillips Fox (Defendant)
IN THE SUPREME COURT
OF NEW SOUTH WALES
COMMON LAW DIVISIONJohnson J
23 March 2010
JUDGMENT (on application to amend Statement of Claim - see T79)2008/289298 MM Constructions (Aust) Pty Limited and Anor v Port Stephens Council (No. 1)
1 JOHNSON J
: By Statement of Claim filed on 23 May 2008 the Plaintiffs, MM Constructions (Aust) Pty Ltd and Milan Maruncic, sue the Defendant, the Port Stephens Council, for misfeasance in public office and negligence. The proceedings relate to the Defendant's consideration, in a period up to 2007, of aspects of the Plaintiffs' development project at Church Street, Nelson Bay.
2 The Defendant sought, and was provided with, further and better particulars of the Plaintiffs' claim by letter dated 20 November 2008 from the Plaintiffs' solicitors (see MFI 4). On 13 May 2009 the Defendant filed a Defence in the proceedings.
3 In May 2009, the parties sought a hearing date with a five-day estimate. The matter was listed for hearing commencing 2 November 2009, but that date was vacated and a further hearing date of 7 December 2009 was fixed. The proceedings were before Price J for certain interlocutory purposes on 4 September 2009, and Rothman J for other interlocutory purposes on 1 and 2 December 2009. The Defendant sought to amend its Defence and this, in due course, has occurred. As it happened, the matter was not reached on 7 December 2009 and a further hearing date was fixed, commencing 22 March 2010, still with a five-day estimate.
4 Upon learning that the matter had been allocated to me, I directed last week that it be listed at 2.00 pm on 19 March 2010 for directions, so that I could acquire some understanding of the issues in the proceedings, ensure that interlocutory orders had been complied with and assure myself that the matter was ready to proceed.…
Keep reading for free
Create a free CaseChat account to read Mm Constructions (Aust) Pty Limited v Port Stephens Council... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] NSWSC 241
- Decision Date
CaseChat Overview and Summary
The central legal issue was whether the plaintiffs' application to amend their Statement of Claim during the final hearing should be granted. The court needed to consider the principles governing amendments to pleadings at such a late stage and the potential impact on the proceedings and the opposing party. The plaintiffs argued that the amendment was necessary to address new evidence that had come to light. However, the Council opposed the amendment, citing the disruptive effect on the proceedings and the fairness to the defending party.
The court, after considering the applicable principles, found that the plaintiffs' application to amend their Statement of Claim during the final hearing should be refused. The court emphasised the importance of finality in proceedings and the potential prejudice to the opposing party if an amendment were allowed at such a late stage. The court also noted that the plaintiffs had not demonstrated a compelling reason for the amendment, and that the application was more likely to cause significant disruption and unfairness. Consequently, the application was dismissed.
The court's decision was that the plaintiffs' application to amend the Statement of Claim during the final hearing was refused, and no further amendments were allowed. The final orders were that the hearing would proceed as scheduled without the proposed amendments.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.