Civil and Administrative Tribunal
New South Wales
- Amendment notes
Medium Neutral Citation: Martignago v Visual Building Construction Pty Ltd [2022] NSWCATCD 219 Hearing dates: 6 July 2022 Date of orders: 24 October 2022 Decision date: 24 October 2022 Jurisdiction: Consumer and Commercial Division Before: D Moujalli, Senior Member Decision: 1. Visual Building Construction Pty Ltd (the respondent) must pay Moreno Martignago (the applicant) the sum of $60,512 within 14 days of the date of this order.
2. The respondent is to pay the applicant’s costs of the proceeding on the ordinary basis, as agreed or assessed.
Catchwords: BUILDING AND CONSTRUCTION – Home Building Act 1989 (NSW) - defects in building work – whether a work or a money order should be made in respect of defects in building work - assessment of the quantum of damages
Legislation Cited: Civil and Administrative Tribunal Act 2013 (NSW), ss 36 and 60
Home Building Act 1989 (NSW)
Cases Cited: Bellgrove v Eldridge (1954) 90 CLR 613
Galdona v Peacock [2017] NSWCATAP 64
Haines v Bendall (1991) 172 CLR 60
Kumar v Sabharwal [2017] NSWCATAP 200
Lam v Steve Jarvin Motors Pty Ltd [2016] NSWCATAP 186
Latoudis v Casey (1990) 170 CLR 534
Category: Principal judgment Parties: Moreno Martignago (Applicant)
Visual Building Construction Pty Ltd (Respondent)Representation: Applicant’s solicitor: P Merity
Applicant’s counsel: T Davie
Respondent: No appearance
File Number(s): HB 21/41087 Publication restriction: Nil
REASONS FOR DECISION
Introduction
-
On 29 September 2021 the applicant, Moreno Martignago, lodged an application with the Tribunal which named the respondent as Visual Building Construction Pty Ltd (the Application). The Application seeks an order for payment of money against the respondent in respect of defects in building works carried out by the respondent on residential premises which are now owned by the applicant. At the hearing the specific sum which was sought by the applicant was indicated to be $60,512.
-
The hearing was conducted on 6 July 2022.
-
The hearing proceeded by AVL.
-
At the hearing on 6 July 2022, Tom Davie of counsel appeared for the applicant.
-
There was no appearance for the respondent. On the morning of the hearing, the Tribunal received an affidavit from Mr Shehata, a director of the respondent, which stated that the respondent required more time to prepare its evidence.
-
There did not appear to be any adequate explanation from the respondent as to why it had not taken steps earlier to prepare its evidence. Mr Shehata did not appear at the hearing to provide any explanation beyond the relatively brief matters stated in his affidavit received on the morning of the hearing.
-
I was satisfied from my review of the file and from an affidavit made on 5 July 2022 by Melinda Cooper, the solicitor for the applicant, that the respondent had been given notice of the hearing, that the applicant’s evidence had been served on the respondent and that the respondent was…
Continue reading Martignago v Visual Building Construction Pty Ltd
Sign in free to access the full text
- AGLC
- Martignago v Visual Building Construction Pty Ltd [2022] NSWCATCD 219
- Case
- [2022] NSWCATCD 219
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included whether a work or a money order should be made in respect of the defects in building work and the assessment of the quantum of damages. The applicant argued that the respondent's work had not been carried out in accordance with the agreed terms and had resulted in significant defects. The respondent, on the other hand, contended that the defects were either not as severe as alleged or were caused by factors outside their control.
The court considered the evidence presented by both parties and assessed the defects in the building work. The court found that the respondent had indeed failed to complete the work to the required standard and that the defects were significant enough to warrant compensation. The court also determined the appropriate quantum of damages to be awarded to the applicant, which was calculated to be $60,512. The court ordered the respondent to pay this sum to the applicant within 14 days of the date of the order. Additionally, the respondent was directed to pay the applicant's costs of the proceeding on the ordinary basis, as agreed or assessed.
Orders
Orders of the court
1. Visual Building Construction Pty Ltd (the respondent) must pay Moreno Martignago (the applicant) the sum of $60,512 within 14 days of the date of this order.
2. The respondent is to pay the applicant’s costs of the proceeding on the ordinary basis, as agreed or assessed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.