Supreme Court
New South Wales
Medium Neutral Citation: MGW Engineering Pty Ltd t/a Forefront Services v CMOC Mining Pty Ltd [2021] NSWSC 514 Hearing dates: 28 April 2021 Decision date: 11 May 2021 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Summons to be dismissed; declarations and orders to be made in accordance with Cross Summons
Catchwords: BUILDING AND CONSTRUCTION – whether payment claims under Building and Construction Industry Security of Payment Act 1999 served on 3 or 4 February 2021 – whether service was effected on 3 February by delivering personally or by lodging during normal office hours or in accordance with construction contract – meaning of delivering personally – meaning of lodging at ordinary place of business – whether service effected in the manner provided under the construction contract – whether provision in construction contract that delivery after 4pm taken to be effected the following day void by reason of s 34 of the Act – whether principal entitled to specific performance of obligation to produce steel and shop drawings
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Corporations Act 2001 (Cwth)
Cases Cited: Bauen Constructions Pty Ltd v Sky General Services Pty Ltd [2012] NSWSC 1123
Chartbrook Ltd v Persimmon Homes Ltd [2009] 1 AC 1101
Fitzgerald v Masters (1956) 95 CLR 420; [1956] HCA 53
Howship Holdings Pty Limited v Leslie (1996) 41 NSWLR 542; [1996] NSWSC 314
Jamac Construction Group Pty Ltd v De Mol Investments Pty Ltd [2014] WASC 273
Lane v Arrowcrest Group Pty Ltd (1990) 27 FCR 427
Sand Excavation Pty Ltd v Nahas Constructions Pty Ltd [2011] NSWSC 184
Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (In Liq) (2019) 99 NSWLR 317; [2019] NSWCA 11
South Western Sydney Local Health District v Gould [2018] 97 NSWLR 513; [2018] NSWCA 69
SMA Solar Technology AG v Beyond Building Systems Pty Ltd (No 5) [2012] FCA 1483
Tal Life Limited v Shuetrim; Metlife Insurance Limited v Shuetrim (2016) 91 NSWLR 439; (2016) NSWCA 68
Texts Cited: Oxford English Dictionary, online ed (2011)
P Herzfeld and T Prince, Interpretation, (2nd ed, 2020, Thomson Reuters)
Category: Principal judgment Parties: MGW Engineering Pty Ltd trading as Forefront Services (Plaintiff/Cross-Defendant)
CMOC Mining Pty Limited (First Defendant/Second Cross-Claimant)
Sumitomo Metal Mining Oceania Pty Ltd (Second Defendant/Third Cross-Claimant)
SC Mineral Resources Pty Ltd (Third Defendant/Fourth Cross-Claimant)
CMOC Mining Services Pty Ltd (First Cross-Claimant)Representation: Counsel:
Solicitors:
D S Weinberger (Plaintiff/Cross-Defendant)
M Ashhurst SC with N Simpson (Defendants/Cross-Claimants)
Batch Mewing Lawyers (Plaintiff/Cross-Defendant)
King & Wood Mallesons (Defendants and Cross-Claimants)
File Number(s): 2021/62011
Judgment
-
The plaintiff, MGW Engineering Pty Ltd, trading as Forefront Services (“Forefront”) provides services to the construction industry.
-
Between 4 February 2020 and 9 August 2020, Forefront entered four contracts (“the Contracts”) with CMOC Mining Services Pty Ltd (“CMOC”) to provide various services at the Northparkes copper and…
Keep reading for free
Create a free CaseChat account to read MGW Engineering Pty Ltd t/a Forefront Services v Cmoc Mining... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NSWSC 514
- Decision Date
CaseChat Overview and Summary
The court examined the evidence presented regarding the service of the payment claims, focusing on whether the claims were effectively delivered personally, during normal office hours, or in accordance with the contractual stipulations. Additionally, the court considered the interpretation of the clause in the construction contract that deemed delivery after 4pm to be effective the following day. The court also had to decide whether this contractual clause was void under section 34 of the Act, which deals with the enforceability of terms that attempt to alter the statutory payment claim process. Furthermore, the court addressed the issue of whether the principal was entitled to specific performance of an obligation to produce steel and shop drawings.
In its reasoning, the court determined that the payment claims were indeed served in a manner that complied with the statutory requirements, despite the discrepancies in the timing of the service. The court held that the term in the construction contract that deemed delivery after 4pm as effective the next day was void under section 34 of the Act. Consequently, the court ruled in favour of MGW Engineering Pty Ltd, holding that the principal was obligated to produce the steel and shop drawings as specified. The court ordered Cmoc Mining Pty Ltd to comply with the terms of the construction contract and provide the necessary drawings within the stipulated timeframe.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.