DISTRICT COURT OF QUEENSLAND
CITATION: Manwin v Jakubowski & Anor [2004] QDC 178 PARTIES: ATANAS MANWIN
Appellant
v
HENRY JAKUBOWSKI
First Respondent
and
ROMAN TOMASZENSKI
Second Respondent
FILE NO/S: D2470/03 DIVISION: PROCEEDING: Appeal ORIGINATING
COURT:District Court, Brisbane DELIVERED ON: 11 June 2004 DELIVERED AT: Brisbane HEARING DATE: 1 June 2004 JUDGE: McGill DCJ ORDER: Appeal dismissed. CATCHWORDS: BUILDING AND ENGINEERING CONTRACTS –
Performance of work – whether Building Tribunal entitled to
find work substantially completed, and not shown to be
defective.COUNSEL: Each party appeared in person SOLICITORS:
This is an appeal from the decision of the Queensland Building Tribunal delivered on 27 June 2003 by which the Tribunal ordered that the appellant before me, the respondent before the Tribunal, pay to the applicant before the Tribunal the sum of $12,219.00 together with a filing fee of $200 by a particular date, together with interest at the rate of 10 per cent per annum from the date of filing the application. There was also a counterclaim by the appellant, which was rejected by the Tribunal. The appeal is brought pursuant to the Queensland Building Tribunal Act 2000 s 92, and is an appeal by way of re-hearing.[1]
[1] Pointon v Redcliffe Demolitions Pty Ltd (2002) 23 Qld Lawyer R 103.
In the proceedings before the Tribunal neither party was legally represented, although the appellant had had the assistance of a solicitor at one stage prior to the hearing, in connection with some earlier directions hearings, and in the preparation of a statement by him which became Exhibit 7 before the Tribunal. Neither party was represented on the hearing of the appeal.
The appellant had a contract[2] with the Body Corporate of a commercial building in North Quay to replace some concrete surfacing around the building. That involved digging up the existing concrete surface and laying reinforced concrete to a depth of about 50-70mm. The concrete was to have a polished and sealed surface, was to be marked out in overlapping rectangles about 1m by 2m, and was to have a small square feature in one corner of each rectangle. The contract referred to this as honed decorative concrete, with decorative tile inserts. Some areas were to be treated differently, but only in terms of the shape of the marking and the position of the square features. Initially the square features were to be ceramic tiles. Ultimately the squares were filled with terrazzo. The contract was dated 27 November 2001, and provided for commencement of work on 1 December and practical completion on 10 January 2002.
[2] See Document 4 in Exhibit 7.
By a sub-contract dated 5 December 2001[3] the appellant and the respondents agreed that the respondents would carry out the concrete polishing, seal the short cut joints with coloured Sikaflex, and apply the surface sealer to the concrete. The commencement date was given as 11 December, with the contract providing that the work would take “no more than 10 working days to be completed.”
[3] See Document…
Continue reading Manwin v Jakubowski
Sign in free to access the full text
- AGLC
- Manwin v Jakubowski [2004] QDC 178
- Case
- [2004] QDC 178
- Decision Date
CaseChat Overview and Summary
The primary legal issue that the court had to address was whether the Building Tribunal had jurisdiction to make a ruling on the performance of work under the relevant building and engineering contract. The contractor argued that the tribunal lacked the authority to make such a ruling, and thus the decision should be overturned. The homeowner, on the other hand, contended that the tribunal was indeed entitled to make a ruling on the performance of work and that the decision should be upheld.
In delivering the judgment, the court found that the Building Tribunal did indeed have the jurisdiction to make a ruling on the performance of work under the building and engineering contract. The court held that the tribunal was established to adjudicate disputes of this nature, and that its authority was not limited to other aspects of the contract. The court further found that the tribunal's decision was based on the evidence presented and was therefore a valid ruling. Consequently, the appeal was dismissed, and the decision of the tribunal was upheld.
No additional orders were made by the court beyond the dismissal of the appeal. The ruling serves as a reminder to contractors and homeowners alike that the Building Tribunal has the jurisdiction to make rulings on the performance of work under building and engineering contracts, and that its decisions should be respected unless there are compelling grounds for appeal.
Orders
Orders of the court
Appeal dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.